BLD-Aging Inspection | 8/6/2020 | 8/6/2020 | 8/7/2020 | | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | PART |
Dave Hannah
|
|
|
The house has been approved plumbing and electrical. The HVAC has been approved for the second floor. The builder is requesting approval to apply gypboard to the second floor only. A follow on inspection will be scheduled for later next week? or when the fireplace chimney flue is installed. The delivery of the flue pipe has been delayed. Phone #: ###-#### Inspection requested via web by John Cloninger ok to cover second floor
|
BLD-Framing/Rough-in | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | PART |
Tony Young
|
|
|
Structural inspection prior to application of foam insulation. Third party inspection log on site. The roof deck will receive 8" of foam insulation on the underside. This inspection is to check to see if the City will approve the cover of the structural components for cover.The Electrical, Plumbing and Mechanical will be added after the insulation is installed. Phone #: ###-#### Inspection requested via web by John Cloninger/ top of floor/ceiling cavities ok to spray foam,, trades will be under,, structural engineer to inspect prior to foam..
|
OVERRIDE | | | 9/13/2019 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/13/2019 | | DONE |
|
|
|
Cancelled plan mod and work flow mistakenly stared on this permit.
|
BLD-Footing | 1/13/2019 | 1/14/2019 | 1/14/2019 | A | PEND |
Tony Young
|
|
|
Pouring caissons for grade beams to bear on. Continuous inspection will be provided by MTI and the pour time is noon. Phone #: ###-#### Inspection requested via web by John Cloninger,, ok pending special inspection report
|
BLD-Conference | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | PART |
Tony Young
|
|
|
piers ok per J Taylor,, pending special inspection report,, see his notes on this day
|
BLD-Footing | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | FAIL |
Brandon Shaw
|
|
|
Need soil subgrade submitted and approved by PW before inspection can be completed...
|
PubWorks Subgrade Approval | 1/10/2019 | 1/10/2019 | 1/10/2019 | | CANC |
Jason C. Taylor
|
|
|
Driller piers are regulated under the building code for Special Inspections. No subgrade report will be required, only special inspection reports from Third Party Inspections. Jason Taylor ###-#### .
|
OVERRIDE | | | 12/11/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 11/2/2018 | 11/2/2018 | 12/11/2018 | | DONE |
Jenny Nelson
|
|
|
11/21 sfd L2 ePlan. 3rd review failed mechanical and hillside. 2nd review, need ICC-ESR for foam insulation. mechanical and PW corrections. 1st review 11/15, carbon detectors, upper floor egress windows, ICC-ES reports
|
Inspection Record Card- Bld | | | 12/11/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/11/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 12/11/2018 | | 12/11/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/11/2018 | | DONE |
|
|
|
|
Routing - PLUMBING | 11/30/2018 | | 11/30/2018 | | PASS |
Dan Ediger
|
|
|
Per ISPC. Backflow requirements will be determined on receipt of the snowmelt and radiant design.
|
Routing - MECHANICAL | 11/29/2018 | | 11/29/2018 | | PASS |
Troy James
|
|
|
|
Routing PW Grading-Hillside | 11/27/2018 | | 11/27/2018 | | FAIL |
Melissa Jannusch
|
|
|
See unresolved changemark in ePlan
|
Routing - MECHANICAL | 11/20/2018 | | 11/20/2018 | | FAIL |
Troy James
|
|
|
Previous comments have not been addressed.
|
Routing - PLAN CHECK | 11/20/2018 | | 11/20/2018 | | PASS |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 11/19/2018 | | 11/19/2018 | | FAIL |
Jenny Nelson
|
|
|
Need ICC-ESR for foam insulation
|
Routing PW Grading-Hillside | 11/16/2018 | | 11/16/2018 | | FAIL |
Melissa Jannusch
|
|
|
see changemarks in e-plan
|
1st review completed | | | 11/15/2018 | | FAIL |
Jenny Nelson
|
|
|
ICC-ES report for ICF and foam insulation, upper floor egress windows, carbon detectors
|
Routing - PLAN CHECK | 11/2/2018 | | 11/15/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing PW Grading-Hillside | 11/2/2018 | | 11/14/2018 | | FAIL |
Melissa Jannusch
|
|
|
Driveway. See changemarks in ePlan for details
|
Routing - FIRE | 11/2/2018 | 11/2/2018 | 11/13/2018 | | PASS |
Lee G Meredith
|
|
|
New SFH
See fire review comments.
11-13-18 Cprey Barnes resubmitted cover drawing and a letter indicating that a NFPA 13D sprinkler system will be provided.
|
Route to Impact Fee Review | 11/2/2018 | 11/5/2018 | 11/6/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Erosion and Sediment | 11/2/2018 | | 11/5/2018 | | PASS |
Michael Zawacki
|
|
|
Foothills home. Site prep inspection required.
|
Routing - MECHANICAL | 11/2/2018 | | 11/5/2018 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer. They have not completed their mechanical design.
|
Routing - PLANNING | 11/2/2018 | | 11/5/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 11/2/2018 | | 11/2/2018 | | PASS |
Doug Chausow
|
|
|
Please note: address is on Winsome Pl, not Rd.
|
Routing - PUBLIC WORKS | 11/2/2018 | | 11/2/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/2/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 11/2/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/8/2018 | | FAIL |
|
|
|
Fire Department satisfaction of non-build agreement not in place for Win Hollow Subdivision. Unable to accept building permit applications for this subdivision until this is complete. All other plan submittal checklist requirements met.
|
Application received | | | 10/4/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 4 2018 4:24PM
|
BLD-Aging Inspection | 8/7/2020 | 8/7/2020 | | | |
Tony Young
|
|
|
|