Letter of compliance/Occupancy | | | 12/5/2019 | | DONE |
|
|
|
|
BLD-Final | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Tony Young
|
|
|
To verify permanent occupany approval. Public Works approved perm.
|
OVERRIDE | | | 12/3/2019 | | |
|
|
|
|
PubWorks Occupancy Approval | 12/3/2019 | 12/3/2019 | 12/3/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
Plan assigned to (BJM) | 11/1/2019 | 11/1/2019 | 12/3/2019 | | DONE |
Brian McGowan
|
|
|
11/08 - Grading Plan
|
CHANGE STATUS TO (ISS) | | | 12/3/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/3/2019 | | 12/3/2019 | | PASS |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 12/3/2019 | | DONE |
|
|
|
plan mod approved, no fees due
|
Routing PW Grading-Hillside | 11/12/2019 | | 11/20/2019 | | PASS |
Melissa Jannusch
|
|
|
plan mod approved.
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLANNING | 11/8/2019 | | 11/19/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - PUBLIC WORKS | 11/8/2019 | | 11/12/2019 | | PASS |
Candy A. Nichols
|
|
|
plan mod
|
Temporary Occupancy | 11/8/2019 | 2/6/2020 | 11/8/2019 | | DONE |
Tisha Gallop
|
|
|
Permanent occupancy pending Public Works approval. Temp Co approved for 60 days (exp 1/7/20)
|
CHANGE STATUS TO (REV) | | | 11/8/2019 | | DONE |
|
|
|
|
BLD-Final | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Tony Young
|
|
|
John Phone #: ###-####,, temp occupancy ok
|
PubWorks Temp Occupancy Appr | 11/7/2019 | 11/7/2019 | 11/7/2019 | | DONE |
Melissa Jannusch
|
|
|
PLAN MOD APPROVAL REQUIRED PRIOR TO FINAL OCCUPANCY. Bond in place. A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works.
|
Plan Reviewer's activity | | | 11/5/2019 | | DONE |
Brian McGowan
|
|
|
Spoke with John about the Grading Plan lacking a few elevations that would clarify what was done. The "Retaining walls by others" were installed by Rock Placement and has engineering which he will email to me. The retaining walls by others follow the contour of the slope and are not dug in at the noted BW elevation or remain at the TW elevation on the plans.
|
Plan Modification Accepted | | | 11/1/2019 | | DONE |
|
|
|
Corey Barnes from Pivot North. Regarding final grading requested by Melissa. Sheet L1.1 Grading and Drainage Plan; Grading Inspection Letter from Civil Engineer.
|
Telephone call | | | 10/31/2019 | | DONE |
|
|
|
Per conversation with Melissa J. plan mod started on 9/13/19 was cancelled and not doing that scope work. Another plan mod needs to be submitted for changes to grading/landscaping and boulder walls. Will wait for applicant to call when ready to submit for newest plan mod to start workflow in ePlan.
|
BLD-Final | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | NR |
Tony Young
|
|
|
John Phone #: ###-####,, needs hillside approval,, driveway,, hand rails
|
Plan assigned to (BJM) | 9/13/2019 | 9/13/2019 | 10/11/2019 | | DONE |
Brian McGowan
|
|
|
09/30- Plan Modification-Hillside- SFD, retaining wall
Plan mod cancelled
|
CHANGE STATUS TO (ISS) | | | 10/10/2019 | | DONE |
|
|
|
Corey from Pivot came in to cancel plan mod. Spoke with Brian McGowan. Plan mod cancelled
|
BLD-Conference | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PART |
Tony Young
|
|
|
John Phone #: ###-####,, walk through on final.. hand rails,, trades,, hill side, fire caulking, etc
|
Routing - PLAN CHECK | 9/20/2019 | | 9/20/2019 | | PASS |
Brian McGowan
|
|
|
|
BLD-Aging Inspection | 9/6/2019 | 9/6/2019 | 9/13/2019 | | PEND |
Tony Young
|
|
|
|
Plan Modification Accepted | | | 9/13/2019 | | CANC |
|
|
|
Corey from Pivot came in to cancel plan mod. Spoke with Brian McGowan. Plan mod cancelled
Plan mod started 9/13/20109 - site retaining wall. Sheet L1.1 per Cory Barnes with Pivot North Architecture
|
BLD-Aging Inspection | 9/5/2019 | 9/5/2019 | 9/6/2019 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | PASS |
Tony Young
|
|
|
Phil Phone #: ###-####
|
BLD-Framing/Rough-in | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | PART |
Tony Young
|
|
|
