Print Statement | | | 11/27/2019 | | DONE |
|
|
|
1ST NOTICE
|
Print Statement | | | 11/6/2019 | | DONE |
|
|
|
|
Second Notice | | 8/15/2019 | 9/20/2019 | | DONE |
|
|
|
mailed 9-23-19
|
First Notice | | 7/25/2019 | 8/5/2019 | | DONE |
|
|
|
mailed 8-6-19
|
Permanent Occupancy | | | 7/15/2019 | | DONE |
|
|
|
|
BLD-Final | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
Zoning Approval | 6/17/2019 | 6/17/2019 | 6/17/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Telephone call | | | 6/17/2019 | | DONE |
|
|
|
Matt emailed in the temp
C of O sign off card but the building final had not been done so i emailed him back and told him once the building final inspection wasa requested and passed he can email the sign off card back in to permits@cityofboise.org
|
Temporary Occupancy | 6/7/2019 | 9/5/2019 | 6/7/2019 | | DONE |
Judith Amador
|
|
|
|
PubWorks Occupancy Approval | 6/7/2019 | 6/7/2019 | 6/7/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval Temp | 6/7/2019 | 6/7/2019 | 6/7/2019 | | PASS |
Katelyn Menuge
|
|
|
Will finalize landscape by 6-12-19. All plant materials on site.
|
BLD-Final | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PART |
Tony Young
|
|
|
for Temp CO Phone #: ###-#### Inspection requested via web by Josh Strasser,, temp. occupancy ok
|
FIRE-Final Inspection | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags, addressing will be installed when received. Final life fire safety inspection complete.
Josh Phone #: ###-####
|
BLD-Wall cover | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PASS |
Jim Sly
|
|
|
Anchor bolts (2) installed Beam to wall has strap ontop of wall and beam Shear locations (2) nailed Phone #: ###-#### Inspection requested via web by Josh Strasser all Framing.....OK.
|
BLD-Framing/Rough-in | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok to insulate pending trades
|
BLD-Wall Bracing | 4/5/2019 | 4/5/2019 | 4/5/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser,, exterior ok
|
BLD-Concrete | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Tony Young
|
|
|
Concrete pour is at 11:00 AM Phone #: ###-#### Inspection requested via web by Josh Strasser,, slab work,, SI report
|
BLD-Foundation | 2/5/2019 | 2/8/2019 | 2/8/2019 | A | PART |
Tony Young
|
|
|
Concrete scheduled for 12:30 PM Phone #: ###-#### Inspection requested via web by Josh Strasser,, ok pending special inspection report
|
BLD-Footing | 2/5/2019 | 2/8/2019 | 2/8/2019 | A | PEND |
Tony Young
|
|
|
This was poured and inspected by All West Inspections Phone #: ###-#### Inspection requested via web by Josh Strasser,, pending special inspection report
|
Print Occupancy Form | | | 1/18/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/28/2018 | | DONE |
|
|
|
emailed Jeff LIkes the permits to be signed-JSTRASSER@WBTBC.COM wanted them so also emailed them to him for signatures
|
Print Occupancy Form | | | 11/28/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/7/2018 | | |
|
|
|
|
OVERRIDE | | | 11/7/2018 | | |
|
|
|
|
Plan assigned to (JG) | 8/29/2018 | 8/29/2018 | 11/7/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 09/28 Einsteins Oilery
|
CHANGE STATUS TO (FEE) | | | 11/7/2018 | | DONE |
|
|
|
changed out of ready status until changemarks resolved and batch stamp is complete
|
Permit Ready to Issue | | | 11/7/2018 | | DONE |
|
|
|
ALL MET-NEED
ACHD
RP
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 11/6/2018 | | 11/7/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2018 | | DONE |
|
|
|
MET JSTRASSER@WBTBC.COM
Need
GC Form
Revised Cert of Value
MET
RP
ACHD
|
Routing - PLAN CHECK | 11/1/2018 | | 11/5/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Design Review | 11/1/2018 | | 11/1/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing PW Sewer Design | 11/1/2018 | | 11/1/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLAN CHECK | 10/18/2018 | | 10/24/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 10/18/2018 | | 10/24/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF Cory Harelson
|
Routing PW Sewer Design | 10/18/2018 | | 10/24/2018 | | FAIL |
DeAnn Brown
|
|
|
Changemarks from first review were not addressed. Please refer to changemarks in eplanreview for corrections required.
|
Routing - PUBLIC WORKS | 10/24/2018 | | 10/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 10/18/2018 | | 10/18/2018 | | FAIL |
Katelyn Menuge
|
|
|
Bike racks cannot obstruct pedestrian path.
|
Route to Impact Fee Review | 10/9/2018 | 10/12/2018 | 10/11/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/29/2018 | 8/29/2018 | 10/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/29/2018 | | 10/2/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 8/29/2018 | | 9/21/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF Cory Harelson
|
Routing PW Environmental | 8/29/2018 | | 9/6/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Design | 8/29/2018 | | 9/5/2018 | | FAIL |
DeAnn Brown
|
|
|
Update demolition plan and utility plan per PW Sewer changemarks in eplanreview.
|
Routing PW Street Lights | 8/29/2018 | | 9/5/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 8/29/2018 | | 9/5/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - MECHANICAL | 8/29/2018 | | 9/4/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/29/2018 | | 9/4/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 8/29/2018 | | 8/30/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2018 | | 8/30/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 8/29/2018 | | 8/30/2018 | | FAIL |
Katelyn Menuge
|
|
|
DRH18-00091 See changemarks for required modifications to site, landscape, lighting.
|
Routing PW Solid Waste | 8/29/2018 | | 8/30/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Erosion and Sediment | 8/29/2018 | | 8/29/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed prior to any site work relating to new building.
ESC has been issued for demo ESC18-01064 for daystar excavation and demolition work.
|
Routing - PLANNING | 8/29/2018 | | 8/29/2018 | | PASS |
Nicolette Womack
|
|
|
Work with Design Review regarding planter widths.
|
Intake Approval | | | 8/27/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/22/2018 | | FAIL |
Brian McGowan
|
|
|
Please provide the following information for your prescreen to be approved:
1. Form #310 must be completely filled out.
2. Show the location of fire hydrants on the Site Plan. Or indicate how far from the proposed site they are located.
3. Your Drainage Plan is proposing a seepage pit. Please provide a completed "Shallow Injection Well Inventory" form.
4. Hazardous Material Inventory and Classification Report. Provide quantities and types of hazardous materials to be used/stored on site.
5. Please show Accessibility clearances on the floor plan.
6. No Sheet E3.2 was provided.
|
Application received | | | 8/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 21 2018 3:25PM
|