BLD-Final | 11/26/2018 | 11/30/2018 | 11/30/2018 | P | FAIL |
Jim Storey
|
|
|
Plans have been left in the meter box Phone #: ###-#### Inspection requested via web by Ashley White no access to insp roof supports per engineering pannels instaled,
|
Plan assigned to (JAB) Josh | 9/7/2018 | 9/7/2018 | 11/5/2018 | | PASS |
Josh Bogle
|
|
|
09/13 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 11/5/2018 | | 11/5/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2018 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 11/5/2018 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 11/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/5/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/29/2018 | | 10/29/2018 | | FAIL |
Josh Bogle
|
|
|
engineering questions
|
Routing - PLAN CHECK | 10/12/2018 | | 10/12/2018 | | FAIL |
Josh Bogle
|
|
|
new engineering, new engineer, I still have structural concerns - see e-mail 10.12.18 8:09am
|
Routing - PLAN CHECK | 10/9/2018 | | 10/9/2018 | | FAIL |
Josh Bogle
|
|
|
structural concerns
|
Plan Reviewer's activity | | | 10/4/2018 | | DONE |
Josh Bogle
|
|
|
accepted resubmittal and forwarded on to AHJ for 3rd party strutural review
|
Routing - PLAN CHECK | 10/1/2018 | | 10/1/2018 | | FAIL |
Josh Bogle
|
|
|
engineering not correct
|
Routing - PLAN CHECK | 9/17/2018 | | 9/17/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 9/14/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/7/2018 | | 9/14/2018 | | FAIL |
Josh Bogle
|
|
|
engineering not to 25# snow load
|
Application received | | | 9/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 7 2018 9:26AM
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/7/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/7/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 9/7/2018 | | 9/7/2018 | | PASS |
Jeff Lowe
|
|
|
|