Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-03023
StatusFinaled
Name ENVIROSPARK ENERGY SOLUTIONS INC
Site Address 8300 W OVERLAND RD
Project NameWalmart elec vehicle charging
Customer Number 
ePlanReviewYes
Description
(WALMART - ELECTRIC VEHICLE CHARGING STATIONS) Permit for the installation of (4) electric vehicle charging stations, equipment yard with (6) power units and switchboard assembly, fencing with (2) gates, parking signage and landscaping. Approval is contingent upon adhering to the approved plans and engineering. This project is classified as a U occupancy. There are no accessibility requirements for U occupancies. Accessible parking is provided elsewhere in the same parking lot. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 5/11/20196/7/2019 DONE
mailed 6-10
Second Notice 4/18/20195/6/2019 DONE
mailed 5-10-19
First Notice3/25/20193/25/20194/8/2019 DONE
DetailsMike Jordan
mailed 4-11-19
BLD-Final3/22/20193/25/20193/25/2019PPASS
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
DOC - Permit Finaled3/25/20193/25/20193/25/2019PPASS
DetailsMike Jordan
BLD-Final3/20/20193/21/20193/21/2019PNR
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez. Needs electrical final.
FIRE-Final Inspection3/20/20193/21/20193/21/2019ACANC
DetailsTroy Cobbley
No life safety, fire alarm or fire sprinkler sign off required per the permit details.

Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
Zoning Approval3/4/20193/4/20193/4/2019 PASS
DetailsKayCee Babb
Per DRH18-00294
Zoning Approval2/8/20192/8/20192/12/2019 FAIL
DetailsKayCee Babb
Trellis requires installation prior to sign-off.
BLD-Concrete1/26/20191/28/20191/28/2019PPART
DetailsMike Jordan
Call prior to going Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez. rebar for slab.
BLD-Concrete1/24/20191/25/20191/25/2019APART
DetailsMike Jordan
As early as possible Phone #: 6027037603 >> Inspection requested via mobile web by Matthew Jimenez
Inspection Record Card- Bld  1/8/2019 DONE
Issue PAID IN FULL permit  1/8/2019 DONE
OVERRIDE  10/5/2018  
PLANS/APPL TAKEN TO FRONT DESK  10/5/2018 DONE
DetailsMichael Hanson
Permit Ready to Issue  10/5/2018 DONE
all met--NEED
ACHD-met
RP-met
GC FORM-met
REVISED VALUE-met
emailed fees due to Breanne
Plan assigned to (M_H)9/1/2018 10/5/2018 DONE
DetailsMichael Hanson
10/02 #502 L1 ePlan. 1st review completed - Pending fire review. MDH
Route to Impact Fee Review10/2/201810/5/201810/3/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE9/1/20189/1/201810/3/2018 PASS
DetailsErika Akin
No comments attached. Electric charging station in existing parking lot for Walmart. No structure. No impact to exisitng FD access.
Routing - Addressing9/1/2018 10/2/2018 PASS
DetailsDoug Chausow
Per ePlan approval. MDH
1st review completed  10/2/2018 DONE
DetailsMichael Hanson
Routing - PLAN CHECK9/1/2018 10/2/2018 PASS
DetailsMichael Hanson
Routing - PLANNING9/1/2018 9/4/2018 PASS
DetailsKayCee Babb
Routing - Design Review9/1/2018 9/4/2018 PASS
DetailsKayCee Babb
per DRH18-00294
Routing - PUBLIC WORKS9/1/2018 9/4/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment9/1/2018 9/4/2018 PASS
DetailsMichael Zawacki
Waiver approved, RP needed
Routing PW Drainage9/4/2018 9/4/2018 PASS
DetailsBrian Murphy
Intake Approval  8/29/2018 PASS
Intake Approval  8/24/2018 FAIL
DetailsJoe Bruce
To complete your application, provide the following:
1. Upload planning & zoning letter(s) of approval.
2. Plans must be drawn on a minimum 18" x 24" size sheet. The plans submitted are on an 11" x 17" sheet size. (see page 2 of checklist)
3. Provide site specific fire flow at hydrants letter from Suez Water or other public water provider.
4. Box on page 3 of application was not checked regarding the "Permanent Operation & Maintenance Agreement form."

Thank you,
Joe Bruce
Application received  8/20/2018 DONE
Application submitted via PDS Online on Aug 20 2018 4:26PM