BLD-Final | 12/26/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Tony Young
|
|
|
Noel Phone #: ###-####
|
BLD-Blower Door Test Results | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Tony Young
|
|
|
Noel Phone #: ###-####.. 3.48
|
DOC - Permit Finaled | 12/27/2019 | 12/27/2019 | 12/27/2019 | P | PASS |
Tony Young
|
|
|
|
PubWorks Subgrade Approval | 12/27/2019 | 12/27/2019 | 12/27/2019 | | DONE |
Melissa Jannusch
|
|
|
PERIMETER FOOTINGS A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
PubWorks Occupancy Approval | 12/27/2019 | 12/27/2019 | 12/27/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Conference | 12/20/2019 | 12/23/2019 | 12/23/2019 | A | PART |
Tony Young
|
|
|
Fabian Phone #: ###-####,, walk through on the final,, needs hillside PW pass,, needs guard rail and hand rail to meet code,, needs fire seperation in the garage..
|
BLD-Aging Inspection | 12/10/2019 | 12/10/2019 | 12/11/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Conference | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Tony Young
|
|
|
Noel Phone #: ###-####,, stair ?s
|
Routing Walk-In (BLD) | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Josh Bogle
|
|
|
Questions about glass guard railing, and about soffit assembly. Railing looked to be ok as long as it all meets code requirements. Gave information on soffit assembly, cementitious board ok with layer of 5/8 type x behind. JJN
|
BLD-Framing/Rough-in | 7/26/2019 | 7/29/2019 | 7/29/2019 | A | PART |
Tony Young
|
|
|
Chet Phone #: ###-####,, needs to seal chases,, ok to insulate
|
BLD-Framing/Rough-in | 7/25/2019 | 7/26/2019 | 7/26/2019 | P | NR |
Tony Young
|
|
|
Chet Phone #: ###-####,,conf. walk through only,, needs trades,, needs tempered glass by final,, temp stairs in now,, verify stairs at the final.. needs fire blocking of chases,, plates
|
Routing - MECHANICAL | 7/22/2019 | | 7/22/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
OVERRIDE | | | 5/14/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 4/29/2019 | 4/29/2019 | 5/14/2019 | | DONE |
Jenny Nelson
|
|
|
Plan mod - block retaining walls. 1st complete, waiting on hillside
|
CHANGE STATUS TO (ISS) | | | 5/14/2019 | | DONE |
|
|
|
PLAN MOD
|
Permit Ready to Issue | | | 5/14/2019 | | DONE |
|
|
|
plan mod approved - fees due
DO NOT REISSUE
|
Routing PW Grading-Hillside | 4/30/2019 | | 5/9/2019 | | PASS |
Melissa Jannusch
|
|
|
PLAN MOD APPROVED. Engineering submitted for change to block walls. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - PLAN CHECK | 4/30/2019 | | 5/7/2019 | | PASS |
Jenny Nelson
|
|
|
1 hour plan mod fee
|
Routing - PUBLIC WORKS | 4/30/2019 | | 4/30/2019 | | PASS |
Angela Hardy
|
|
|
|
Plan Modification Accepted | | | 4/29/2019 | | DONE |
|
|
|
plan modification requested by H.O.
|
BLD-Concrete | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | PART |
Tony Young
|
|
|
Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel,, work in progress on upper level ICF walls
|
BLD-Concrete | 3/18/2019 | 3/20/2019 | 3/20/2019 | P | NR |
Dave Hannah
|
|
|
Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel
|
BLD-Foundation | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | PART |
Tony Young
|
|
|
rebar// sabian Phone #: ###-####,, icf block wall,, mid wall ok to grout
|
BLD-Concrete | 1/14/2019 | 1/17/2019 | 1/17/2019 | A | PART |
Mike Jordan
|
|
|
Phone #: 2088806738 >> Inspection requested via mobile web by Chet Clark. ICF permiter wall from top of footing to 10ft. 8 inch elev. Needs to tie verts in place and complet lintel steel.
|
BLD-Footing | 1/8/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Brandon Shaw
|
|
|
First story footings... Work in progress...
|
BLD-Wall Bracing | 12/1/2018 | 12/5/2018 | 12/5/2018 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel,, upper retaining wall,, work in progress,, will tent and heat for freezing temps
|
BLD-Footing | 11/20/2018 | 11/26/2018 | 11/26/2018 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel,, upper retaining wall ok
|
PubWorks Subgrade Approval | 11/20/2018 | 11/20/2018 | 11/20/2018 | | DONE |
Melissa Jannusch
|
|
|
RETAINING WALL. A letter from the applicant’s geotechnical engineer indicating that the RETAINING WALL footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 11/17/2018 | 11/19/2018 | 11/17/2018 | A | CANC |
Tony Young
|
|
|
As early as possible Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel Inspection cancelled via mobile web on Saturday, November 17, 2018.
|
OVERRIDE | | | 10/26/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 9/28/2018 | 9/28/2018 | 10/26/2018 | | DONE |
Jenny Nelson
|
|
|
10/17 sfd L2 ePlan. 1st review complete 10/15 Metal roof under minimum pitch, ES report for ICF walls, specify prescriptive energy or Rescheck, structural calcs update code year
|
Issue PAID IN FULL permit | | | 10/26/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/26/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/26/2018 | | 10/26/2018 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 10/26/2018 | | DONE |
|
|
|
|
Routing - FIRE | 10/25/2018 | 10/25/2018 | 10/25/2018 | | PASS |
Tim Frost
|
|
|
Fire Sprinklers are Required
|
Routing - MECHANICAL | 10/18/2018 | | 10/24/2018 | | PASS |
Troy James
|
|
|
Waiting for task to complete this job
|
Routing - PLAN CHECK | 9/28/2018 | | 10/16/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 9/28/2018 | | 10/16/2018 | | FAIL |
Troy James
|
|
|
Corrections sent to heating supply
|
1st review completed | | | 10/15/2018 | | FAIL |
|
|
|
Metal roof under minimum pitch, ES report for ICF walls, specify prescriptive energy or Rescheck, structural calcs update code year
|
Routing PW Grading-Hillside | 9/28/2018 | | 10/9/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Routing - FIRE | 9/28/2018 | 9/28/2018 | 10/3/2018 | | FAIL |
Tim Frost
|
|
|
See attached Review.
|
Routing - PLANNING | 9/28/2018 | | 10/2/2018 | | PASS |
Leon Letson
|
|
|
|
Route to Impact Fee Review | 9/28/2018 | 10/1/2018 | 10/1/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/28/2018 | | 9/28/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/28/2018 | | 9/28/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 9/28/2018 | | 9/28/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed, site prep inspection required.
|
Intake Approval | | | 9/28/2018 | | FAIL |
|
|
|
per hillside- need updated Grading plans and retaining wall calculation from the updated CFH18-00075 case
|
Plans ACCEPTED BY PLAN TECH | | | 9/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/28/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/10/2018 | | FAIL |
|
|
|
ESC NARRATIVE
STRUCTURAL CALCS
MET
ENERGY COMPLIANC/RESCHECK
MEC EQUIPMENT
|
Application received | | | 9/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2018 1:07PM
|