Permit Information
Permit NumberBLD18-03121
StatusFinaled
Name BILTMORE COMPANY
Site Address 11783 W KING ST
Project NameFairview Apartments - Bldg 2
Customer Number 
ePlanReviewYes
Description
(FAIRVIEW APARTMENTS) (BLDG 2) (DRH17-00532) (GRD18-00035) Permit for the construction of Building 2, a 27,059 sq ft, 3-story, 24-unit apartment building. This building is one of six buildings within a multi-family development, which includes (3) three-story, 24-unit multi-family buildings and (3) two-story, 8-unit buildings for a total of 96 units on the site. Work to include general site work and the construction of the new building per the approved plans. Special Inspections required per attached Form 310. All buildings are to be fully fire sprinklered with an NFPA 13-R system as required for residential occupancy and story increase. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/16/201910/16/201910/16/2019PPASS
DetailsTell Riley
PAT Phone #: ###-####//all trades finals complete//signatures required complete//final complete//
Permanent Occupancy  10/16/2019 DONE
BLD-Final10/14/201910/15/201910/15/2019PCANC
DetailsTell Riley
Pat Phone #: ###-####
PubWorks Occupancy Approval10/14/201910/14/201910/14/2019 DONE
DetailsTiffany Lowery
BLD-Footing10/8/201910/9/201910/9/2019ACANC
DetailsTell Riley
Matt Phone #: ###-####
BLD-Final10/8/201910/8/201910/8/2019PPASS
DetailsTell Riley
Matt Phone #: ###-####//last six units complete//temp occupancy approved for entire building//final can be complete once all signatures are complete//
FIRE-Final Inspection10/7/201910/8/201910/8/2019APASS
DetailsTroy Cobbley
life safety passed

Matt Phone #: ###-####
BLD-Final10/2/201910/2/201910/2/2019PCANC
DetailsTell Riley
Matt Phone #: ###-####//cancel per Matt//
FIRE-Final Inspection10/2/201910/2/201910/2/2019PFAIL
DetailsTroy Cobbley
Apartment 201 needs the ceiling patched in several locations and the smoke alarm re-mounted. Apartment 301 sprinkler pendant is missing canopy.

Matt Phone #: ###-####
BLD-Final9/30/201910/1/201910/1/2019PPART
DetailsTell Riley
Matt Phone #: ###-####//103,104,203,204,303,304/// finals complete on these units//
FIRE-Final Inspection9/30/201910/1/201910/1/2019APART
DetailsTroy Cobbley
Life safety complete for apartments 103, 104, 203, 204, 303 and 304. Matt Phone #: ###-####
FIRE-Final Inspection9/25/20199/26/20199/26/2019ACANC
DetailsTroy Cobbley
Matt Phone #: ###-#### cancel per matt
BLD-Final9/25/20199/26/20199/26/2019PCANC
DetailsTell Riley
Matt Phone #: ###-#### cancel per matt
BLD-Final9/23/20199/24/20199/24/2019APART
DetailsTell Riley
Matt Phone #: ###-####//units 105,106,205,206,305,306 are ok to occupy when door springs have been adjusted//
FIRE-Final Inspection9/23/20199/23/20199/23/2019PCANC
DetailsTroy Cobbley
The rooms needing inspection have been looked at by me last week. Matt Phone #: ###-####
FIRE-Final Inspection9/19/20199/19/20199/19/2019PPART
DetailsTroy Cobbley
Life safety passed for apartments 105, 106, 205, 206, 305, 306. Matt Phone #: ###-####
Temporary Occupancy9/18/201912/17/20199/18/2019 DONE
DetailsBrittany Hill
PubWorks Occupancy Approval9/18/20199/18/20199/18/2019 PART
DetailsBrittany Hill
card was signed by brian murphy
BLD-Final9/16/20199/17/20199/17/2019APART
DetailsTell Riley
Pat-1st 6 units Phone #: ###-####//north 6 units//final complete pending fire//
Zoning Approval9/13/20199/13/20199/13/2019 PASS
DetailsJosh Wilson
FIRE-Final Inspection9/5/20199/5/20199/5/2019PPART
DetailsTroy Cobbley
The six apartments, 1st through 3rd floors at the very north end of this building have the life safety passed. The FDC needs the required clearance as discussed prior to a final inspection. Matt Phone #: ###-####
