Third Notice | | 3/10/2020 | 3/20/2020 | | DONE |
|
|
|
This permit finaled on the web by Rupert Castilleja
|
Third Notice | | 2/12/2020 | 3/5/2020 | | DONE |
|
|
|
mailed 3-6-20
|
Third Notice | | 1/4/2020 | 2/7/2020 | | DONE |
|
|
|
mailed 2-10-20
|
Second Notice | | 12/6/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
First Notice | | 11/18/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
BLD-Final | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Dave Hannah
|
|
|
Casey Phone #: ###-####
|
Permanent Occupancy | | | 11/8/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection for this area of work is complete (Fire alarm permit FIR19-00268 is for the entire building, permit will remain in issued status until fire alarm inspection for entire building is complete), fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.
Casey Phone #: ###-####
|
FIRE-Final Inspection | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | FAIL |
Jim Page
|
|
|
Fire alarm failed inspection, fire alarm must be finaled before life fire safety can be completed.
Casey Phone #: ###-####
|
BLD-Final | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | CANC |
Dave Hannah
|
|
|
Call prior to going Phone #: 9282376335 >> Inspection requested via mobile web by Casey Huntley Inspection cancelled via mobile web on Wednesday, October 23, 2019.
|
Zoning Approval | 10/22/2019 | 10/22/2019 | 10/22/2019 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Conference | 10/11/2019 | 10/14/2019 | 10/14/2019 | A | DONE |
Dave Hannah
|
|
|
Call prior to going Phone #: 9282376335 >> Inspection requested via mobile web by Casey Huntley
|
BLD-Conference | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | DEFR |
Jim Storey
|
|
|
Call prior to going Phone #: 9282376335 >> Inspection requested via mobile web by Casey Huntley // wanted walk thru with insp. in charge of permit.
|
BLD-Conference | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | CANC |
Dave Hannah
|
|
|
Call prior to going Phone #: 9282376335 >> Inspection requested via mobile web by Casey Huntley
|
BLD-Ceiling Grid Inspection | 9/16/2019 | 9/16/2019 | 9/17/2019 | P | PASS |
Dave Hannah
|
|
|
Shane Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | PASS |
Dave Hannah
|
|
|
partial // Shane Phone #: ###-#### west side ok
|
BLD-Wall cover | 7/22/2019 | 7/22/2019 | 7/23/2019 | P | PASS |
Dave Hannah
|
|
|
dry wall // shane Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/8/2019 | 7/9/2019 | 7/9/2019 | P | PASS |
Dave Hannah
|
|
|
locker break room M/F ** shane Phone #: ###-####
|
BLD-Wall cover | 6/14/2019 | 6/14/2019 | 6/17/2019 | P | PASS |
Dave Hannah
|
|
|
CASEY Phone #: ###-####
|
BLD-Framing/Rough-in | 5/22/2019 | 5/23/2019 | 5/23/2019 | A | PART |
Dave Hannah
|
|
|
Shane Phone #: ###-#### area a ok to cover
|
BLD-Framing/Rough-in | 5/6/2019 | 5/7/2019 | 5/7/2019 | A | PART |
Dave Hannah
|
|
|
Shane Phone #: ###-#### ok to cover rlec and it room and top 4ft of walls
|
Fees Due Hold | 4/12/2019 | | 5/6/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Foundation | 4/5/2019 | 4/8/2019 | 4/9/2019 | P | PASS |
Dave Hannah
|
|
|
Shane Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/5/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (CJW) | 3/29/2019 | 3/29/2019 | 4/3/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - St Luke's Boise Surgery Center (routed to staff)
|
Plan Reviewer's activity | | | 4/3/2019 | | PASS |
|
|
|
Plan mod reviewed and approved
|
Permit Ready to Issue | | | 4/3/2019 | | DONE |
|
|
|
PLAN MOD
|
Routing - Erosion and Sediment | 4/2/2019 | | 4/3/2019 | | PASS |
Michael Zawacki
|
|
|
|
Routing - Design Review | 4/2/2019 | | 4/2/2019 | | PASS |
Katelyn Menuge
|
|
|
Plan Mod Pass
|
Routing - PLAN CHECK | 3/29/2019 | | 4/1/2019 | | PASS |
Carl Westfall
|
|
|
Plan intake and plan review passed
|
Plan Modification Accepted | | | 3/29/2019 | | DONE |
|
|
|
Revise existing passenger drop off area to meet current code compliance per plan review comments
|
Issue PAID IN FULL permit | | | 3/6/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/6/2019 | | DONE |
|
|
|
|
Telephone call | | | 2/15/2019 | | DONE |
