Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-03159
StatusFinaled
Name MACFARLANE RENOVATIONS
Site Address 2960 N HILLWAY DR
Project NameMacfarlane Remodel
Customer Number 
ePlanReviewNo
Description
This permit for an interior remodel with work to include: Major interior remodel - structural engineering provided for stairway move and large structural beams to be installed. 1st floor remodelling kitchen and bathroom, (3) new exterior doors, (2) demo exterior doors, (1) new half bathroom, (1) new lavatory. Basement remodeling bath/laundry room and finishing unfinished basement, (1) new bathtub, (2) new bedroom 1 with egress by door 1 with egress through window well. Stairs shifted see structural engineering and new column and footing. Exterior WUI deck per plans engineering. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **MDH**

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/12/20196/13/20196/13/2019ADONE
DetailsTony Young
Tom Phone #: ###-####
DOC - Permit Finaled6/13/20196/13/20196/13/2019PPASS
DetailsTony Young
c of c issued,, prior issues ok now
BLD-Final6/3/20196/4/20196/4/2019AFAIL
DetailsTony Young
Tom Phone #: ###-####- please call for access ,, needs guard rails, hand rails per code,, needs egress
BLD-Final5/17/20195/24/20195/24/2019PCANC
DetailsTony Young
as late as possible // Tom Phone #: ###-#### canel per tom mcfarland
Routing - MECHANICAL5/6/2019 5/6/2019 PASS
DetailsTroy James
Revised manual j report
BLD-Energy code compliance1/17/20191/18/20191/18/2019PPASS
DetailsBrandon Shaw
Tom Phone #: ###-####
BLD-Foundation1/9/20191/10/20191/15/2019APEND
DetailsTony Young
Tommy Phone #: ###-####,, poured,,
BLD-Framing/Rough-in1/9/20191/10/20191/10/2019APART
DetailsTony Young
Tommy Phone #: ###-####,, ok to insulate,, need to verify seal package,, strap plates
PubWorks Subgrade Approval10/23/201810/23/201810/23/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Plan assigned to (M_H)9/5/2018 10/17/2018 DONE
DetailsMichael Hanson
09/11 #406 L2 Paper. 1st review completed - See email for corrections required. MDH 2nd review completed - See email for correction required. MDH
OVERRIDE  10/12/2018  
Routing Walk-In (BLD)10/12/201810/12/201810/12/2018PDONE
DetailsJosh Bogle
Routing - PLAN CHECK10/12/2018 10/12/2018 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  10/12/2018 DONE
DetailsJosh Bogle
Case Summary (BLD)  10/12/2018 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  10/12/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  10/12/2018 DONE
Issue PAID IN FULL permit  10/12/2018 DONE
Routing PW Grading-Hillside10/11/2018 10/11/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Routing - PLANNING9/5/2018 10/11/2018 PASS
DetailsSue Cummings
Plan Reviewer's activity  10/10/2018 DONE
DetailsJosh Bogle
took plans to Planning
Routing Walk-In (BLD)10/9/201810/9/201810/9/2018PPASS
DetailsJosh Bogle
wanted to talk to Josh about resubmittals (Michael out of office)
Plan resubmittals received  10/9/2018 DONE
Resubmittal received 2 of 8 sheets 2 beam post & pad footings & 2 struc calcs-was told to put on JAB's chair
Routing - PLAN CHECK10/5/2018 10/5/2018 FAIL
DetailsMichael Hanson
Addition of WUI compliant deck requiring corrections and more information on the remodel required. MDH
Routing Walk-In (BLD)10/4/201810/4/201810/4/2018PFAIL
DetailsJosh Bogle
talked about Tommy's resubmittals
Plan resubmittals received  10/4/2018 DONE
two copies of calcs and whole new plans, stamped and taken to plan reviewer
1st review completed  9/12/2018 FAIL
DetailsMichael Hanson
See email for corrections required. MDH
Routing - PLAN CHECK9/5/2018 9/12/2018 FAIL
DetailsMichael Hanson
See email for corrections required. MDH
Routing - MECHANICAL9/10/2018 9/10/2018 PASS
DetailsTroy James
Manual j report
Routing Walk-In (BLD)9/5/20189/5/20189/5/2018APASS
DetailsMichael Hanson
Intake Approval  9/5/2018 PASS
DetailsMichael Hanson
Routing - Erosion and Sediment9/5/2018 9/5/2018 PASS
DetailsMichael Zawacki
Waiver approved, owner to act as RP.
Routing Walk-In (BLD)8/28/20188/28/20188/28/2018PFAIL
DetailsJosh Bogle
Routing - PLAN CHECK8/28/2018 8/28/2018 FAIL
DetailsJosh Bogle
applicant getting better plans
1st review completed  8/28/2018 FAIL
DetailsJosh Bogle
Application received 8/28/2018