BLD-Final | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.88
|
BLD-Energy code compliance | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon. Previously noted hardware not yet installed.
|
BLD-Framing/Rough-in | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PEND |
Brandon Shaw
|
|
|
Install CST strap per plans at tall wall, see framing pg... OK to insulate...
|
BLD-Wall Bracing | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending installation of remaining two hold downs and two anchor botls...
|
Routing - MECHANICAL | 3/5/2019 | | 3/5/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 2/22/2019 | 2/26/2019 | 2/26/2019 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs to be installed correctly... Anchor bolts to be no more than 12" from ends of sill plates... Need a ledible Approved set of plans...
|
BLD-Framing/Rough-in | 2/22/2019 | 2/26/2019 | 2/26/2019 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gus Brandon Inspection cancelled from web by: Gus Brandon
|
BLD-Foundation | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
OVERRIDE | | | 10/19/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/19/2018 | | 10/19/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 10/19/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 9/19/2018 | | 10/19/2018 | | DONE |
Michael Hanson
|
|
|
10/02 #402 L1 ePlan. 1st review completed - See changemarks in ePlan. MDH
|
Routing - PLAN CHECK | 9/19/2018 | | 10/1/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan. MDH
|
1st review completed | | | 10/1/2018 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan. MDH
|
Routing - MECHANICAL | 9/19/2018 | | 9/21/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/19/2018 | 9/22/2018 | 9/20/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 9/19/2018 | | 9/19/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 9/19/2018 | | 9/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2018 | | 9/19/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/19/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/19/2018 | | PASS |
Brittany Hill
|
|
|
|
Application received | | | 9/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 18 2018 4:11PM
|