Permit Information
Permit NumberBLD18-03003
StatusIssued
Name WALLACE RENOVATIONS
Site Address 405 E LOGAN ST
Project NameHerman addition
Customer Number 
ePlanReviewNo
Description
Permit for a two story addition (320sq' up/199sq' down) that includes an expanded Family room and new 67sq' covered deck on the main level and a new Master Suite on the 2nd level. All work per plans, notations, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/6/20195/6/20195/6/2019PPASS
DetailsDave Hannah
Manny Phone #: ###-####
Zoning Approval5/1/20195/1/20195/1/2019 DONE
DetailsTed Vanegas
Zoning Approval4/19/20194/19/20194/19/2019 FAIL
DetailsTed Vanegas
Per DRH18-00233. Balcony railing is not complete; minor window changes that do not match approved plans.
BLD-Energy code compliance12/3/201812/3/201812/3/2018PPASS
DetailsDave Hannah
Manny Phone #: ###-####
BLD-Energy code compliance11/30/201811/30/201811/30/2018PPART
DetailsDave Hannah
Manny-whole upper half of bldg-if have call Manny Phone #: ###-#### ok to cover up stairs
BLD-Framing/Rough-in11/27/201811/27/201811/27/2018PPASS
DetailsDave Hannah
Manny Phone #: ###-####
BLD-Wall Bracing10/4/201810/4/201810/4/2018PPASS
DetailsBrandon Shaw
Manny Phone #: ###-####
BLD-Footing8/28/20188/28/20188/28/2018PPASS
DetailsDave Hannah
JR Phone #: ###-####
OVERRIDE  8/27/2018  
Plan assigned to (JAB) Josh8/22/20188/22/20188/27/2018 PASS
DetailsJosh Bogle
08/28 remodel, paper
Inspection Record Card- Bld  8/27/2018 DONE
DetailsJosh Bogle
Case Summary (BLD)  8/27/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  8/27/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  8/27/2018 DONE
need
RP (Jeff Wallace states hes took the class March/April, could not find his name)
Telephone call  8/27/2018 DONE
Spoke with Jeff to inform him the permit is ready, what fees are due and RP is needed.
Issue PAID IN FULL permit  8/27/2018 DONE
Routing - PLAN CHECK8/24/2018 8/27/2018 PASS
DetailsJosh Bogle
Routing - MECHANICAL8/22/2018 8/24/2018 PASS
DetailsTroy James
Routing Walk-In (BLD)8/22/20188/22/20188/22/2018PPASS
DetailsJosh Bogle
took in and routed
Routing PW Flood Plain8/22/2018 8/22/2018 PASS
DetailsJason C. Taylor
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
Routing - PLANNING8/22/2018 8/22/2018 PASS
DetailsNicki Heckenlively
Routing Walk-In (BLD)8/20/20188/20/20188/20/2018AFAIL
DetailsJosh Bogle
Routing - PLAN CHECK8/20/2018 8/20/2018 FAIL
DetailsJosh Bogle
Floodplain - needs elevation cert. - may need to run through the #112 process - e-mail out to JCT
1st review completed  8/20/2018 FAIL
DetailsJosh Bogle
Application received 8/20/2018