Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-03401
StatusIssued
Name CHRISTENSEN HOMES
Site Address 2826 N 28TH ST
Project NameAbel Residence
Customer Number 
ePlanReviewYes
Description
**PLAN MOD - Changing foundation to crawl space, changes to floor plan, new sq ft is 5639 sq ft. Now has 6 bedrooms and 5.5 bathrooms. Garage now 976 sq ft. ONLY ONE STOVE ALLOWED IN HOUSE. JJN 05/20/19** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 4935 sq. ft., one story single family dwelling with 4 bedrooms, 3.5 bathrooms, approximately a 878 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/28/20207/29/20207/29/2020ANR
DetailsTony Young
Phone #: ###-#### Inspection requested via web by chad christensen// needs trades,, driveway cut and hard surface or fire / zoning approval as is// smoke detector outside of bedrooms in 2nd area// (not a duplex,, see project scope)// firecaulking in firewalls// address visible from 28th// landings or steps at doors// firedoor// etc called and left a voicemail
BLD-Aging Inspection4/30/20204/30/20205/4/2020 PEND
DetailsTony Young
BLD-Aging Inspection4/29/20204/29/20204/30/2020 PEND
DetailsTony Young
BLD-Wall cover12/16/201912/17/201912/17/2019APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by chad christensen
BLD-Framing/Rough-in12/10/201912/11/201912/11/2019APART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by chad christensen,, c/n posted,, ok to insulate,, needs to have full sprinkler pass prior to cover
BLD-Energy code compliance11/14/201911/14/201911/14/2019PNR
DetailsTony Young
Phone #: ###-#### Inspection requested via web by chad christensen
BLD-Framing/Rough-in11/13/201911/13/201911/13/2019PNR
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by chad christensen
BLD-Wall Bracing8/14/20198/15/20198/15/2019APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by chad christensen needs to add two hd hold downs each side of front door ok to cover ext
BLD-Foundation7/15/20197/15/20197/15/2019PPASS
DetailsDave Hannah
Nate Phone #: ###-####
BLD-Footing7/9/20197/9/20197/9/2019PPART
DetailsTony Young
Nate Phone #: ###-####,, work in progress,, setbacks appear ok,, pin on side is apparently in the tree,, contractor noted that he would take full responsibility via phone call with concrete guys phone
OVERRIDE  7/1/2019  
Routing - FIRE6/28/20196/28/20197/1/2019 PASS
DetailsMark Scharfen
Building shown with fire sprinklers. Uploaded rev_fire 07.01.2019.pdf.
Plan assigned to (J_N)5/16/20195/16/20197/1/2019 DONE
DetailsJenny Nelson
resubmitt/plan mod. 3rd, failed fire. 2nd review, failed planning, need engineering for pre-fab green house. 1st complete 5/20 not all plans match updated structure, failed planning, waiting on fire review
Permit Ready to Issue  7/1/2019 DONE
need GC form
Issue PAID IN FULL permit  7/1/2019 DONE
Inspection Record Card- Bld  7/1/2019 DONE
Routing - FIRE6/28/20196/28/20196/28/2019 FAIL
DetailsMark Scharfen
06.26.2019-Completed fire review, inadequate fire flow. uploaded rev_fire 06.28.2019.pdf.
Routing - FIRE6/21/20196/21/20196/27/2019 FAIL
DetailsMark Scharfen
completed fire review 06.27.2019. Uploaded rev_fire 06.27.2019.pdf and emailed to applicant.
Routing - PLANNING6/21/2019 6/21/2019 PASS
DetailsSue Cummings
Only one kitched now
Routing - PLAN CHECK6/21/2019 6/21/2019 PASS
DetailsJenny Nelson
Routing - FIRE5/31/20195/31/20196/10/2019 FAIL
DetailsMark Scharfen
06.10.2019-Completed fire review. uploaded rev_fire 06.10.2019.pdf and emailed applicant.
