(F) Reprint permit | | | 2/20/2019 | | DONE |
|
|
|
|
Meeting | | | 2/20/2019 | | DONE |
|
|
|
homeowner had permit transferred over to new GC Oconnor Building Supply. Dreamweavers is no longer working on project. see letter in documents
|
BLD-Energy code compliance | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 10/23/2018 | 10/24/2018 | 10/25/2018 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Footing | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-#### Footings and Wall.....OK
|
OVERRIDE | | | 8/24/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 8/24/2018 | 8/24/2018 | 8/24/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/24/2018 | | 8/24/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/24/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/24/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 8/24/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/24/2018 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 8/20/2018 | 8/20/2018 | 8/20/2018 | A | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 8/20/2018 | 8/20/2018 | 8/20/2018 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/20/2018 | | 8/20/2018 | | FAIL |
Josh Bogle
|
|
|
inncorrect structural plans
|
1st review completed | | | 8/20/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 8/20/2018 | | | |
|
|
|
|