BLD-Final | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Brandon Shaw
|
|
|
Call ahead // Mark Phone #: ###-####
|
DOC - Permit Finaled | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 3/28/2019 | 3/28/2019 | 3/29/2019 | P | PEND |
Tony Young
|
|
|
drainage issues from neighbor,, talked with the contractor about it..
|
Zoning Approval | 3/29/2019 | 3/29/2019 | 3/29/2019 | | DONE |
Ted Vanegas
|
|
|
|
BLD-Energy code compliance | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Tony Young
|
|
|
Mark- Phone #: ###-####
|
BLD-Framing/Rough-in | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PASS |
Tony Young
|
|
|
Mark Phone #: ###-####-0380,, ok to insulate
|
BLD-Wall cover | 11/19/2018 | 11/19/2018 | 11/19/2018 | P | PASS |
Tony Young
|
|
|
Gary Phone #: ###-####,, exterior ok
|
BLD-Conference | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | PASS |
Tony Young
|
|
|
Gary Phone #: ###-####,, general frame ?s
|
BLD-Foundation | 10/15/2018 | 10/15/2018 | 10/15/2018 | P | PART |
Tony Young
|
|
|
Adam Phone #: ###-#### pour time 3:00,, work in progress
|
BLD-Footing | 10/12/2018 | 10/12/2018 | 10/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Concrete at 2 Adam Phone #: ###-####
|
BLD-Footing | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | NR |
Dave Hannah
|
|
|
Gary Phone #: ###-#### need a prop line set for set backs
|
Issue PAID IN FULL permit | | | 9/21/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/18/2018 | | |
|
|
|
|
OVERRIDE | | | 9/18/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 9/18/2018 | 9/18/2018 | 9/18/2018 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 9/11/2018 | 9/11/2018 | 9/18/2018 | | PASS |
Josh Bogle
|
|
|
09/17 ADU, paper - 1st done
|
Inspection Record Card- Bld | | | 9/18/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 9/18/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2018 | | DONE |
Josh Bogle
|
|
|
|
Override - Parcel Holds | | | 9/18/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 9/18/2018 | | DONE |
|
|
|
Appeal Period ends 5pm 9/20
waiting for Impact fees police park & fire
|
Plan resubmittals received | | | 9/18/2018 | | DONE |
|
|
|
Resubmittals recieved 2 sets of sheets A1.0, A2.0 & A3.0-put on JAB's chair-contractor will be back shortly
|
Routing - PLAN CHECK | 9/18/2018 | | 9/18/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 9/17/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 9/17/2018 | | 9/17/2018 | | FAIL |
Josh Bogle
|
|
|
venting & fire separation issues
|
Routing - MECHANICAL | 9/11/2018 | | 9/17/2018 | | PASS |
Troy James
|
|
|
Energy star fan installed for mechanical ventilation
|
Routing - PLANNING | 9/11/2018 | | 9/11/2018 | | PASS |
Brent Moore
|
|
|
|
Routing - Addressing | 9/11/2018 | | 9/11/2018 | | PASS |
Doug Chausow
|
|
|
ADU Address: 1603 N 7th St
|
Routing - PUBLIC WORKS | 9/11/2018 | | 9/11/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/11/2018 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 9/11/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/11/2018 | | DONE |
|
|
|
|
Application received | | 9/11/2018 | | | |
|
|
|
|