First Notice | | 5/3/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
BLD-Final | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Mike Jordan
|
|
|
I have had to move zoning and landscape until tomorrow at 11:00 am if you could come after that it would be great. Thanks Phone #: ###-#### Inspection requested via web by Jimmie Miller. ok for perm occ.
|
Zoning Approval | 4/23/2019 | 4/23/2019 | 4/23/2019 | | DONE |
Andrea Tuning
|
|
|
|
Permanent Occupancy | | | 4/23/2019 | | DONE |
|
|
|
|
BLD-Final | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | CANC |
Mike Jordan
|
|
|
I have final zoning landscape at 11:00 with Andrea and if it passed i need final building right after if possible, so I can get occupancy certificate and move the owners in. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jimmie Miller
|
BLD-Final | 4/16/2019 | 4/19/2019 | 4/19/2019 | P | NR |
Brandon Shaw
|
|
|
I have final Zoning/ landscape set up for 2:30. Please come after that has passed if it don''t pass I will cancel it. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
FIRE-Final Inspection | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire exitnguishers are placed with current inspection tags. Final life fire safety inspection complete.
Treasure Valley Fire protection and Priority electric are going to schedule fire sprinkler and alarm. Make this one the final life/safety please. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
PubWorks Occupancy Approval | 4/18/2019 | 4/18/2019 | 4/18/2019 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled before a life safety inspection. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
FIRE-Final Inspection | 4/11/2019 | 4/16/2019 | 4/15/2019 | A | CANC |
Troy Cobbley
|
|
|
I believe final plumbing, mechanical,electrical, are complete for final but can you check to make sure so i will be ready to call in final occupancy when landscape and zoning are completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jimmie Miller
|
Print Occupancy Form | | | 4/8/2019 | | DONE |
|
|
|
|
BLD-Other | 2/25/2019 | 2/26/2019 | 2/26/2019 | P | CANC |
Mike Jordan
|
|
|
Mechanical HVAC inspect condensate line for the mini split and visual on the heat tape wrapping that pipe. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Needs mech inspection.
|
BLD-Energy code compliance | 2/23/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Mike Jordan
|
|
|
Insulation inspection on B line exterior wall. Phone #: ###-#### Inspection requested via web by Jimmie Miller. North exterior wal.
|
BLD-Framing/Rough-in | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Mike Jordan
|
|
|
Insulation inspection on B line exterior wall. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | NR |
Mike Jordan
|
|
|
Interior wall inspection. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Needs electrical rough in inspection first.
|
BLD-Framing/Rough-in | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Mike Jordan
|
|
|
Framing and shear wall inspection. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Exterior steel stud framed shear walls/holdowns and wind girts ok.
|
BLD-Energy code compliance | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PASS |
Mike Jordan
|
|
|
Roofing insulation inspection Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
BLD-Other | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | DEFR |
Mike Jordan
|
|
|
Structural Steel on B line of building. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Welding, ok to frame and sheet one side only after special inspection has taken place on welds.
|
BLD-Concrete | 1/9/2019 | 1/11/2019 | 1/11/2019 | P | PART |
Jim Sly
|
|
|
Jimmie Phone #: ###-#### Interior slab OK pending MTI special inspection, tests and approvals.
|
Override - Parcel Holds | 1/9/2019 | 1/1/1900 | 1/9/2019 | | |
|
|
|
this is for a different address on the same parcel
|
BLD-Energy code compliance | 1/3/2019 | 1/4/2019 | 1/4/2019 | A | PASS |
Mike Jordan
|
|
|
Ridged Polystyrene on foundation wall. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
BLD-Foundation | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | PART |
Brandon Shaw
|
|
|
North foundation for new building front. Work in progress. Ok to place cocrete pending special inspection.
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PART |
Mike Jordan
|
|
|
pour @ 12 // Daryl Phone #: ###-####. North footings for new building front. Work in progress. Ok to place cocrete pending special inspection.
|
Issue PAID IN FULL permit | | | 11/1/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/1/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/29/2018 | | |
|
|
|
|
Plan assigned to (JHB) | 9/26/2018 | 9/26/2018 | 10/29/2018 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 10/19 (L3) - Idaho Central Credit Union Storage (Struc)
|
Routing Off Site - STRUCTURAL | 10/23/2018 | | 10/29/2018 | | PASS |
Joe Bruce
|
|
|
Dave Haugland - AHJ
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/29/2018 | | DONE |
|
|
|
Email to David Moe
Need
RP-met
ACHD-met
GC Form - met
Revised Cert of Value - met
|
Plan resubmittals received | | | 10/23/2018 | | DONE |
Joe Bruce
|
|
|
Received structural response letter and revised sheet S3.0. **JHB**
|
Route to Impact Fee Review | 10/22/2018 | 10/25/2018 | 10/22/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/22/2018 | | FAIL |
Joe Bruce
|
|
|
Failed: 1) Structural
|
Plan resubmittals requested | | | 10/22/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 9/26/2018 | 9/26/2018 | 10/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 9/26/2018 | | 10/17/2018 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Street Lights | 9/27/2018 | | 10/17/2018 | | PASS |
Tom Marshall
|
|
|
Street lights not required.
|
Routing PW Drainage | 9/27/2018 | | 10/10/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 9/26/2018 | | 10/9/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ - Dave Haugland
|
Routing - MECHANICAL | 9/26/2018 | | 9/28/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 9/26/2018 | | 9/27/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 9/26/2018 | | 9/27/2018 | | PASS |
Andrea Tuning
|
|
|
OK per DRH18-00301
|
Routing - Addressing | 9/26/2018 | | 9/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2018 | | 9/27/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/26/2018 | | 9/26/2018 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PLANNING | 9/26/2018 | | 9/26/2018 | | PASS |
Susan Riggs
|
|
|
|
Plan Reviewer's activity | | | 9/24/2018 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 9/24/2018 | | PASS |
|
|
|
|
Intake Approval | | | 9/18/2018 | | FAIL |
|
|
|
(9-18-18) Refer to the circled items in the plan review report. Resolve each item as directed. CJW
Tried to call the Architect to discuss the issues but there was not answer or way to leave a message. CJW
|
Application received | | | 9/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 5 2018 1:36PM
|