BLD-Aging Inspection | 9/11/2019 | 9/11/2019 | 9/13/2019 | | PASS |
Tell Riley
|
|
|
Expires: 03/09/20
|
BLD-Aging Inspection | 9/10/2019 | 9/10/2019 | 9/11/2019 | | PASS |
Tell Riley
|
|
|
Expires: 10/26/19
|
Issue PAID IN FULL permit | | | 10/26/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/26/2018 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 9/19/2018 | 9/19/2018 | 10/25/2018 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 10/05 (L2) - TCD AWNINGS ePlan (Struc)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/25/2018 | | DONE |
|
|
|
DANA@SUPERIORSIGNSIDAHO.COM
MET
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 10/17/2018 | | 10/24/2018 | | PASS |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 10/17/2018 | | 10/24/2018 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 10/17/2018 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 10/5/2018 | 10/8/2018 | 10/8/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/5/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 10/5/2018 | | DONE |
Joe Bruce
|
|
|
Spoke with applicant on the phone regarding a C of O for occupancy and additional information needed from 1st Review. **JHB**
|
Routing - PLAN CHECK | 9/19/2018 | | 10/5/2018 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 9/19/2018 | | 10/3/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ - Dave Haugland - Corrections Required, see changemarks.
|
Routing - Design Review | 9/19/2018 | | 9/19/2018 | | PASS |
KayCee Babb
|
|
|
per CZC18-00204
|
Intake Approval | | | 9/18/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 9/12/2018 | | FAIL |
Joe Bruce
|
|
|
1) All the plans will need to be submitted on a minimum 18"x24" sheet size. Site Plan SP1 and SP2 are both on a sheet that does not meet these requirements.
2) We will need to see the Planning and Zoning letter(s) of approval for the exterior changes to the building. Upload these letters/documents into the documents folder.
3) Provide a table of contents/drawing index on the cover sheet of the drawings.
4) Provide a code analysis/building data information on the drawings stating the construction type, land use zone, construction type, fire suppression system / sprinklers, etc... on the plans.
|
Intake Approval | | | 8/30/2018 | | FAIL |
Joe Bruce
|
|
|
Emailed checklist #518 "Minor TI Submittal" that will need to be filled out and completed along with all required documents for prescreen.
|
Application received | | | 8/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2018 1:45PM
|