Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-03039
StatusFinaled
Name IDAHO TOWER CONSTRUCTION CO
Site Address 720 E PARK BLVD
Project NameAT&T
Customer Number 
ePlanReviewYes
Description
(AT&T - BOISE EAST) Permit for the modifications to the existing cellular roof top penthouse wall antenna mount assembly with work to include removal of (3) SBNHH-1D65C antennas, removal of (3) RRH2X40W-07L RRHs, adding (3) Kathrein 800-10992K antennas, adding (3) airscale RRH 4T4R B5 160W AHCA RRHs, adding (3) airscale dual RRH 4T4R B12/14 320W AHLBA RRHs, @ the existing equipment platform adding (3) 50A, 1-pole, -48VDC breakers for the (p) airscale dual RRH 4T4R B12/14 320W AHLBA RRHs, adding (3) 25A, 1-pole, -48VDC breakers for the (p) airscale RRH 4T4R B5 160W AHCA RRHs. Structural engineering and plans provided. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/20/20198/20/20198/20/2019APASS
DetailsDave Hannah
DOC - Permit Finaled8/20/20198/20/20198/20/2019PPASS
DetailsDave Hannah
BLD-Aging Inspection8/16/20198/16/20198/20/2019 PEND
DetailsDave Hannah
Plan assigned to (JG)9/10/20189/10/201810/1/2018 PASS
DetailsJavier Guzman
1st rev comp, 9/21 L2 ATT Antenna ePlan, pend DR
Routing - PLAN CHECK9/29/2018 10/1/2018 PASS
DetailsJavier Guzman
Routing - Design Review9/29/2018 10/1/2018 PASS
DetailsKayCee Babb
Due to low visual impact, DR manager has approved project without Design Review being required.
PLANS/APPL TAKEN TO FRONT DESK  10/1/2018 DONE
Permit Ready to Issue  10/1/2018 DONE
Need - all met 10/1/18 C_P
GC Form
Revised Cert of Value

email to Lorelei - lforonda@md7.com
Issue PAID IN FULL permit  10/1/2018 DONE
Inspection Record Card- Bld  10/1/2018 DONE
Routing - Design Review9/26/2018 9/26/2018 PASS
DetailsKayCee Babb
Alteration does not cause significant visual changes and does not require DR approval, per Design Review Manager.
Route to Impact Fee Review9/19/20189/22/20189/20/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  9/19/2018 DONE
DetailsJavier Guzman
Routing - PLAN CHECK9/10/2018 9/19/2018 FAIL
DetailsJavier Guzman
Routing - PLANNING9/10/2018 9/11/2018 PASS
DetailsNicolette Womack
Routing - Design Review9/10/2018 9/11/2018 FAIL
DetailsKayCee Babb
Design Review required for proposed project due to exterior alterations and addition of antennas.
Intake Approval  9/10/2018 PASS
DetailsJavier Guzman
Intake Approval  9/5/2018 FAIL
DetailsBrian McGowan
1. Engineering must be updated to current Boise City Codes. See Sheet 1 of the SSOE documents under Analysis Criteria. This is the Engineering in the Document Folder. Analysis Criteria must be done under the 2015 IBC, not the 2012 IBC.
Intake Approval  8/29/2018 FAIL
DetailsBrian McGowan
Please correct the following items :
1. Engineering must be updated to current Boise City Codes. See Sheet 1 of the SSOE documents under Analysis Criteria.
2. The sheets uploaded should be named exactly as the sheet it is replacing so it will "Version" over, replace, that sheet as V2.
3. Several sheets are numbered the same ( A0.4, A0.5....) They should be numbered differently. You can use the actual sheet number if you wish with a description behind it (E-101 RF Plumbing Diagrams for example). I can delete files you specify once it comes back to me if needed.
Intake Approval  8/22/2018 FAIL
DetailsBrian McGowan
Please correct the following items :
1. Add the Page numbers where the items can be located on the submittal checklist.
2. Code Analysis needs to be updated to current Boise City Codes.
3. Verify the site address- Address on the application is for E. Park Boulevard. The Site Plan and Vicinity map show W. Caesar Chavez Lane. Update plans to match.
4. Site Plan needs to show building, Streets and location on the property (see checklist).
5. Engineering must be updated to current Boise City Codes.
Application received  8/21/2018 DONE
Application submitted via PDS Online on Aug 21 2018 2:42PM
First Notice8/20/20198/20/2019   
DetailsDave Hannah