Print Statement | | | 5/13/2019 | | DONE |
|
|
|
|
Third Notice | | 4/13/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
Second Notice | | 3/21/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4-11-19
|
First Notice | 3/5/2019 | 3/5/2019 | 3/11/2019 | | DONE |
Mike Jordan
|
|
|
mailed 3-12-19
|
BLD-Final | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | PASS |
Mike Jordan
|
|
|
jack Phone #: ###-####
|
FIRE-Final Inspection | 3/4/2019 | 3/5/2019 | 3/5/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Jack Phone #: ###-####
|
FIRE-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire sprinkler permits finaled prior to a life safety. Matt Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. INterior steel stud walls at first floor for new door and elec/mech rooms.
|
BLD-Ceiling Grid Inspection | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. 2nd. floor ok.
|
BLD-Framing/Rough-in | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Interior steel stud framed walls only ok.
|
Inspection Record Card- Bld | | | 11/1/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/1/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/4/2018 | 10/4/2018 | 10/31/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 10/15 L2 NxEdge ePlan
|
Routing - PLAN CHECK | 10/30/2018 | | 10/31/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2018 | | DONE |
|
|
|
Need:
GC form
Revised cert of value
|
Routing - PLAN CHECK | 10/23/2018 | | 10/29/2018 | | FAIL |
Javier Guzman
|
|
|
|
Route to Impact Fee Review | 10/17/2018 | 10/20/2018 | 10/18/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 10/4/2018 | 10/4/2018 | 10/17/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/17/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/4/2018 | | 10/17/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 10/4/2018 | | 10/9/2018 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 10/2/2018 | | PASS |
|
|
|
|
Application received | | | 9/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 26 2018 3:29PM
|