BLD-Final | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Tell Riley
|
|
|
PAT Phone #: ###-####//all trades finals complete//signatures required complete//final complete//
|
Permanent Occupancy | | | 10/16/2019 | | DONE |
|
|
|
|
BLD-Final | 10/14/2019 | 10/15/2019 | 10/15/2019 | P | CANC |
Tell Riley
|
|
|
Pat Phone #: ###-####
|
PubWorks Occupancy Approval | 10/14/2019 | 10/14/2019 | 10/14/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Footing | 10/8/2019 | 10/9/2019 | 10/9/2019 | A | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####
|
BLD-Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//last six units complete//temp occupancy approved for entire building//final can be complete once all signatures are complete//
|
FIRE-Final Inspection | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Matt Phone #: ###-####
|
BLD-Final | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####//cancel per Matt//
|
FIRE-Final Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
Apartment 201 needs the ceiling patched in several locations and the smoke alarm re-mounted. Apartment 301 sprinkler pendant is missing canopy.
Matt Phone #: ###-####
|
BLD-Final | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//103,104,203,204,303,304/// finals complete on these units//
|
FIRE-Final Inspection | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety complete for apartments 103, 104, 203, 204, 303 and 304. Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | CANC |
Troy Cobbley
|
|
|
Matt Phone #: ###-#### cancel per matt
|
BLD-Final | 9/25/2019 | 9/26/2019 | 9/26/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-#### cancel per matt
|
BLD-Final | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//units 105,106,205,206,305,306 are ok to occupy when door springs have been adjusted//
|
FIRE-Final Inspection | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Troy Cobbley
|
|
|
The rooms needing inspection have been looked at by me last week. Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 105, 106, 205, 206, 305, 306. Matt Phone #: ###-####
|
Temporary Occupancy | 9/18/2019 | 12/17/2019 | 9/18/2019 | | DONE |
Brittany Hill
|
|
|
|
PubWorks Occupancy Approval | 9/18/2019 | 9/18/2019 | 9/18/2019 | | PART |
Brittany Hill
|
|
|
card was signed by brian murphy
|
BLD-Final | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PART |
Tell Riley
|
|
|
Pat-1st 6 units Phone #: ###-####//north 6 units//final complete pending fire//
|
Zoning Approval | 9/13/2019 | 9/13/2019 | 9/13/2019 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PART |
Troy Cobbley
|
|
|
The six apartments, 1st through 3rd floors at the very north end of this building have the life safety passed. The FDC needs the required clearance as discussed prior to a final inspection. Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | CANC |
Troy Cobbley
|
|
|
Life safety will be a pass for the north most apartments when the project related fire alarm and fire sprinkler permits are passed. Matt- mid mornign Phone #: ###-####
|
BLD-Energy code compliance | 7/29/2019 | 7/30/2019 | 7/30/2019 | P | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//ok to cover units101,102,201,202,301,302, all units passed//
|
BLD-Framing/Rough-in | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//framinng corrections onsite//ok to insulate only// 101,102,201,202,301,303//
|
BLD-Energy code compliance | 7/19/2019 | 7/22/2019 | 7/22/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//corrections made//103,104, 203, 204, 303, 304// ok to cover//
|
BLD-Energy code compliance | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | NR |
Tell Riley
|
|
|
Matt Phone #: ###-####//add vapor barrier at bottom on first two floors//fix tenting 3rd floor//fix broken stud first floor//re inspect monday//103/104/203/204/303/304
|
BLD-Framing/Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//framing corrections made//call for insulation on 103,104,203,204,303,304//
|
PubWorks Temp Occupancy Appr | 7/18/2019 | 7/18/2019 | 7/18/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Framing/Rough-in | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PART |
Tell Riley
|
|
|
Bill Phone #: ###-####//see corrections onsite// ok to insulate--keep areas that need changes open//call for 7/17 pm inspection//103,104,203,204, 303, 304
|
BLD-Framing/Rough-in | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//corrections made//rough-ins passed//105,106,205,206,305,306//
|
BLD-Framing/Rough-in | 7/10/2019 | 7/10/2019 | 7/10/2019 | P | CANC |
Tell Riley
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | NR |
Tell Riley
|
|
|
Matt Phone #: ###-####//hold downs need to be 18" max per manufacturer//clear up issues with interior wall hold downs//let me know......////
|
BLD-Energy code compliance | 6/28/2019 | 6/28/2019 | 6/28/2019 | P | NR |
Tell Riley
|
|
|
Bill Phone #: ###-####//not ready//
|
BLD-Other | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | CANC |
Tell Riley
|
|
|
follow up on hold down installation....
|
BLD-Other | 6/26/2019 | 6/26/2019 | 6/26/2019 | A | CANC |
Tell Riley
|
|
|
follow up on hold down installation........
|
BLD-Framing/Rough-in | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PART |
Tell Riley
|
|
|
Bill Phone #: ###-####//framing corrections made//waiting for hold down extensions//will schedule follow up mid am 6/27//install trimmers on header second floor//ok to insulate top down//units 5's and 6's
|
BLD-Framing/Rough-in | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | FAIL |
Tell Riley
|
|
|
bill Phone #: ###-####//see corrections list onsite with Bill//call for re-inspection//
|
BLD-Energy code compliance | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Mike Jordan
|
|
|
Bill- please late morning Phone #: ###-####. framing issues corrected.
