Letter of compliance/Occupancy | | | 4/25/2019 | | DONE |
|
|
|
|
BLD-Final | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
DOC - Permit Finaled | 3/15/2019 | 3/15/2019 | 3/15/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Other | 1/11/2019 | 1/14/2019 | 1/14/2019 | A | CANC |
Jim Storey
|
|
|
Mike-soffits Phone #: ###-####
|
BLD-Other | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | CANC |
Jim Storey
|
|
|
Fire Rated Soffit Inspection Phone #: ###-#### >> Inspection requested via web by Mike Cook
|
BLD-Energy code compliance | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Storey
|
|
|
Rusty Phone #: ###-####
|
BLD-Framing/Rough-in | 1/2/2019 | 1/2/2019 | 1/2/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Mike Cook
|
BLD-Footing | 10/10/2018 | 10/10/2018 | 10/10/2018 | P | PASS |
Jim Storey
|
|
|
Derik Phone #: ###-####
|
BLD-Footing | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | NR |
Jim Storey
|
|
|
Derik Phone #: ###-####
|
OVERRIDE | | | 9/26/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 8/23/2018 | 8/23/2018 | 9/26/2018 | | DONE |
Rob Patrick
|
|
|
09/04 sfd L1 ePlan...9/5 Failed: Wall Bracing, Stairs, Smoke Detectors
|
Issue PAID IN FULL permit | | | 9/26/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/26/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 9/26/2018 | | 9/26/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 9/26/2018 | | 9/26/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/26/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 9/26/2018 | | DONE |
|
|
|
met
|
1st review completed | | | 9/5/2018 | | FAIL |
Rob Patrick
|
|
|
Wall Bracing, Stairs, Smoke Detectors
|
Routing - PLAN CHECK | 8/23/2018 | | 9/5/2018 | | FAIL |
Rob Patrick
|
|
|
Wall Bracing, Stairs, Smoke Detectors
|
Route to Impact Fee Review | 8/23/2018 | 8/26/2018 | 8/24/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/23/2018 | | 8/23/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/23/2018 | | 8/23/2018 | | FAIL |
Katelyn Menuge
|
|
|
Need garage width minimum of 19 feet.
|
Routing - Addressing | 8/23/2018 | | 8/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/23/2018 | | 8/23/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/23/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/23/2018 | | PASS |
Brittany Hill
|
|
|
|
Intake Approval | | | 8/22/2018 | | FAIL |
Christina Prado
|
|
|
Need to show stairways on all levels, currently not shown on upper level, need detailed stair section
|
Application received | | | 8/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 21 2018 5:30PM
|