Permit NumberBLD18-03068
StatusFinaled
Name K & A LANDSCAPE
Site Address 1407 E HOLLY ST
Project NameBaun-Holly
Customer NumberBLD14-02714 DEMO CFH18-00090
ePlanReviewYes
Description
**FLOODPLAIN** **PRESCRIPTIVE ENERGY REQUIREMENTS** previous home Demo'd- Permit for the construction of a new 2941 sq. ft., two story (first story 1528 sq. ft., second story 1413 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 525 sq. ft. of covered patio/porch and a 950 sq. ft. attached garage per the approved plans and any notations. ****** zoning and setbacks per planning. NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor 208-608-7171
JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/10/20197/11/20197/11/2019APASS
DetailsBrandon Shaw
Ethan Phone #: ###-####
DOC - Permit Finaled7/11/20197/11/20197/11/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results7/11/20197/11/20197/11/2019ADONE
DetailsBrandon Shaw
ACH 50- 3.5
PubWorks Occupancy Approval7/9/20197/9/20197/9/2019 DONE
DetailsJason C. Taylor
Recieved all floodplain requirements. JCT
Elevation Cert Rec'd-Final  7/9/2019 DONE
Recieved Final Elevation Certificate. JCT
BLD-Energy code compliance4/12/20194/12/20194/12/2019PPASS
DetailsDave Hannah
Nate Phone #: ###-####
BLD-Framing/Rough-in4/9/20194/10/20194/10/2019APART
DetailsDave Hannah
Nate Phone #: ###-#### ok to insulate but needs to fire block fur downs and fur outsand above fire place
Elevation Cert Rec'd-Midconst  4/9/2019 DONE
Recieved EC #2. Framing inspection may be scheduled. JCT
Routing PW Flood Plain4/9/2019 4/9/2019 PASS
DetailsJason C. Taylor
Recieved EC #2
BLD-Framing/Rough-in4/8/20194/9/20194/8/2019ACANC
DetailsDave Hannah
Nate Phone #: ###-####
Nate cancel this inspection, needs more time to be make it ready.
BLD-Framing/Rough-in4/3/20194/4/20194/5/2019PNR
DetailsDave Hannah
Nate Phone #: ###-#### needs flood plan cert
BLD-Wall Bracing3/13/20193/14/20193/14/2019APART
DetailsDave Hannah
Cory Phone #: ###-#### second floor ok ground floor ok but needs to nail type3 install holddowns and floor to floor stapes
BLD-Foundation1/2/20191/3/20191/3/2019PPASS
DetailsDave Hannah
Willy Phone #: ###-####
BLD-Footing12/28/201812/31/201812/31/2018APASS
DetailsDave Hannah
Willie Phone #: ###-#### footing are covered and heaters running ok to place concrete
BLD-Footing12/27/201812/28/201812/28/2018AFAIL
DetailsDave Hannah
Willie Phone #: ###-#### ground is frozen
BLD-Foundation12/7/201812/7/201812/10/2018PPART
DetailsDave Hannah
wall // Sergio Phone #: ###-#### crew will cover and heat
BLD-Footing11/21/201811/21/201811/21/2018PPART
DetailsBrandon Shaw
Retaining walls...
Issue PAID IN FULL permit  11/5/2018 DONE
OVERRIDE  11/1/2018  
Plan assigned to (J_N)10/5/201810/5/201811/1/2018 DONE
DetailsJenny Nelson
10/18 sfd L1 ePlan. 1st review done 10/18, 2nd story wall bracing plan, code year, engineering for steel beams and columns
Routing - PLAN CHECK11/1/2018 11/1/2018 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  11/1/2018 DONE
DetailsJenny Nelson
Permit Ready to Issue  11/1/2018 DONE
NEED RP
1st review completed  10/18/2018 FAIL
DetailsJenny Nelson
2nd story wall bracing plan, code year, engineering for steel beams and columns
Routing - PLAN CHECK10/5/2018 10/18/2018 FAIL
DetailsJenny Nelson
Routing PW Flood Plain10/8/2018 10/11/2018 PASS
DetailsJason C. Taylor
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
Route to Impact Fee Review10/5/201810/8/201810/8/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Addressing10/5/2018 10/8/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/5/2018 10/8/2018 PASS
DetailsMorgan Webb
Routing - MECHANICAL10/5/2018 10/8/2018 PASS
DetailsTroy James

Routing - PLANNING10/5/2018 10/5/2018 PASS
DetailsBrent Moore
Plans ACCEPTED BY PLAN TECH  10/5/2018 DONE
Intake Approval  10/5/2018 PASS
Recd Pcfee & Taken To Pln CK  10/5/2018 DONE
Intake Approval  10/2/2018 FAIL
nothing has changed-still need CFH permit to pass
Intake Approval  9/25/2018 FAIL
still need approval letter for CFH18-00090. As of today it still shows FAILED
Intake Approval  9/13/2018 FAIL
CFH18-00090 failed intake-need approval letter for floodplain in the docs before we can approve intake
Intake Approval  9/5/2018 FAIL
CFH18-00090 (floodplain development application) must be approved and approval letter uploaded to documents folder prior to acceptance of building permit application.
Intake Approval  9/4/2018 FAIL
all code years need to be 2015 IRC, drawing file names (A1.0 Floor plan) and need elevation cert for floodplain.
Application received  8/23/2018 DONE
Application submitted via PDS Online on Aug 23 2018 8:28AM
Intake Approval  8/23/2018 FAIL
need prescrip or res check-plans are drawn to the wrong code