First Notice | 12/11/2018 | 12/11/2018 | 12/13/2018 | | DONE |
Mike Jordan
|
|
|
mailed 12-14
|
Letter of compliance/Occupancy | | | 12/12/2018 | | DONE |
|
|
|
|
BLD-Final | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Mike Jordan
|
|
|
Joe Phone #: ###-####
|
DOC - Permit Finaled | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PASS |
Mike Jordan
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/11/2018 | | DONE |
|
|
|
Should not have been finaled. not sure if 475 did by accident, doc final activity is gone blh 12-11-18
|
FIRE-Final Inspection | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, fire alarm inspection complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.Gale Phone #: ###-####
|
BLD-Framing/Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | P | PASS |
Jim Storey
|
|
|
early afternoon- please call ahead- Gill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/25/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/25/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/2/2018 | 10/2/2018 | 10/23/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 10/08 L1 Albertsons Riverview 2nd Floor ePlan
|
Routing - PLAN CHECK | 10/18/2018 | | 10/23/2018 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/23/2018 | | DONE |
|
|
|
jessica@falashcompanyinc.com
NEED
GC
Rev cert of val
|
Route to Impact Fee Review | 10/11/2018 | 10/14/2018 | 10/12/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 10/2/2018 | | 10/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 10/11/2018 | | FAIL |
Javier Guzman
|
|
|
|
Intake Approval | | | 10/2/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 9/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 27 2018 11:05AM
|