BLD-Final | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Mike Jordan
|
|
|
Please call Candyce at ###-#### when finalized Phone #: ###-#### Inspection requested via web by Candyce Moss
|
DOC - Permit Finaled | 11/15/2018 | 11/15/2018 | 11/15/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Footing | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | FAIL |
Mike Jordan
|
|
|
Please call Candyce @ ###-#### as soon as inspection is complete. Inspection requested via web by Candyce Moss. North footing not 30 X 30.
|
BLD-Footing | 11/2/2018 | 11/5/2018 | 11/2/2018 | P | CANC |
Mike Jordan
|
|
|
Please Call Candyce @ ###-#### when inspection is complete Phone #: ###-#### >> Inspection requested via web by Candyce Moss Inspection cancelled from web by: Candyce Moss
|
Issue PAID IN FULL permit | | | 10/29/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/29/2018 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 10/1/2018 | 10/1/2018 | 10/2/2018 | | PASS |
Josh Bogle
|
|
|
10/05 patio cover, ePlan
|
Routing - PLAN CHECK | 10/1/2018 | | 10/2/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 10/2/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 10/2/2018 | | DONE |
|
|
|
met
|
Routing - PLANNING | 10/1/2018 | | 10/1/2018 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/1/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/1/2018 | | DONE |
|
|
|
no fee taken at intake, 406
|
Intake Approval | | | 10/1/2018 | | PASS |
|
|
|
|
Application received | | | 8/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 27 2018 3:33PM
|