Second Notice | | 2/17/2019 | 2/14/2019 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | | 1/24/2019 | 2/7/2019 | | DONE |
|
|
|
mailed 2-11-19
|
Permanent Occupancy | | | 1/14/2019 | | DONE |
|
|
|
|
BLD-Final | 1/10/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Mike Jordan
|
|
|
Call half hour before // Sean Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Building inspector will verify the exit sign/emergency light is repaired and the other stand alone emergency light is repaired or removed.
Call half hour before // Sean Phone #: ###-####
|
BLD-Final | 1/3/2019 | 1/4/2019 | 1/4/2019 | A | NR |
Mike Jordan
|
|
|
Shawn Phone #: ###-####
|
FIRE-Conference | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | DONE |
Troy Cobbley
|
|
|
I went over general life safety requirements with the general contractor and discussed the possible need for a duct smoke detector and separate FIR permit for the new 10 ton HVAC unit serving the new areas.
|
BLD-Ceiling Grid Inspection | 12/19/2018 | 12/19/2018 | 12/19/2018 | P | PASS |
Mike Jordan
|
|
|
Shawn Phone #: ###-####
|
BLD-Framing/Rough-in | 11/30/2018 | 12/3/2018 | 12/3/2018 | A | PASS |
Jim Sly
|
|
|
Sean Phone #: ###-####
|
Print Occupancy Form | | | 11/30/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/30/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
Plan assigned to (JG) | 11/5/2018 | 11/5/2018 | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, Plan Mod Catapult ePlan, pend fire
|
Routing - PLAN CHECK | 11/26/2018 | | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2018 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/27/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 11/27/2018 | | DONE |
|
|
|
Plan mod approved
DO NOT REISSUE
|
Routing - FIRE | 11/7/2018 | 11/7/2018 | 11/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 11/7/2018 | | 11/15/2018 | | FAIL |
Javier Guzman
|
|
|
|
BLD-Framing/Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Mike Jordan
|
|
|
Sharn Phone #: ###-####. Inteior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Mike Jordan
|
|
|
demising walls- Tom Phone #: ###-####. Demissing wall only ok.
|
Plan Modification Accepted | | | 11/5/2018 | | DONE |
|
|
|
adding a 1hr rated mech roan w/lid around existing fire riser area
|
Plan Reviewer's activity | | | 11/1/2018 | | DONE |
Javier Guzman
|
|
|
Requested revised floor plans from architect on 10/30 and 11/1 2018 and sent him the plan mod application
|
Print Occupancy Form | | | 10/24/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/24/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 9/4/2018 | 9/4/2018 | 10/17/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 9/13 L2 Catapult ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/17/2018 | | DONE |
|
|
|
GWALKER@ADPBOISE.COM
MET
Need
Revised Cert of value
|
Routing - PLAN CHECK | 9/21/2018 | | 10/17/2018 | | PASS |
Javier Guzman
|
|
|
|
Plan Reviewer's activity | | | 10/11/2018 | | DONE |
Javier Guzman
|
|
|
This project has been sitting due to the pending BLD18-03595 permit passing prescreen. Reason why at the beginning of the project there was a created vanilla space which separated a warehouse and the architect was asked to provide a separate application for the created vanilla space where he told me a future T.I was to come in the following week under a separate permit. The separate permit BLD referenced did come in but is pending pertinent details regarding the existing 2-hour wall with unpermitted openings. once the information regarding the rated wall openings and the pending items to pass prescreen have been completed this permit will be released for issuance. (both the architect and the contractor Kelly have been advised)
|
Route to Impact Fee Review | 9/19/2018 | 9/22/2018 | 9/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing Off Site - STRUCTURAL | 9/4/2018 | | 9/19/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Chris Holladay
|
1st review completed | | | 9/19/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 9/4/2018 | | 9/17/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/4/2018 | | 9/10/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 9/4/2018 | | 9/4/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/4/2018 | | 9/4/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Design Review | 9/4/2018 | | 9/4/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Intake Approval | | | 8/31/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 8/28/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 28 2018 3:31PM
|