FIRE-Final Inspection9/3/20199/4/20199/4/2019ACANC
DetailsTroy Cobbley
Life safety will be a pass for the north most apartments when the project related fire alarm and fire sprinkler permits are passed. Matt- mid mornign Phone #: ###-####
BLD-Energy code compliance7/29/20197/30/20197/30/2019PPASS
DetailsTell Riley
Matt Phone #: ###-####//ok to cover units101,102,201,202,301,302, all units passed//
BLD-Framing/Rough-in7/25/20197/26/20197/26/2019APASS
DetailsTell Riley
Matt Phone #: ###-####//framinng corrections onsite//ok to insulate only// 101,102,201,202,301,303//
BLD-Energy code compliance7/19/20197/22/20197/22/2019APASS
DetailsTell Riley
Matt Phone #: ###-####//corrections made//103,104, 203, 204, 303, 304// ok to cover//
BLD-Energy code compliance7/19/20197/19/20197/19/2019PNR
DetailsTell Riley
Matt Phone #: ###-####//add vapor barrier at bottom on first two floors//fix tenting 3rd floor//fix broken stud first floor//re inspect monday//103/104/203/204/303/304
BLD-Framing/Rough-in7/18/20197/18/20197/18/2019PPART
DetailsTell Riley
Matt Phone #: ###-####//framing corrections made//call for insulation on 103,104,203,204,303,304//
PubWorks Temp Occupancy Appr7/18/20197/18/20197/18/2019 DONE
DetailsTiffany Lowery
BLD-Framing/Rough-in7/16/20197/16/20197/16/2019PPART
DetailsTell Riley
Bill Phone #: ###-####//see corrections onsite// ok to insulate--keep areas that need changes open//call for 7/17 pm inspection//103,104,203,204, 303, 304
BLD-Framing/Rough-in7/11/20197/12/20197/12/2019APASS
DetailsTell Riley
Matt Phone #: ###-####//corrections made//rough-ins passed//105,106,205,206,305,306//
BLD-Framing/Rough-in7/10/20197/10/20197/10/2019PCANC
DetailsTell Riley
Matt Phone #: ###-####
BLD-Framing/Rough-in7/2/20197/2/20197/2/2019PNR
DetailsTell Riley
Matt Phone #: ###-####//hold downs need to be 18" max per manufacturer//clear up issues with interior wall hold downs//let me know......////
BLD-Energy code compliance6/28/20196/28/20196/28/2019PNR
DetailsTell Riley
Bill Phone #: ###-####//not ready//
BLD-Other6/26/20196/27/20196/27/2019ACANC
DetailsTell Riley
follow up on hold down installation....
BLD-Other6/26/20196/26/20196/26/2019ACANC
DetailsTell Riley
follow up on hold down installation........
BLD-Framing/Rough-in6/26/20196/26/20196/26/2019PPART
DetailsTell Riley
Bill Phone #: ###-####//framing corrections made//waiting for hold down extensions//will schedule follow up mid am 6/27//install trimmers on header second floor//ok to insulate top down//units 5's and 6's
BLD-Framing/Rough-in6/25/20196/25/20196/25/2019PFAIL
DetailsTell Riley
bill Phone #: ###-####//see corrections list onsite with Bill//call for re-inspection//
BLD-Energy code compliance6/19/20196/20/20196/20/2019APASS
DetailsMike Jordan
Bill- please late morning Phone #: ###-####. framing issues corrected.
BLD-Framing/Rough-in6/18/20196/18/20196/18/2019PPART
DetailsTell Riley
bill Phone #: ###-####//install H2.5 on trusses//nail all truss hangers//add nuts to HDU's//caulk penetrations as discussed//ok to insulate only//
BLD-Wall Bracing5/10/20195/10/20195/10/2019PPART
DetailsJim Sly
Bill Phone #: ###-####
Exterior straps and nailing only.....OK..
BLD-Foundation3/4/20193/5/20193/5/2019APASS
DetailsJim Sly
Please go late morn and call Dean Phone #: ###-####
BLD-Foundation3/1/20193/4/20193/5/2019PPASS
DetailsJim Sly
DAne Phone #: ###-####
BLD-Foundation2/28/20193/1/20193/1/2019PPASS
DetailsJim Sly
Dane Phone #: ###-####
BLD-Footing2/25/20192/26/20192/26/2019PPART
DetailsJim Sly
Dane Phone #: ###-####
BLD-Footing2/20/20192/21/20192/22/2019PCANC
DetailsJim Sly
Dane Phone #: ###-####
BLD-Footing2/19/20192/20/20192/20/2019PPASS
DetailsBrandon Shaw
Remove snow and/or ice before pouring...
