BLD-Final | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tony Young
|
|
|
CLOBY Phone #: ###-####
|
DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | NH |
Tony Young
|
|
|
CLOBY Phone #: ###-####
|
BLD-Energy code compliance | 5/14/2019 | 5/15/2019 | 5/16/2019 | P | PASS |
Tony Young
|
|
|
Colby Phone #: ###-####
|
BLD-Framing/Rough-in | 5/10/2019 | 5/13/2019 | 5/14/2019 | P | PASS |
Tony Young
|
|
|
Cory Phone #: ###-####
|
BLD-Wall Bracing | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Other | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | PASS |
Jim Sly
|
|
|
second layer sheet rock // Phone #: ###-#### 1st floor
|
BLD-Wall Bracing | 4/3/2019 | 4/3/2019 | 4/3/2019 | P | PART |
Jim Sly
|
|
|
Colby-dry wall Phone #: ###-#### rated wall 1st layer OK.
|
BLD-Footing | 3/21/2019 | 3/21/2019 | 3/22/2019 | P | PART |
Tony Young
|
|
|
Colby Phone #: ###-####,, interior slab footings, work in progress, ok
|
BLD-Foundation | 3/7/2019 | 3/8/2019 | 3/8/2019 | P | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 3/6/2019 | 3/7/2019 | 3/7/2019 | A | PART |
Tony Young
|
|
|
Dane Phone #: ###-####,, work in progress
|
Issue PAID IN FULL permit | | | 2/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/11/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 1/10/2019 | 1/10/2019 | 1/11/2019 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 1/10/2019 | | 1/11/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/11/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 1/11/2019 | | DONE |
|
|
|
met
|
Routing - Design Review | 1/11/2019 | | 1/11/2019 | | PASS |
Josh Wilson
|
|
|
|
Plan assigned to (M_H) | 10/26/2018 | | 1/10/2019 | | DEFR |
Michael Hanson
|
|
|
10/16 sfd L2 ePlan...10/16 Failed; Corrections Needed 10/26 Failed arch sealed and wall bracing. 12/17 Failed arch sealed and wall bracing. MDH
|
Routing - PLAN CHECK | 12/17/2018 | | 12/17/2018 | | FAIL |
Michael Hanson
|
|
|
Failed arch sealed and wall bracing. MDH
|
Plan assigned to (RDP) | 9/27/2018 | 9/27/2018 | 10/26/2018 | | DEFR |
Rob Patrick
|
|
|
10/16 sfd L2 ePlan...10/16 Failed; Corrections Needed
|
Routing - PLAN CHECK | 10/26/2018 | | 10/26/2018 | | FAIL |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 9/27/2018 | | 10/16/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Needed
|
1st review completed | | | 10/16/2018 | | FAIL |
Rob Patrick
|
|
|
Correction Needed
|
Route to Impact Fee Review | 9/26/2018 | 9/29/2018 | 9/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 9/27/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/27/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/27/2018 | | PASS |
|
|
|
|
Routing - MECHANICAL | 9/27/2018 | | 9/27/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 9/27/2018 | | 9/27/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 9/27/2018 | | 9/27/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/27/2018 | | 9/27/2018 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | | 9/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2018 1:22PM
|