First Notice | 12/12/2019 | 12/12/2019 | 12/16/2019 | | DONE |
Jim Storey
|
|
|
This permit finaled on the web by Jimmy Martin
|
DOC - Permit Finaled | 12/12/2019 | 12/12/2019 | 12/12/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 12/11/2019 | 12/12/2019 | 12/12/2019 | P | PASS |
Jim Storey
|
|
|
Prefer 1pm if possible Phone #: ###-#### Inspection requested via web by Jimmy Martin
|
BLD-Framing/Rough-in | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jimmy Martin
|
FIRE-Final Inspection | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Jim Page
|
|
|
Final life fire safety inspection for scope of work complete, signature card not available at time of inspection.
Phone #: ###-#### Inspection requested via web by Jimmy Martin
|
BLD-Framing/Rough-in | 11/26/2019 | 11/27/2019 | 11/26/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Jimmy Martin Inspection cancelled from web by: Jimmy Martin
|
BLD-Aging Inspection | 11/8/2019 | 11/8/2019 | 11/8/2019 | | DONE |
Brandon Shaw
|
|
|
|
Extend Permit 90/180 days | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | DEFR |
Brandon Shaw
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/14/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | | 1/25/2019 | 2/28/2019 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 2/21/2019 | | 2/28/2019 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 2/28/2019 | | DONE |
|
|
|
PLAN MOD FEE ONLY UNDER BLD18-03640
|
Routing - PLAN CHECK | 1/28/2019 | | 2/1/2019 | | FAIL |
Julie Romig
|
|
|
|
Plan Modification Accepted | | | 1/25/2019 | | DONE |
|
|
|
Plan mod - revise Glu-Lam beam size at exposed walkway support to qualify as heavy timber and revise detail of dimensional walkway support beam to include full GWB wrap for fireproofing.
Include new column splice detail for replacing damaged portions of heavy timber columns.
|
Issue PAID IN FULL permit | | | 12/24/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/24/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 10/24/2018 | 10/24/2018 | 12/18/2018 | | DONE |
Julie Romig
|
|
|
12/17 - Pending Floodplain Approval - 1st Rev Comp - L3 Cottonwood Apartments Bldg 2
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/18/2018 | | DONE |
|
|
|
Need- all met
GC Form
Revised Cert of Value for each building (13 buildings)
(DO NOT ISSUE WITHOUT ALL 13 BUILDING PERMITS HAVE BEEN PAID)(BLD18-03640, BLD18-03644 TO BLD18-03655)
|
Routing - PLANNING | 12/13/2018 | | 12/18/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing PW Flood Plain | 12/13/2018 | | 12/13/2018 | | PASS |
Jason C. Taylor
|
|
|
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - PLAN CHECK | 12/13/2018 | | 12/13/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - PLANNING | 11/30/2018 | | 12/11/2018 | | FAIL |
Nicolette Womack
|
|
|
Appeal period ends December 17 at 5 pm for CFH18-00116.
|
Routing PW Flood Plain | 11/30/2018 | | 12/11/2018 | | FAIL |
Jason C. Taylor
|
|
|
Failed per ePlanReview.
|
Plan Reviewer's activity | | | 12/6/2018 | | DONE |
|
|
|
Permit cannot be issued until flood plain certificate CFH18-00116 is approved and the appeal period has passed. All other department reviews have passed.
|
Routing - PLAN CHECK | 11/30/2018 | | 12/6/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 11/30/2018 | | 12/3/2018 | | PASS |
Katelyn Menuge
|
|
|
No Design Review required. Current Planning to ensure floodplain approval.
|
Route to Impact Fee Review | 11/16/2018 | 11/19/2018 | 11/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 11/16/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 10/24/2018 | | 11/16/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 10/24/2018 | 10/24/2018 | 10/30/2018 | | CANC |
Adele J Schaffeld-Griffin
|
|
|
scope of work does not require fire plan review, will complete fire life safety insepction 11/16 - L3 Cottonwood Apartments Repair
|
Routing PW Flood Plain | 10/24/2018 | | 10/29/2018 | | FAIL |
Jason C. Taylor
|
|
|
Failed per ePlan Review
|
Routing - Design Review | 10/24/2018 | | 10/25/2018 | | FAIL |
Katelyn Menuge
|
|
|
No Design Review Required. Floodplain application required.
|
Intake Approval | | | 10/22/2018 | | PASS |
|
|
|
|
Application received | | 10/3/2018 | | | |
|
|
|
|