BLD-Blower Door Test Results | 4/24/2019 | 4/26/2019 | 4/26/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Final | 4/24/2019 | 4/26/2019 | 4/26/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Final | 4/23/2019 | 4/25/2019 | 4/25/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 4/25/2019 | 4/25/2019 | 4/25/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 4/23/2019 | 4/25/2019 | 4/25/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.34
|
BLD-Other | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Energy code compliance | 2/13/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Energy code compliance | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | FAIL |
Brandon Shaw
|
|
|
Complete all corrections... Do Not Cover...
|
BLD-Framing/Rough-in | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | FAIL |
Brandon Shaw
|
|
|
Redo all shear nailing... Hold downs to be installed as per plans... Anchor bolts to be no more than 12" from ends of sill plates... Truss hangres to be positively connected to truss/ wall... Interior walls to be positively connected to sub-flooring... Per plans- (2) 11 7/8 LVL to be installed per Engineering... 3 ply truss to bear down to foundation... Per shear pg- CS16 strap with blocking at over height wall... Per framing page, Over height wall framing- (2) 2x6 DF #2 at 16" O.C.
|
Routing - MECHANICAL | 2/6/2019 | | 2/6/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | FAIL |
Brandon Shaw
|
|
|
Not ready... Hold downs and anchor bolts missing in garage... See red paint... Garage only...
|
BLD-Foundation | 11/21/2018 | 11/21/2018 | 11/21/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Foundation | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | CANC |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell Inspection cancelled via mobile web on Wednesday, November 21, 2018.
|
BLD-Footing | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 10/29/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/29/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/26/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 9/18/2018 | 9/18/2018 | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
10/1 sfd L1 ePlan- 1st Review Complete - Additional Corrections Required
|
Routing - PLAN CHECK | 10/26/2018 | | 10/26/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/26/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 10/26/2018 | | 10/17/2018 | | FAIL |
Brian McGowan
|
|
|
Needs to add holddowns on foundation plan
|
1st review completed | | | 10/1/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 10/1/2018 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 9/18/2018 | 9/21/2018 | 9/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 9/18/2018 | | 9/19/2018 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 9/18/2018 | | 9/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/18/2018 | | 9/18/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/18/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/18/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 9/18/2018 | | 9/18/2018 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 9/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 7 2018 2:35PM
|