BLD-Final | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PASS |
Mike Jordan
|
|
|
Fire re-inspect to be completed early AM Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
FIRE-Final Inspection | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 11/30/2018 | 12/3/2018 | 12/3/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
FIRE-Final Inspection | 11/30/2018 | 12/3/2018 | 12/3/2018 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the fire alarm issue is resolved for the overspace stobe on the ground level south/east corner.
Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
|
BLD-Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | P | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Ryan Wilhelm Inspection cancelled from web by: Ryan Wilhelm
|
BLD-Framing/Rough-in | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####. 2nd floor infill ok.
|
Permit Ready to Issue | | | 10/5/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/5/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/5/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (REV) | | | 10/4/2018 | | DONE |
|
|
|
Occupant loads need to be added.
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
Need
ACHD - met
GC Form - met
Revised Cert of Value - met
|
Plan assigned to (JHB) | 8/22/2018 | 8/22/2018 | 9/25/2018 | | PASS |
Joe Bruce
|
|
|
(1st / 2nd / 3rd Rev Comp) - 09/07 (L2) - Wing Center ePlan
|
Routing - PLAN CHECK | 9/25/2018 | | 9/25/2018 | | PASS |
Joe Bruce
|
|
|
Signed off by Carl M
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/19/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 9/19/2018 | | 9/19/2018 | | FAIL |
Joe Bruce
|
|
|
(3rd Rev Comp) - Provide structural calculations for the entire load path.
|
Plan resubmittals requested | | | 9/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/14/2018 | | 9/17/2018 | | FAIL |
Joe Bruce
|
|
|
(2nd Rev Comp) - Provide structural engineering & calculations for mezzanine.
|
Plan resubmittals requested | | | 9/17/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/14/2018 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 9/11/2018 | 9/14/2018 | 9/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 9/11/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/29/2018 | 8/29/2018 | 9/10/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 9/10/2018 | | FAIL |
Joe Bruce
|
|
|
(1st Rev Comp)
|
Routing - PLAN CHECK | 8/21/2018 | | 8/29/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan assigned to (JG) | 8/21/2018 | 8/21/2018 | 8/22/2018 | | DEFR |
Javier Guzman
|
|
|
8/27 L1 Wing Center ePlan
|
Routing - PUBLIC WORKS | 8/21/2018 | | 8/21/2018 | | PASS |
Rachael Beierle
|
|
|
|
Intake Approval | | | 8/21/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 8/21/2018 | | 8/21/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 8/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2018 5:08AM
|