Letter of compliance/Occupancy | | | 5/28/2019 | | DONE |
|
|
|
|
BLD-Final | 5/21/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Jim Storey
|
|
|
Lock box on front porch for the key, code is 3380 Phone #: ###-#### Inspection requested via web by Joe Perdew
|
DOC - Permit Finaled | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | DONE |
Jim Storey
|
|
|
Lock box on front porch for the key, code is 3380 Phone #: ###-#### Inspection requested via web by Joe Perdew 3.96
|
BLD-Aging Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | | PASS |
Jim Storey
|
|
|
|
Plan Modification Accepted | | | 1/4/2019 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 1/4/2019 | | 1/4/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Energy code compliance | 12/31/2018 | 12/31/2018 | 12/31/2018 | P | PASS |
Jim Storey
|
|
|
Insulation Inspection. Approved REScheck attached to wall by the staircase. Phone #: ###-#### Inspection requested via web by Joe Perdew
|
BLD-Framing/Rough-in | 12/26/2018 | 12/26/2018 | 12/26/2018 | P | PASS |
Jim Storey
|
|
|
Approved Plans sitting on the stair case Phone #: ###-#### Inspection requested via web by Joe Perdew
|
OVERRIDE | | | 11/27/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 11/26/2018 | 11/26/2018 | 11/27/2018 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 11/26/2018 | | 11/27/2018 | | PASS |
Rob Patrick
|
|
|
One hour minimum review charge to be added. Mechanical review not required per Troy.
|
Permit Ready to Issue | | | 11/27/2018 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 11/27/2018 | | DONE |
|
|
|
plan mod
|
Plan Modification Accepted | | | 11/26/2018 | | DONE |
|
|
|
adding windows
|
BLD-Foundation | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 10/22/2018 | 10/23/2018 | 10/24/2018 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Shelly Murphy
|
BLD-Foundation | 10/22/2018 | 10/23/2018 | 10/23/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Shelly Murphy
|
BLD-Foundation | 10/22/2018 | 10/23/2018 | 10/22/2018 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Shelly Murphy Inspection cancelled from web by: Shelly Murphy
|
Issue PAID IN FULL permit | | | 10/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/10/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 9/24/2018 | 9/24/2018 | 10/10/2018 | | DONE |
Rob Patrick
|
|
|
10/5 sfd L1 ePlan...10/5 Failed: Per Planning comment that plan must be one story
|
Routing - PLAN CHECK | 10/10/2018 | | 10/10/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/10/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 9/24/2018 | | 10/5/2018 | | FAIL |
Rob Patrick
|
|
|
Per Planning comment that plan must be one story.
|
Routing - PLANNING | 9/24/2018 | | 10/5/2018 | | PASS |
Leon Letson
|
|
|
|
1st review completed | | | 10/5/2018 | | FAIL |
Rob Patrick
|
|
|
Per Planning comment that plan must be one story
|
Route to Impact Fee Review | 9/24/2018 | 9/27/2018 | 9/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 9/24/2018 | | 9/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 9/24/2018 | | 9/25/2018 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/24/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/24/2018 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/24/2018 | | 9/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 9/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 21 2018 11:07AM
|