BLD-Final | 2/5/2019 | 2/6/2019 | 2/6/2019 | A | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
DOC - Permit Finaled | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 2/6/2019 | 2/6/2019 | 2/6/2019 | A | DONE |
Jim Storey
|
|
|
Adam Phone #: ###-#### 3.2
|
BLD-Framing/Rough-in | 11/21/2018 | 11/26/2018 | 11/26/2018 | A | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Energy code compliance | 11/21/2018 | 11/26/2018 | 11/26/2018 | A | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | PART |
Jim Storey
|
|
|
Adam Phone #: ###-#### web bracing a4/a3// naill girder d5g/ ok to insulate
|
BLD-Wall Bracing | 10/29/2018 | 10/30/2018 | 10/30/2018 | P | PASS |
Brandon Shaw
|
|
|
shear // Jarrett Phone #: ###-####
|
BLD-Foundation | 10/9/2018 | 10/9/2018 | 10/9/2018 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
BLD-Footing | 10/4/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
Issue PAID IN FULL permit | | | 10/2/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/2/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/27/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 9/13/2018 | 9/13/2018 | 9/27/2018 | | DONE |
Jenny Nelson
|
|
|
09/26 sfd L1 ePlan 1st review complete 9/21 foundation spread footing, wall bracing, beams at patio
|
Routing - PLAN CHECK | 9/27/2018 | | 9/27/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/27/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/13/2018 | | 9/21/2018 | | FAIL |
Jenny Nelson
|
|
|
As per JJN
|
1st review completed | | | 9/21/2018 | | FAIL |
|
|
|
Foundation spread footings, provide beams at patio, wall bracing
|
Route to Impact Fee Review | 9/13/2018 | 9/16/2018 | 9/14/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 9/13/2018 | | 9/14/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/13/2018 | | 9/13/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 9/13/2018 | | 9/13/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/13/2018 | | 9/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/13/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2018 | | DONE |
|
|
|
|
Application received | | | 9/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 12 2018 4:48PM
|