BLD-Framing/Rough-in | 3/8/2019 | 3/8/2019 | 3/8/2019 | P | PASS |
Tony Young
|
|
|
Brett Phone #: ###-####
|
BLD-Energy code compliance | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | PASS |
Tony Young
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2018 | 11/9/2018 | 11/10/2018 | P | PASS |
Dave Hannah
|
|
|
Kara Phone #: ###-####
|
Plan assigned to (BJM) | 10/10/2018 | 10/10/2018 | 11/8/2018 | | DONE |
Brian McGowan
|
|
|
Need the Plans for the proposed remodel before we can accept Plan Modifications.
|
BLD-Footing | 10/22/2018 | 10/23/2018 | 10/23/2018 | A | PASS |
Tony Young
|
|
|
Call on the way // Bret Phone #: ###-####,, added onto existing footing,, ok
|
Routing Walk-In (BLD) | 10/18/2018 | 10/18/2018 | 10/18/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/18/2018 | | 10/18/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/18/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 10/18/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/18/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/10/2018 | | 10/16/2018 | | FAIL |
Brian McGowan
|
|
|
Original Permit is for discovery demo only. There were no plans of the remodel provided. Proposed plans must be provided prior to making Plan Modifications.
|
1st review completed | | | 10/16/2018 | | FAIL |
Brian McGowan
|
|
|
|
Plan Modification Accepted | | | 10/10/2018 | | DONE |
|
|
|
plan mod received 1 set of calcs and A2.1-took to Brian B for review
|
Routing Walk-In (BLD) | 10/1/2018 | 10/1/2018 | 10/1/2018 | A | DONE |
Josh Bogle
|
|
|
|
1st review completed | | | 10/1/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/1/2018 | | 10/1/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 10/1/2018 | | DONE |
Brian McGowan
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 10/1/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/1/2018 | | DONE |
|
|
|
|
Application received | | 10/1/2018 | | | |
|
|
|
|