Second Notice | | 6/17/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Telephone call | | | 6/14/2019 | | DONE |
|
|
|
Left a message to Chris at ###-#### to get an updated address for Arbor Finish Carpentry because the 1st notice for final request was returned to us.
|
First Notice | | 6/1/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
Print Occupancy Form | | | 5/22/2019 | | DONE |
|
|
|
|
BLD-Final | 5/7/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Jim Sly
|
|
|
Call Chris Eby (General Contractor) 30 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby
|
FIRE-Final Inspection | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Corrections have been addressed. Chris Phone #: ###-####
Per Troy N/A for fire Alarm & Sprinkle work
|
FIRE-Final Inspection | 5/7/2019 | 5/9/2019 | 5/9/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide small documents, provide annual inspection for Kitchen Hood suppression system, remove doors as discussed between dining area and kitchen, remove lever hardware or provide panic on the doors between the kitchen and the rear exit corridor, provide verification of annual inspection for the fire sprinkler system.
Call Chris Eby (General Contractor) 30 minutes prior to inspection. Phone #: ###-#### Inspection requested via web by Chris Eby
|
Print Occupancy Form | | | 3/7/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/7/2019 | | DONE |
|
|
|
|
Expiration Notice | 3/6/2019 | 3/27/2019 | 3/6/2019 | | DONE |
Brittany Hill
|
|
|
|
Route to Impact Fee Review | 3/1/2019 | 3/4/2019 | 3/4/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (CJW) | 2/7/2019 | 2/7/2019 | 3/4/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 02/22/19 (L3 - 15 days) (ePlan - 5 sheets) Ramma Pong (l-3) (routed back to applicant)
|
Plan resubmittals received | | | 3/4/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/4/2019 | | 3/4/2019 | | PASS |
Carl Westfall
|
|
|
2nd IBC plan review approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/4/2019 | | DONE |
|
|
|
MET MIRA@RAMAPONG.COM
Need gc
need rev cert of val
|
Routing - PLAN CHECK | 2/7/2019 | | 3/1/2019 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 3/1/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/1/2019 | | DONE |
|
|
|
|
Routing - FIRE | 2/7/2019 | 2/7/2019 | 2/28/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Fire Code Review 02.28.2019.pdf uploaded.
|
Routing - PUBLIC WORKS | 2/7/2019 | | 2/13/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Environmental | 2/8/2019 | | 2/13/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 2/7/2019 | | 2/11/2019 | | PASS |
Troy James
|
|
|
Field verify.
|
Routing - PLANNING | 2/7/2019 | | 2/11/2019 | | PASS |
Nicolette Womack
|
|
|
No exterior modifications approved.
|
Routing - Addressing | 2/7/2019 | | 2/8/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address to match drawings.
|
Routing - PLUMBING | 2/8/2019 | | 2/8/2019 | | PASS |
Daryl Spivey
|
|
|
All fixtures to drain seperately to floor sink and increase water pipe sizing to 3/4 inch. Ice maker may require backflow protection.
|
Intake Approval | | | 2/4/2019 | | PASS |
|
|
|
|
Intake Approval | | | 1/24/2019 | | FAIL |
Joe Bruce
|
|
|
1) Sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space (4"x4" on the cover sheet) located 3” off the right sheet edge to allow for the title block. Submittal requirements can be found at: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
2) RESOLVED - Upload a current Central District Health Dept. plan review form. The uploaded form is from 6/1/16 and is no longer current. CDHD will need to review the current plans. A food menu will also be required to be uploaded for public works approval.
3) RESOLVED - The required plumbing fixtures are existing, but no plumbing fixture calculations were provided showing how the existing occupants and the new added occupant load will adequately serve the occupant load. Provide the plumbing fixture calculation for all occupants on the plans per IBC table 2902.1.
4) No fire resistive details provided on sheet A2.1 per checklist. It appears from the plans that new lighting is being installed in the rated floor/ceiling assembly. Provide details for all penetrations in the rated floor/ceiling assembly.
5) RESOLVED - Provide mechanical plans & calculations showing the increase demand for fresh air. The occupant load is being significantly increased and additional fresh air ventilation will need to be provided per checklist.
6) Provide plumbing plans with all required elements on the checklist. Several plumbing fixtures are being added. Since this is a food service occupancy, these plans will be required to be stamped by an engineer unless the applicant gets prior approval to have the architect stamp the plumbing plans.
7) Sheet index is incorrect and does not include the newly added mechanical plan. Revised cover sheet to include all sheets in plan set.
|
Intake Approval | | | 10/12/2018 | | FAIL |
Joe Bruce
|
|
|
1) Sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space (4"x4" on the cover sheet) located 3” off the right sheet edge to allow for the title block. Submittal requirements can be found at: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
2) Upload a current Central District Health Dept. plan review form. The uploaded form is from 6/1/16 and is no longer current. CDHD will need to review the current plans. A food menu will also be required to be uploaded for public works approval.
3) The required plumbing fixtures are existing, but no plumbing fixture calculations were provided showing how the existing occupants and the new added occupant load will adequately serve the occupant load. Provide the plumbing fixture calculation for all occupants on the plans per IBC table 2902.1.
4) No fire resistive details provided on sheet A2.1 per checklist. It appears from the plans that new lighting is being installed in the rated floor/ceiling assembly. Provide details for all penetrations in the rated floor/ceiling assembly.
5) Provide mechanical plans & calculations showing the increase demand for fresh air. The occupant load is being significantly increased and additional fresh air ventilation will need to be provided per checklist.
6) Provide plumbing plans with all required elements on the checklist. Several plumbing fixtures are being added. Since this is a food service occupancy, these plans will be required to be stamped by an engineer unless the applicant gets prior approval to have the architect stamp the plumbing plans.
|
Application received | | | 9/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2018 8:52AM
|