|
BLD-Framing/Rough-in | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PART |
Tell Riley
|
|
|
bill Phone #: ###-####//install H2.5 on trusses//nail all truss hangers//add nuts to HDU's//caulk penetrations as discussed//ok to insulate only//
|
BLD-Wall Bracing | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | PART |
Jim Sly
|
|
|
Bill Phone #: ###-#### Exterior straps and nailing only.....OK..
|
BLD-Foundation | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Jim Sly
|
|
|
Please go late morn and call Dean Phone #: ###-####
|
BLD-Foundation | 3/1/2019 | 3/4/2019 | 3/5/2019 | P | PASS |
Jim Sly
|
|
|
DAne Phone #: ###-####
|
BLD-Foundation | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/25/2019 | 2/26/2019 | 2/26/2019 | P | PART |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/20/2019 | 2/21/2019 | 2/22/2019 | P | CANC |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Brandon Shaw
|
|
|
Remove snow and/or ice before pouring... Frost protection is required...
|
BLD-Footing | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PART |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/19/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/19/2019 | | DONE |
|
|
|
|
Meeting | | | 2/12/2019 | | DONE |
|
|
|
sent email to recommend an extension request be sent in
|
Meeting | | | 2/12/2019 | | DONE |
|
|
|
Jeremy sent in request for extension
|
OVERRIDE | | | 2/8/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 9/26/2018 | 9/26/2018 | 2/8/2019 | | DONE |
Julie Romig
|
|
|
02/11 - 1st Rev Comp - 3rd Rev - 506 Fairview Apartments Bldg 2
|
Routing PW Street Lights | 2/7/2019 | | 2/8/2019 | | PASS |
Tom Marshall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/8/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/7/2019 | | 2/7/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 1/10/2019 | | 1/17/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/10/2019 | | 1/17/2019 | | PASS |
Julie Romig
|
|
|
AHJ
|
Routing - PLANNING | 1/10/2019 | | 1/11/2019 | | PASS |
Susan Riggs
|
|
|
|
Route to Impact Fee Review | 11/13/2018 | 11/16/2018 | 11/14/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/26/2018 | 9/26/2018 | 11/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 11/13/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/26/2018 | | 11/6/2018 | | FAIL |
Julie Romig
|
|
|
Plan Review report emailed to applicant.
|
Routing Off Site - STRUCTURAL | 9/26/2018 | | 10/10/2018 | | FAIL |
Julie Romig
|
|
|
AHJ - Corrections Required per ePlanReview
|
Routing - MECHANICAL | 9/26/2018 | | 10/3/2018 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 9/26/2018 | | 10/2/2018 | | PASS |
Andrea Tuning
|
|
|
DRH17-532 Andrea
|
Routing - PLUMBING | 9/26/2018 | | 10/1/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 9/26/2018 | | 10/1/2018 | | PASS |
Doug Chausow
|
|
|
Correct Parcel number and address: 11783 W King St, Apts 101-108
|
Routing PW Sewer Design | 9/27/2018 | | 10/1/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Sewer Rating | 9/27/2018 | | 10/1/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 9/27/2018 | | 9/28/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 9/27/2018 | | 9/28/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 9/27/2018 | | 9/28/2018 | | FAIL |
Tom Marshall
|
|
|
Sent email to jeremy for required corrections.
|
Routing - PUBLIC WORKS | 9/26/2018 | | 9/27/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/26/2018 | | 9/27/2018 | | PASS |
Andy J. Long
|
|
|
SWPPP approved. Valid stormwater team designated. Site already started under GRD18-00035, no site prep required.
|
Routing - PLANNING | 9/26/2018 | | 9/26/2018 | | FAIL |
Susan Riggs
|
|
|
PUD17-22 Susan
APPLICANT MUST POST BOND FOR AMENITIES
|
Intake Approval | | | 9/21/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/28/2018 | | FAIL |
Joe Bruce
|
|
|
1. Verification of legal lot or parcel form must be signed/dated by PDS subdivision staff.
2. Sheet A-1.1 does not call out or designate any fire hydrants. Resubmit with this information.
3. Provide architectural stamp / signature on (A-205, A-402, A402.1, A-403, A-404, A-405, A-406)
4. Provide and upload form #310 - Statement of Special Inspections completed and stamped by the design engineer for all special inspections noted on sheet S0.01
5. Incorrect codes are referenced on sheet G002. Resubmit with currently adopted codes by City of Boise. (see redlines)
6. Incorrect version of IECC is used on G008 and G009. Resubmit with 2015 IECC
7. I did not see the Manual J report in the "Documents" folder or referenced on the drawings. Please upload the Manual J , Manual D, and Manual S reports noted on the checklist.
|
Application received | | | 8/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 27 2018 10:13AM
|
First Notice | | 10/26/2019 | | | |
|
|
|
|