BLD-Final | 10/16/2018 | 10/17/2018 | 10/17/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by rich prasch
|
DOC - Permit Finaled | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Footing | 10/10/2018 | 10/10/2018 | 10/11/2018 | P | PASS |
Jim Sly
|
|
|
Inspection can be done at anytime in the PM today. Alex will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
Issue PAID IN FULL permit | | | 10/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2018 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 9/19/2018 | 9/19/2018 | 9/28/2018 | | PASS |
Josh Bogle
|
|
|
09/25 patio cover, ePlan - 1st done
|
Routing - PLAN CHECK | 9/28/2018 | | 9/28/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 9/28/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 9/19/2018 | | 9/25/2018 | | FAIL |
Josh Bogle
|
|
|
needs engineered footings
|
1st review completed | | | 9/25/2018 | | DONE |
Josh Bogle
|
|
|
|
Application received | | | 9/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2018 2:24PM
|
Plans ACCEPTED BY PLAN TECH | | | 9/19/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/19/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 9/19/2018 | | 9/19/2018 | | PASS |
Sue Cummings
|
|
|
|