Phil Phone #: ###-####,, ok to insulate,, needs 1 more sprinkler inspection prior to cover
|
BLD-Ceiling Grid Inspection | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PART |
Tony Young
|
|
|
soffit inspection // Phil Phone #: ###-####,, ok to start covering
|
Routing - MECHANICAL | 3/20/2019 | | 3/20/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
Routing - MECHANICAL | 3/11/2019 | | 3/11/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 3/1/2019 | 3/1/2019 | 3/1/2019 | P | PART |
Tony Young
|
|
|
shear// john Phone #: ###-####,, exterior ok
|
BLD-Footing | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Brandon Shaw
|
|
|
Bill-pour time 2:30 Phone #: ###-####1
|
BLD-Footing | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PASS |
Tony Young
|
|
|
2 pm pour time- Bill Phone #: ###-####
|
PubWorks Subgrade Approval | 12/13/2018 | 12/13/2018 | 12/13/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Inspection Record Card- Bld | | | 11/29/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/29/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/28/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 10/18/2018 | 10/18/2018 | 11/28/2018 | | DONE |
Brian McGowan
|
|
|
11/6 sfd L2 ePlan- 1st Review Complete
|
Routing - PLAN CHECK | 11/28/2018 | | 11/28/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/28/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/28/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 11/23/2018 | | 11/23/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.
|
Routing - FIRE | 11/21/2018 | 11/21/2018 | 11/21/2018 | | PASS |
Tim Frost
|
|
|
|
Routing PW Grading-Hillside | 11/14/2018 | | 11/14/2018 | | FAIL |
Melissa Jannusch
|
|
|
Retaining wall engineering and plan mod to grading
|
Plan Reviewer's activity | | | 11/8/2018 | | DONE |
Brian McGowan
|
|
|
Spoke with John Seidl. The designer/Architect has not resubmitted any drawings as of this date. Gave him a copy of the Corrections Required.
|
Routing - PLAN CHECK | 10/18/2018 | | 10/31/2018 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 10/31/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 10/19/2018 | | 10/30/2018 | | FAIL |
Melissa Jannusch
|
|
|
Provide structural engineering for reatining wall that accounts for the surcharge loading of the hill above.
|
Routing - FIRE | 10/18/2018 | 10/18/2018 | 10/25/2018 | | FAIL |
Tim Frost
|
|
|
Fire sprinklers required. See attached review.
|
Routing - MECHANICAL | 10/18/2018 | | 10/23/2018 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/18/2018 | | 10/22/2018 | | PASS |
Michael Zawacki
|
|
|
Foothills lot, site prep inspection required.
|
Route to Impact Fee Review | 10/18/2018 | 10/21/2018 | 10/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/18/2018 | | 10/19/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 10/18/2018 | | 10/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2018 | | 10/19/2018 | | PASS |
Rita DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/18/2018 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 10/18/2018 | | |
|
|
|
|
Override - Parcel Holds | | | 10/18/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/4/2018 | | FAIL |
|
|
|
informed applicant if plans are named exactly the same it will overlay
|
Intake Approval | | | 10/3/2018 | | FAIL |
|
|
|
Still need to upload grading and drainage plans with a more current date. Per Melissa can not accept 6/20/18
|
Application received | | | 10/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 2 2018 9:49AM
|
Intake Approval | | | 10/2/2018 | | FAIL |
|
|
|
see Brittany's email as well-CAT II Hillside permit approved under CFH18-00087. Please remove C1-1 Grading and Drainage Plan with stamp date of 6-21-2018. C1-1_Drainage Plan with a stamp date of 9-12-2018 is the most recent grading and drainage plan. Once the old plan is removed the application can be accepted for building permit review. --MMJ 10-2-2018
Also need plans to reflect the 2015 energy codes as well as the 2015 IRC codes
|