BLD-Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Jim Storey
|
|
|
Please contact Russ at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
DOC - Permit Finaled | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/13/2019 | 5/17/2019 | 5/17/2019 | A | PASS |
Mark Scharfen
|
|
|
Conducted fire life safety. Checked battery rack and fire extinguisher. Passed. Note: Contractor was not given stamped plans. No approved plans on site.
Please call Russ at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum
|
BLD-Final | 3/13/2019 | 3/14/2019 | 3/14/2019 | A | NR |
Jim Storey
|
|
|
Please call Russ Wood, thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum need ele permit and fire insp per plan reviewer.
|
BLD-Final | 12/4/2018 | 12/10/2018 | 12/10/2018 | A | NR |
Mike Jordan
|
|
|
Please call Russ with any questions, Thank YOU! Phone #: ###-#### Inspection requested via web by Rhonda Marcum. Needs to provide 3rd. party inspections on ll field welding.
|
Inspection Record Card- Bld | | | 11/15/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/15/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/2/2018 | 10/2/2018 | 10/16/2018 | | PASS |
Javier Guzman
|
|
|
10/15 L2 AT&T ePlan, pend eng
|
Routing Off Site - STRUCTURAL | 10/2/2018 | | 10/16/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers Chris Holladay
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/16/2018 | | DONE |
|
|
|
email permit to jfouts@ymcinc.com
|
1st review completed | | | 10/15/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/2/2018 | | 10/13/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 10/2/2018 | | 10/2/2018 | | PASS |
Nicolette Womack
|
|
|
|
Intake Approval | | | 10/2/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 9/25/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Plans drawn on 18”x24” minimum size plan sheets. (currently 23 drawing plans on 11” x 17”)
• Plan sheets E1.1, RF1.0, RF1.1 are required to stamped by the Idaho licensed engineer
• Provide a completed special inspection form 310 found at our website at https://pds.cityofboise.org/media/104147/final310_special_inspections.pdf for the welding found at the platform reinforcement on plan sheet S1.5 and connections details found on plan sheet S1.4
|
Application received | | | 9/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 10 2018 4:48PM
|
First Notice | 6/6/2019 | 6/6/2019 | | | |
Jim Storey
|
|
|
|