|
|
|
Spoke with Brian Coleman, turned in a plan mod app, to see if this should be a resubmittal or not. He stated st lukes wants to pay and pick up the plans that have already been approved. Stated he will send me an email as a reminder for the plan mod once the are fully ready
|
Plan assigned to (CJW) | 10/12/2018 | 10/12/2018 | 2/6/2019 | | PASS |
Carl Westfall
|
|
|
(2nd done) 10/31/18 (L3 - 15 days) (ePlan - 126 sheets) St. Lukes Surgical Center
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/6/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/6/2019 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Routing - MECHANICAL | 1/31/2019 | | 2/4/2019 | | PASS |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 1/31/2019 | | 2/4/2019 | | PASS |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Plan Reviewer's activity | | | 1/31/2019 | | DONE |
|
|
|
Routing was delayed until stamped and signed mechanical plans were received.
|
Routing - PLAN CHECK | 1/25/2019 | | 1/28/2019 | | PASS |
Carl Westfall
|
|
|
Pending structural - remember to upload the plan review report
|
Plan resubmittals received | | | 1/25/2019 | | DONE |
|
|
|
|
Routing - FIRE | 1/8/2019 | | 1/18/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan resubmittals requested | | | 1/18/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/8/2019 | | 1/15/2019 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - MECHANICAL | 1/8/2019 | | 1/11/2019 | | FAIL |
Troy James
|
|
|
Mechanical engineer to address the fire damper required as noted on mechanical floor plan per the building plan reviewer.
|
Routing - PLAN CHECK | 1/7/2019 | | 1/8/2019 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Plan resubmittals received | | | 1/7/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 11/30/2018 | 12/3/2018 | 12/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 11/30/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 11/30/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/12/2018 | | 11/30/2018 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 10/12/2018 | 10/12/2018 | 11/9/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing Off Site - STRUCTURAL | 10/12/2018 | | 10/29/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - MECHANICAL | 10/12/2018 | | 10/24/2018 | | FAIL |
Troy James
|
|
|
|
Routing PW Environmental | 10/16/2018 | | 10/23/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - PUBLIC WORKS | 10/12/2018 | | 10/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 10/12/2018 | | 10/15/2018 | | PASS |
Michael Zawacki
|
|
|
TI. No ESC required, owner responsible for good house keeping.
|
Routing - Design Review | 10/12/2018 | | 10/15/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLUMBING | 10/12/2018 | | 10/15/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan ISPC and NFPA 99.
|
Routing - Addressing | 10/12/2018 | | 10/15/2018 | | PASS |
Doug Chausow
|
|
|
|
Telephone call | | | 10/11/2018 | | DONE |
|
|
|
emailed Breanne after receiving the payment for the erosion-let her know we still needed RP, cert of val, GC & ACHD letter
|
Intake Approval | | | 10/11/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/5/2018 | | FAIL |
Joe Bruce
|
|
|
1) Provide an updated Certificate of Value that reflects a value for the mechanical, plumbing, electrical, and fire sprinkler/alarm values. A value of $0 cannot be accepted.
2) The special inspections form (#310) needs to be completely filled out with all the information on the 1st page. A signature from the owner (or owner's representative) is required.
3) Missing various sheets from the sheet index. Please upload: D100, P-100 thru P-500
4) Sheet M-600 is not listed on the sheet index. Please add to the sheet index on the cover sheet.
5) On your checklist is says there are no deferred items, however on sheet S001 several deferred submittals are noted. Please update your checklist to reflect deferred submittals.
6) Missing Site specific fire flow at hydrants letter from Suez Water Dept. Upload this into the documents folder.
|
Application received | | | 10/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 3 2018 3:26PM
|