BLD-Final | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sarah Schuller
|
DOC - Permit Finaled | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | FAIL |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Sarah Schuller Need Electrical final first. then call for bldg. final.
|
Issue PAID IN FULL permit | | | 9/27/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
met
|
Plan assigned to (JAB) Josh | 8/24/2018 | 8/24/2018 | 9/25/2018 | | PASS |
Josh Bogle
|
|
|
08/30 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 9/25/2018 | | 9/25/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2018 | | DONE |
|
|
|
ESC no - Energy no
|
Routing - PLAN CHECK | 9/18/2018 | | 9/18/2018 | | FAIL |
Josh Bogle
|
|
|
engineering not to 25lb snow load
|
Routing - PLAN CHECK | 9/10/2018 | | 9/10/2018 | | FAIL |
Josh Bogle
|
|
|
engineering doesn't explicitly note that this is for a manufactured home
|
Routing - PLAN CHECK | 9/6/2018 | | 9/6/2018 | | FAIL |
Josh Bogle
|
|
|
innadequate sonw loads in engineering
|
1st review completed | | | 8/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/24/2018 | | 8/27/2018 | | FAIL |
Josh Bogle
|
|
|
need engineering for install on manufactured home
|
Routing - PLANNING | 8/24/2018 | | 8/24/2018 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/24/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2018 | | DONE |
|
|
|
|
Application received | | | 8/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2018 12:20AM
|