Second Notice | | 9/29/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
First Notice | 8/28/2019 | 8/28/2019 | 9/19/2019 | | DONE |
Mike Jordan
|
|
|
mailed 9-20-19
|
BLD-Final | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PASS |
Mike Jordan
|
|
|
Neil Phone #: ###-####
|
DOC - Permit Finaled | 8/28/2019 | 8/28/2019 | 8/28/2019 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 8/23/2019 | 8/26/2019 | 8/26/2019 | P | FAIL |
Mike Jordan
|
|
|
Neil Phone #: ###-####. Provide 34 inch max counter height for breakroom counter to meet ADA requirements.
|
FIRE-Final Inspection | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Single action hardware to be provided prior to a building inspection as discussed.
NEIL Phone #: ###-####
|
BLD-Final | 8/22/2019 | 8/23/2019 | 8/22/2019 | A | CANC |
Mike Jordan
|
|
|
NOT READY -NEIL Phone #: ###-####
|
BLD-Framing/Rough-in | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | PASS |
Mike Jordan
|
|
|
Neil Phone #: ###-####
|
Inspection Record Card- Bld | | | 11/19/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 10/10/2018 | 10/10/2018 | 11/16/2018 | | PASS |
Joe Bruce
|
|
|
*(1st Rev Comp) 11/05 (L3) - Vanilla T.I.
|
Routing - PLAN CHECK | 11/14/2018 | | 11/16/2018 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/16/2018 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Plan resubmittals received | | | 11/14/2018 | | DONE |
Joe Bruce
|
|
|
Received resubmittal in Eplan. **JHB**
|
Route to Impact Fee Review | 11/2/2018 | 11/5/2018 | 11/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - Design Review | 11/1/2018 | | 11/2/2018 | | PASS |
Josh Wilson
|
|
|
See email in uploaded in Eplan "Documents" folder. **JHB**
|
1st review completed | | | 11/2/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 11/2/2018 | | DONE |
Joe Bruce
|
|
|
Spoke to architect over the phone about plan corrections. Emailed him the plan review report. **JHB**
|
Routing - PLAN CHECK | 10/10/2018 | | 11/1/2018 | | FAIL |
Joe Bruce
|
|
|
See Plan Corrections in Plan Review Report. **JHB**
|
Routing - Addressing | 10/10/2018 | | 10/10/2018 | | PASS |
Doug Chausow
|
|
|
Corrected address 182 N Cole Rd
|
Intake Approval | | | 10/9/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/2/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
1. Provide a DR letter of approval for the exterior work
|
Application received | | | 10/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 1 2018 2:56PM
|