BLD-Final | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PASS |
Brandon Shaw
|
|
|
BRIAN Phone #: ###-####
|
DOC - Permit Finaled | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/8/2019 | 5/8/2019 | 5/8/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.6
|
BLD-Energy code compliance | 2/4/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Tony Young
|
|
|
Brian Phone #: ###-####
|
BLD-Framing/Rough-in | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Tony Young
|
|
|
Bryan Phone #: ###-####,, ok to insulate
|
BLD-Wall Bracing | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Footing | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PART |
Tony Young
|
|
|
Jeremy Phone #: ###-####
|
OVERRIDE | | | 11/6/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 10/16/2018 | 10/16/2018 | 11/6/2018 | | DONE |
Brian McGowan
|
|
|
10/17 sfd L1 ePlan - Corrections Required
|
Inspection Record Card- Bld | | | 11/6/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/6/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/6/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/6/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 10/31/2018 | | 10/31/2018 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 10/17/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/4/2018 | | 10/17/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 10/4/2018 | | 10/9/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/4/2018 | 10/7/2018 | 10/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/4/2018 | | 10/5/2018 | | PASS |
Brent Moore
|
|
|
|
Routing - Addressing | 10/4/2018 | | 10/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Plan assigned to (J_N) | 10/4/2018 | 10/4/2018 | 10/4/2018 | | DEFR |
|
|
|
Def. 10/17 sfd L1 ePlan
|
Routing - PUBLIC WORKS | 10/4/2018 | | 10/4/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/4/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/26/2018 | | FAIL |
|
|
|
MISSING
CORRECT LABELING
HEIGHT ON ELEVATION
|
Application received | | | 9/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 22 2018 3:58PM
|