Plan Reviewer's activity | | | 8/4/2020 | | DONE |
Michael Hanson
|
|
|
Spoke with Stacey from Exterior Concepts and discussed WUI applications for 3 layer stucco over foam and advised that none of the foam can be exposed to the exterior or open air. Also advised for him to contact Romeo G. and his department for approved means and methods for WUI protection. MDH
|
BLD-Wall Bracing | 7/22/2020 | 7/23/2020 | 7/23/2020 | A | PART |
Tony Young
|
|
|
Screened- Phone #: ###-####,, exterior nailing ok
|
BLD-Wall Bracing | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PART |
Tony Young
|
|
|
Screened- Phone #: ###-####// walk around only with framer// fix various areas as needed,, appears that all of exterior will need 5/8th sheetrock also
|
Routing - MECHANICAL | 7/15/2020 | | 7/15/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Aging Inspection | 6/10/2020 | 6/10/2020 | 6/11/2020 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 6/9/2020 | 6/9/2020 | 6/11/2020 | | PEND |
Tony Young
|
|
|
|
Fees Due Hold | 1/28/2020 | | 5/18/2020 | | DONE |
|
|
|
|
Print Statement | | | 3/18/2020 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PART |
Mike Jordan
|
|
|
James Phone #: ###-####. Conferance on sofit detail. Ok to sheet with OSB and install 5/8 type X rock and offset joints. will call for inspection after install of 5/8.
|
Routing - MECHANICAL | 1/27/2020 | | 1/27/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report. Plan mod fee does apply. 2 hours
|
Telephone call | | | 1/27/2020 | | DONE |
|
|
|
Called and left a message that the Manual J is ready for pick up.
|
BLD-Foundation | 10/10/2019 | 10/10/2019 | 10/13/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | DONE |
Tony Young
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
BLD-Footing | 9/29/2019 | 9/30/2019 | 10/2/2019 | P | PART |
Tony Young
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
|
PubWorks Subgrade Approval | 10/1/2019 | 10/1/2019 | 10/1/2019 | | DONE |
Melissa Jannusch
|
|
|
*MAIN HOME* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 9/30/2019 | 9/30/2019 | 9/30/2019 | A | PART |
Tony Young
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro,, work in progress on house footings,, needs soils approval
|
BLD-Footing | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | FAIL |
Brandon Shaw
|
|
|
No plans on site... Not rerady...
|
BLD-Footing | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Tony Young
|
|
|
JR Phone #: ###-####,, main retaining wall,, work in progress..
|
BLD-Footing | 7/8/2019 | 7/9/2019 | 7/9/2019 | A | PART |
Tony Young
|
|
|
JR Phone #: ###-####,, added wing footings ok after cleaning loose soils that has fallen in
|
PubWorks Subgrade Approval | 7/8/2019 | 7/8/2019 | 7/8/2019 | | DONE |
Melissa Jannusch
|
|
|
**Foundation outside previously place concrete*** (see e-mail for drawing) A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 7/2/2019 | 7/3/2019 | 7/3/2019 | A | NR |
Tony Young
|
|
|
JR Phone #: ###-####,, needs to verify setbacks,, also need to verify soils are ok on footing extension,, not ready
|
BLD-Footing | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PART |
Tony Young
|
|
|
jr Phone #: ###-####// work in progress,, on second upper retaining wall,, and southern wall
|
BLD-Footing | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | PEND |
Tony Young
|
|
|
JR Phone #: ###-####
|
BLD-Footing | 6/10/2019 | 6/10/2019 | 6/11/2019 | P | NR |
Tony Young
|
|
|
JR Phone #: ###-####,, needs newer soils report for approval for next northern areas
|
BLD-Footing | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | PART |
Brandon Shaw
|
|
|
*Southern RETAINING WALL* Work in progress...
|
PubWorks Subgrade Approval | 5/1/2019 | 5/1/2019 | 5/1/2019 | | DONE |
Melissa Jannusch
|
|
|
*Southern RETAINING WALL* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 4/26/2019 | 4/29/2019 | 4/29/2019 | P | NR |
Tony Young
|
|
|
JR Phone #: ###-####,, needs soils hillside approval 1st
|
Meeting | | | 3/13/2019 | | DONE |
|
|
|
plan mod came in for a material method change for fire-gave to M_H-he will talk to fire inspecotr and give to who ever it needs to go to
|
Issue PAID IN FULL permit | | | 12/26/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 12/4/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/4/2018 | | DONE |
|
|
|
|
Telephone call | | | 12/4/2018 | | DONE |
|
|
|
Left voicemail for Jason to inform him what fees are due and that the permit is ready.
|
Routing - PUBLIC WORKS | 12/3/2018 | | 12/4/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLAN CHECK | 12/4/2018 | | 12/4/2018 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 12/4/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/4/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 10/26/2018 | | 12/4/2018 | | DONE |
Michael Hanson
|
|
|
10/22 sfd L2 Paper. 1st review completed. See emailed plan review report. MDH
|
Routing PW Grading-Hillside | 11/23/2018 | | 12/3/2018 | | PASS |
Melissa Jannusch
|
|
|
Resubmittals + spa ok
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
|
Plan resubmittals received | | | 11/20/2018 | | DONE |
|
|
|
received two copies of form 310, sturctural calculations, lab testing report, and plan sheets A1, A1.1, A2, S0, S1, S2.1, S2.2, S3.1, S3.2, S4.1, S4.2, S4.3, S5.1, S5.2, S5.3; put on Michael Hansons desk
|
Routing - FIRE | 11/9/2018 | 11/9/2018 | 11/9/2018 | | PASS |
Lee G Meredith
|
|
|
Owner supplied letter stating that sprinklers will be provided in all rooms.
|
1st review completed | | | 11/6/2018 | | FAIL |
Michael Hanson
|
|
|
See emailed plan review report. MDH
|
Routing - PLAN CHECK | | | 11/6/2018 | | FAIL |
Michael Hanson
|
|
|
10/22 sfd L2 Paper...10/18 In review with Erosion and Mechanical. See emailed plan review report. MDH
|
Routing - FIRE | 11/1/2018 | 11/1/2018 | 11/1/2018 | | FAIL |
Lee G Meredith
|
|
|
See fire review comments
|
Plan assigned to (RDP) | 10/4/2018 | 10/4/2018 | 10/26/2018 | | DEFR |
Rob Patrick
|
|
|
10/22 sfd L2 Paper...10/18 In review with Erosion and Mechanical
|
Routing - MECHANICAL | | | 10/22/2018 | | PASS |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 10/18/2018 | | 10/18/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan with narrative and site map approved. Site preparation inspection is required before earthwork and after BMP installation. Listed RP needs to recertify or become interim RP to get permit
|
Routing - PUBLIC WORKS | 10/4/2018 | | 10/17/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/17/2018 | | 10/17/2018 | | PASS |
Nicolette Womack
|
|
|
Comply with the Fire Dept Memo 8-28-18 in CFH18-00085.
|
Routing PW Grading-Hillside | 10/4/2018 | | 10/16/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Route to Impact Fee Review | 10/4/2018 | 10/7/2018 | 10/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 10/4/2018 | | 10/4/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/4/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/4/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/4/2018 | | DONE |
|
|
|
|
Application received | | 10/4/2018 | | | |
|
|
|
|