Frost protection is required...
BLD-Footing2/19/20192/19/20192/19/2019PPART
DetailsJim Sly
Dane Phone #: ###-####
Issue PAID IN FULL permit  2/19/2019 DONE
Inspection Record Card- Bld  2/19/2019 DONE
Print Occupancy Form  2/19/2019 DONE
Meeting  2/12/2019 DONE
sent email to recommend an extension request be sent in
Meeting  2/12/2019 DONE
Jeremy sent in request for extension
OVERRIDE  2/8/2019  
Plan assigned to (JAR)9/26/20189/26/20182/8/2019 DONE
DetailsJulie Romig
02/11 - 1st Rev Comp - 3rd Rev - 506 Fairview Apartments Bldg 2
Routing PW Street Lights2/7/2019 2/8/2019 PASS
DetailsTom Marshall
PLANS/APPL TAKEN TO FRONT DESK  2/8/2019 DONE
Permit Ready to Issue  2/8/2019 DONE
Routing - PLAN CHECK2/7/2019 2/7/2019 PASS
DetailsJulie Romig
Routing - PLAN CHECK1/10/2019 1/17/2019 FAIL
DetailsJulie Romig
Routing Off Site - STRUCTURAL1/10/2019 1/17/2019 PASS
DetailsJulie Romig
AHJ
Routing - PLANNING1/10/2019 1/11/2019 PASS
DetailsSusan Riggs
Route to Impact Fee Review11/13/201811/16/201811/14/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE9/26/20189/26/201811/13/2018 PASS
DetailsErika Akin
Attached comments to case
1st review completed  11/13/2018 FAIL
DetailsJulie Romig
Routing - PLAN CHECK9/26/2018 11/6/2018 FAIL
DetailsJulie Romig
Plan Review report emailed to applicant.
Routing Off Site - STRUCTURAL9/26/2018 10/10/2018 FAIL
DetailsJulie Romig
AHJ - Corrections Required per ePlanReview
Routing - MECHANICAL9/26/2018 10/3/2018 PASS
DetailsTroy James
Routing - Design Review9/26/2018 10/2/2018 PASS
DetailsAndrea Tuning
DRH17-532 Andrea
Routing - PLUMBING9/26/2018 10/1/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing9/26/2018 10/1/2018 PASS
DetailsDoug Chausow
Correct Parcel number and address: 11783 W King St, Apts 101-108
Routing PW Sewer Design9/27/2018 10/1/2018 PASS
DetailsDeAnn Brown
Routing PW Sewer Rating9/27/2018 10/1/2018 PASS
DetailsBeverly Mountain
Routing PW Solid Waste9/27/2018 9/28/2018 PASS
DetailsEvan Carpenter
Routing PW Drainage9/27/2018 9/28/2018 PASS
DetailsBrian Murphy
Routing PW Street Lights9/27/2018 9/28/2018 FAIL
DetailsTom Marshall
Sent email to jeremy for required corrections.
Routing - PUBLIC WORKS9/26/2018 9/27/2018 PASS
DetailsBeverly Mountain
Routing - Erosion and Sediment9/26/2018 9/27/2018 PASS
DetailsAndy J. Long
SWPPP approved. Valid stormwater team designated. Site already started under GRD18-00035, no site prep required.
Routing - PLANNING9/26/2018 9/26/2018 FAIL
DetailsSusan Riggs
PUD17-22 Susan
APPLICANT MUST POST BOND FOR AMENITIES
Intake Approval  9/21/2018 PASS
Intake Approval  8/28/2018 FAIL
DetailsJoe Bruce
1. Verification of legal lot or parcel form must be signed/dated by PDS subdivision staff.
2. Sheet A-1.1 does not call out or designate any fire hydrants. Resubmit with this information.
3. Provide architectural stamp / signature on (A-205, A-402, A402.1, A-403, A-404, A-405, A-406)
4. Provide and upload form #310 - Statement of Special Inspections completed and stamped by the design engineer for all special inspections noted on sheet S0.01
5. Incorrect codes are referenced on sheet G002. Resubmit with currently adopted codes by City of Boise. (see redlines)
6. Incorrect version of IECC is used on G008 and G009. Resubmit with 2015 IECC
7. I did not see the Manual J report in the "Documents" folder or referenced on the drawings. Please upload the Manual J , Manual D, and Manual S reports noted on the checklist.
Application received  8/27/2018 DONE
Application submitted via PDS Online on Aug 27 2018 10:13AM
First Notice 10/26/2019