Routing - PLAN CHECK6/5/2019 6/5/2019 FAIL
DetailsJenny Nelson
Need engineering for pre-fab green house. Failed planning due to 3 kitchens - needs approval for adu or duplex.
Routing - PLANNING5/31/2019 5/31/2019 FAIL
DetailsSue Cummings
STILL HAS THREE KITCHENS. Please change the floor plan.
Routing - FIRE5/17/20195/17/20195/22/2019 FAIL
DetailsMark Scharfen
Completed review. Structure exceeds fd access, hydrant access and no fire flow letter. Uploaded rev_fire 05.22.2019.pdf and emailed contractor. Resubmittal required.
Routing - PLANNING5/17/2019 5/20/2019 FAIL
DetailsSue Cummings
Structure still has three kitchens. Only one is allowed unless approval of an ADU or a duplex is approved.
Routing - PLAN CHECK5/16/2019 5/20/2019 FAIL
DetailsJenny Nelson
Not all plans match structural updates
Plan resubmittals received  5/16/2019 DONE
Switching from slab to crawl space. (permit has never been issued)
Extend Review Timeline  3/15/2019 DONE
1st approved 180 day extension per adele. see documents
Meeting  3/14/2019 DONE
sent letter to alex informing this permit is going to expire soon and is welcome to send in a request for an extension. see documents
Meeting  3/14/2019 DONE
sent in request for extension
Expiration Notice2/25/20193/18/20192/25/2019 DONE
DetailsBrittany Hill
Meeting  11/19/2018 DONE
Flynner Properties not longer working on project. Permit is now under parcel owner
OVERRIDE  10/23/2018  
Plan assigned to (J_N)10/9/201810/9/201810/23/2018 DONE
DetailsJenny Nelson
10/09 sfd L1 ePlan. 2nd review 10/22, emergency escape window master bed. 1st review 10/10 update code year, specify egress windows, show mech equip on plans, specify girder trusses, update wind speed
Routing - PLAN CHECK10/23/2018 10/23/2018 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  10/23/2018 DONE
DetailsJenny Nelson
Permit Ready to Issue  10/23/2018 DONE
MET-need GC form
received a letter from the parcel owner-i emailed him the GC form to fill out and send back
Routing - PUBLIC WORKS10/22/2018 10/22/2018 PASS
DetailsBeverly Mountain
Routing - PLAN CHECK10/22/2018 10/22/2018 FAIL
DetailsJenny Nelson
Emergency escape window needed in master bedroom
Routing - PLANNING10/22/2018 10/22/2018 PASS
DetailsSue Cummings
No ADU approval at this time
1st review completed  10/10/2018 FAIL
Details
Update code year, egress windows, specify mech equipment on plans, specify girder trusses, update wind speed
Routing - PLAN CHECK9/25/2018 10/10/2018 FAIL
DetailsMichael Hanson
Plan assigned to (M_H)9/25/2018 10/9/2018 DEFR
DetailsMichael Hanson
10/09 #402 L1 ePlan
Route to Impact Fee Review9/25/20189/28/20189/26/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL9/25/2018 9/26/2018 PASS
DetailsChad Schwendiman
Routing - Addressing9/25/2018 9/26/2018 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  9/25/2018 DONE
Intake Approval  9/25/2018 PASS
Recd Pcfee & Taken To Pln CK  9/25/2018 DONE
Intake Approval  9/24/2018 FAIL
9/25/18 took out bath & second kitchen, will apply for ADU once approval with zoning is complete
9/24/18
plans and documents good
NEED APPROVAL FROM PLANNING FOR THE ADU ON OTHER SIDE OF GARAGE
Application received  9/18/2018 DONE
Application submitted via PDS Online on Sep 18 2018 2:46PM
Routing - PUBLIC WORKS9/25/2018   FAIL
DetailsBeverly Mountain
Per PW requirement verify structure does not encroach into existing Boise City Sanitary Sewer Easement. Called Kristy 9-25-18 bam
Routing - PLANNING9/25/2018   FAIL
Too many kitchens. Only one is allowed. Need a separate floor plan