Second Notice | | 3/15/2020 | 3/17/2020 | | DONE |
|
|
|
This permit finaled on the web by Justin Dauby
|
First Notice | | 2/15/2020 | 3/5/2020 | | DONE |
|
|
|
mailed 3-6-20
|
Telephone call | | | 2/5/2020 | | DONE |
|
|
|
Called and emailed to let them know their occupancy is ready to issue and that we need the inspection card.
|
Permanent Occupancy | | | 2/5/2020 | | DONE |
|
|
|
|
BLD-Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Dave Hannah
|
|
|
Erik Phone #: ###-####
|
FIRE-Final Inspection | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Erik Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
FIRE-Final Inspection | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | CANC |
Jim Page
|
|
|
Reference noted entered by Troy on 21OCT2019 for life fire safety, this request is cancelled.
Eric Phone #: ###-####
|
Temporary Occupancy | 10/22/2019 | 1/20/2020 | 10/22/2019 | | DONE |
Brittany Hill
|
|
|
|
Print Occupancy Form | | | 10/22/2019 | | DONE |
|
|
|
|
BLD-Final | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PART |
Brandon Shaw
|
|
|
Temp C. of O. is OK'd for coffee bar area only...
|
FIRE-Final Inspection | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety has been approved per Joe Bruce. Still need the project related fire alarm permit issued/finaled prior to a final life safety inspection.
Eric Phone #: ###-####
|
BLD-Conference | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | DONE |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
FIRE-Conference | 9/19/2019 | 9/19/2019 | 9/19/2019 | A | DONE |
Jim Page
|
|
|
Fire conference is complete, a fire alarm contractor will need to be contacted, fire alarm notification is required for area of work, currently no notification is in place in lobby remodel.
|
FIRE-Final Inspection | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | CANC |
Jim Page
|
|
|
Request was for a conference, this request is cancelled.
Eric Phone #: ###-####
|
BLD-Framing/Rough-in | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, plaza west area ok for seating planter framing ok
|
FIRE-Final Inspection | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | CANC |
Jim Page
|
|
|
Wrong pemrit called in for fire life safety, this request is cancelled per conversation with point of contact.
Erik Phone #: ###-####
|
BLD-Framing/Rough-in | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | PART |
Brandon Shaw
|
|
|
Southwest corner in ground planter, rebar... Southeast corner planter boxes, framing...
|
BLD-Framing/Rough-in | 3/25/2019 | 3/25/2019 | 3/25/2019 | P | PART |
Tony Young
|
|
|
Eirc Phone #: ###-####,, bench frame on the north/east corner
|
BLD-Framing/Rough-in | 3/15/2019 | 3/15/2019 | 3/18/2019 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
BLD-Foundation | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, s/e planter slab area
|
Plan assigned to (CJW) | 12/20/2018 | 12/20/2018 | 2/11/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - Boise Plaza Lobby Remodel (routed to structural)
|
Plan Reviewer's activity | | | 2/11/2019 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 2/11/2019 | | DONE |
|
|
|
Plan mod please do not re issue
|
Print Occupancy Form | | | 2/11/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/11/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 2/6/2019 | | 2/7/2019 | | PASS |
Carl Westfall
|
|
|
Howie Henrikson / Jared Bauder (Jacobs)
|
Routing - PLAN CHECK | 2/5/2019 | | 2/6/2019 | | PASS |
Carl Westfall
|
|
|
pending structural
|
Plan resubmittals received | | | 2/5/2019 | | DONE |
|
|
|
|
BLD-Foundation | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PART |
Brandon Shaw
|
|
|
Work in progress... Planter A...
|
Routing - FIRE | 1/9/2019 | 1/9/2019 | 1/25/2019 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing PW Environmental | 1/10/2019 | | 1/25/2019 | | PASS |
Terry Alber
|
|
|
Per BCC10-5-12-3, and relayed via phone conversation (1/25/19) with Sean Drake of Cator Ruma, grease abatement is required for coffee bar.
|
Plan resubmittals requested | | | 1/25/2019 | | DONE |
|
|
|
|
BLD-Other | 1/22/2019 | 1/22/2019 | 1/22/2019 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-#### fire prof floor pens.
|
Routing Off Site - STRUCTURAL | 1/9/2019 | | 1/22/2019 | | FAIL |
Carl Westfall
|
|
|
Howie Henrikson / Jared Bauder (Jacobs)
|
BLD-Conference | 1/9/2019 | 1/9/2019 | 1/10/2019 | P | PEND |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
Routing - PLUMBING | 1/9/2019 | | 1/10/2019 | | PASS |
Daryl Spivey
|
|
|
See redline notes. Per plan and ISPC
|
Routing PW Sewer Rating | 1/9/2019 | | 1/10/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLAN CHECK | 1/7/2019 | | 1/9/2019 | | PASS |
Carl Westfall
|
|
|
pending structural
|
Routing Off Site - C.D.H | 1/7/2019 | | 1/7/2019 | | PASS |
Carl Westfall
|
|
|
Drawings signed and dated 12-17-18 by CDH submitted on 1-7-19.
|
Plan Modification Accepted | | | 1/7/2019 | | DONE |
|
|
|
Task in ePlanReview received
|
Plan Modification Accepted | | | 12/20/2018 | | DONE |
|
|
|
plan mod accepted in e plan-concierge desk, coffee bar, meeting pods & post/canopies-struc cals-assigned to Carl W
|
Print Occupancy Form | | | 11/8/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/8/2018 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/20/2018 | 9/20/2018 | 11/7/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 10/10/18 (L3 - 15 days) (ePlan - 24 sheets) Boise Plaza Lobby Renovation
|
Plan Reviewer's activity | | | 11/7/2018 | | DONE |
|
|
|
Received stamped and signed structural documents and uploaded them
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2018 | | DONE |
|
|
|
JDAUBY@DAUBYCONST.COM
MET
NEED
GC FORM
REVISED VALUE
|
Routing Off Site - STRUCTURAL | 10/24/2018 | | 11/5/2018 | | PASS |
Carl Westfall
|
|
|
Howie Henrikson / Jared Bauder (Jacobs)
|
Routing - PLAN CHECK | 10/23/2018 | | 10/24/2018 | | PASS |
Carl Westfall
|
|
|
Pending approval by structural
|
Plan resubmittals received | | | 10/23/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/15/2018 | 10/18/2018 | 10/16/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 10/15/2018 | | DONE |
|
|
|
|
Routing - FIRE | 9/20/2018 | 9/20/2018 | 10/12/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/12/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/20/2018 | | 10/12/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing Off Site - STRUCTURAL | 9/20/2018 | | 10/5/2018 | | FAIL |
Carl Westfall
|
|
|
Howie Henrikson / Jared Bauder (Jacobs)
|
Routing - PLUMBING | 9/20/2018 | | 9/21/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 9/20/2018 | | 9/21/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/20/2018 | | 9/20/2018 | | PASS |
Michael Zawacki
|
|
|
Minor TI in non-sensitive area, no ESC needed
|
Intake Approval | | | 9/20/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Joe accepted prescreen, let applicant know this was a major TI.
|
Routing - Addressing | 9/20/2018 | | 9/20/2018 | | PASS |
Laura Hunter
|
|
|
|
Application received | | | 9/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2018 3:22PM
|