BLD-Final | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.87
|
BLD-Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | NR |
Brandon Shaw
|
|
|
Need PLM and ELE finals...
|
PubWorks Occupancy Approval | 1/29/2019 | 1/29/2019 | 1/29/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Other | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Energy code compliance | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending under floor and plumbing insulation...
|
BLD-Framing/Rough-in | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PEND |
Brandon Shaw
|
|
|
Remove dryer duct from garage seperation wall, as per discussion... OK to insulate...
|
BLD-Framing/Rough-in | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | DEFR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick// washer and dryer in the garage// membrane wall protection not clear as to how planreviewer meets code.
|
BLD-Wall Bracing | 12/20/2018 | 12/20/2018 | 12/20/2018 | A | PART |
Brandon Shaw
|
|
|
First floor only... Work in progress...
|
BLD-Footing | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | CANC |
Brandon Shaw
|
|
|
Already poured
|
BLD-Foundation | 11/8/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Brandon Shaw
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/5/2018 | 11/6/2018 | 11/5/2018 | A | CANC |
Brandon Shaw
|
|
|
Inspection cancelled via mobile web on Monday, November 05, 2018.
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | NR |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell still working on spredding boards and no geo tect sign off
|
PubWorks Subgrade Approval | 11/5/2018 | 11/5/2018 | 11/5/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 10/25/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/25/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/3/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 9/13/2018 | 9/13/2018 | 10/3/2018 | | DONE |
Jenny Nelson
|
|
|
10/02 sfd L2 ePlan
|
Routing - PLAN CHECK | 9/13/2018 | | 10/3/2018 | | PASS |
Jenny Nelson
|
|
|
Per JJN review. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/3/2018 | | DONE |
|
|
|
met
|
Routing - FIRE | 9/13/2018 | 9/13/2018 | 10/1/2018 | | PASS |
Erika Akin
|
|
|
New SFH 4985 fire flow area, 1750 gpm available. Per alternate request signed 9-6-18, fire flow duration is allowed to be reduced to achieve flow required for homes up to 5000 square feet in Harris Ranch North. Hydrant proximity, access and WUI checked and compliant.
|
1st review completed | | | 10/1/2018 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 9/13/2018 | | 9/17/2018 | | PASS |
Michael Zawacki
|
|
|
Foothills lot, site prep inspection required.
|
Routing - Addressing | 9/13/2018 | | 9/17/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 9/13/2018 | | 9/17/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/13/2018 | 9/16/2018 | 9/14/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 9/13/2018 | | 9/14/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Grading-Hillside | 9/14/2018 | | 9/14/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/13/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 9/13/2018 | | 9/13/2018 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 9/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 12 2018 1:35PM
|