Third Notice | | 11/3/2019 | 11/26/2019 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Third Notice | | 9/25/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1 with second follow up
|
Second Follow up | | | 10/29/2019 | | DONE |
|
|
|
|
Third Notice | | 8/18/2019 | 9/20/2019 | | DONE |
|
|
|
mailed 9-23-19 with first follow up letter
|
First Follow up | | | 9/20/2019 | | DONE |
|
|
|
|
Third Notice | | 7/15/2019 | 8/13/2019 | | DONE |
|
|
|
mailed 8-13
|
Second Notice | | 6/20/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
First Notice | | 5/17/2019 | 6/10/2019 | | DONE |
|
|
|
mailed 6-11
|
BLD-Final | 5/7/2019 | 5/7/2019 | 5/7/2019 | P | PASS |
Dave Hannah
|
|
|
per Dave H. over the phone, inspection pass
Zack Phone #: ###-####
|
Permanent Occupancy | | | 5/7/2019 | | DONE |
|
|
|
|
BLD-Final | 4/19/2019 | 4/22/2019 | 4/22/2019 | A | PART |
Jim Storey
|
|
|
Zack Phone #: ###-#### health dept sign off/ mech permit resolved// ok to final upon all others sign offs
|
BLD-Final | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | NR |
Brandon Shaw
|
|
|
Need to have permit and plans readily available... Install all grab bars in ADA bathroom...
|
FIRE-Final Inspection | 4/18/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Mark Scharfen
|
|
|
Life saftey inspection complete. Zack will hang extinguishers before Building inspection.
Zack Phone #: ###-####
|
FIRE-Final Inspection | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | FAIL |
Troy Cobbley
|
|
|
The contractor actually just wanted a conference. I noted that the project related fire sprinkler pemit has not been finaled and the city approved plans indicate panic hardware at the rear exit door so panic hardware may be required at the front exit door from the space. The plans indicate that hardware is to be provided if not existing but not what type of hardware. Will also need exit signs and emergency lights placed as per plans. It does not appear to be any fire alarm notification devices with-in the space. Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/1/2019 | 4/2/2019 | 4/2/2019 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/27/2019 | 3/27/2019 | 3/28/2019 | P | NR |
Dave Hannah
|
|
|
Zach Phone #: ###-####
|
BLD-Framing/Rough-in | 2/22/2019 | 2/22/2019 | 2/22/2019 | P | PEND |
Dave Hannah
|
|
|
Zack Phone #: ###-#### plumbing location of toilet not in rigth spot and no grab bar backing
|
BLD-Framing/Rough-in | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/22/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 10/8/2018 | 10/8/2018 | 1/11/2019 | | PASS |
Joe Bruce
|
|
|
*(4th Rev Comp) 10/23 (L2) - Main Street Deli (Plan)
|
Plan resubmittals received | | | 1/11/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 1/11/2019 | | 1/11/2019 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/11/2019 | | DONE |
|
|
|
all met-NEED
ACHD-met
GC FORM-met
REVISED VALUE-met
do not issue without BLD19-00130
|
Routing - PLAN CHECK | 1/9/2019 | | 1/10/2019 | | FAIL |
Joe Bruce
|
|
|
|
Telephone call | | | 1/10/2019 | | DONE |
Joe Bruce
|
|
|
Spoke with Andrew Britt regarding additional corrections that are required on the plans. Another plan review cycle will be required to address necessary comments. **JHB**
|
Plan resubmittals requested | | | 1/10/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 11/21/2018 | | 11/23/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 11/23/2018 | | DONE |
Joe Bruce
|
|
|
Emailed the plan review report (2nd Review) to the architect. **JHB**
|
Plan resubmittals received | | | 11/21/2018 | | DONE |
Joe Bruce
|
|
|
Received resubmittal in ePlan. **JHB**
|
Route to Impact Fee Review | 10/24/2018 | 10/27/2018 | 10/24/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 10/8/2018 | | 10/24/2018 | | FAIL |
Joe Bruce
|
|
|
|
1st review completed | | | 10/24/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 10/24/2018 | | FAIL |
Joe Bruce
|
|
|
Emailed Plan Review Report to Architect on 10/24. **JHB**
|
Routing - FIRE | 10/8/2018 | 10/8/2018 | 10/23/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Addressing | 10/8/2018 | | 10/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/8/2018 | | 10/8/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/8/2018 | | 10/8/2018 | | PASS |
Nicolette Womack
|
|
|
|
Intake Approval | | | 10/4/2018 | | PASS |
|
|
|
|
Intake Approval | | | 9/25/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Provide plan sheets G1.1 and A1.1 with the Architects stamp that is signed and dated from the Idaho licensed architect
• Provide a stamped floor plan from CDH for the expansion.
• Provide on plans the furniture and fixture layout of the tenant space
|
Application received | | | 9/21/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 21 2018 5:36PM
|