Print Statement | | | 10/9/2019 | | DONE |
|
|
|
sent 1st late notice on final fees
|
Print Statement | | | 6/18/2019 | | DONE |
|
|
|
|
First Notice | | 5/20/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
Permanent Occupancy | | | 5/10/2019 | | DONE |
|
|
|
|
BLD-Final | 5/6/2019 | 5/7/2019 | 5/7/2019 | A | PASS |
Mike Jordan
|
|
|
Brian Phone #: ###-####. Ok for trmp occ. All issues resolved. Will be ok for perm occ. once plumbing signs perm.
|
BLD-Final | 5/3/2019 | 5/6/2019 | 5/6/2019 | P | PART |
Mike Jordan
|
|
|
Brian Phone #: ###-####. Ok for temp occ. Needs to provide code compliant lever hardware on tanning room doors. Also reviewed special inspection report mfor the welding for new RTU supports. Also provde prrof of tempered glass in doors to tanning area.
|
FIRE-Final Inspection | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Mark Scharfen
|
|
|
Checked extinguishers, exit lighting and emergency lighting. Passed fire life safety.
|
BLD-Final | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | NR |
Mike Jordan
|
|
|
Brian Phone #: ###-####. Needs fire sprinkler and fire/life/safety finals.
|
BLD-Ceiling Grid Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Jim Sly
|
|
|
Brian Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/26/2019 | 4/29/2019 | 4/29/2019 | P | NR |
Mike Jordan
|
|
|
Bryan Phone #: ###-####. Needs sprinkler rough in inspection first.
|
BLD-Framing/Rough-in | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PASS |
Mike Jordan
|
|
|
Brian Phone #: ###-####. Interior steel stud framed walls for phase 2, restrooms and locker rooms ok.
|
BLD-Framing/Rough-in | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | PASS |
Mike Jordan
|
|
|
Brian Phone #: ###-####. Interior steel stud framed walls, phase 2, tanning area and IT room.
|
BLD-Framing/Rough-in | 3/14/2019 | 3/15/2019 | 3/18/2019 | P | PART |
Dave Hannah
|
|
|
Bryan Phone #: ###-#### north high wall between gym and rooms ok to cover
|
BLD-Framing/Rough-in | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | PASS |
Mike Jordan
|
|
|
Bryan Phone #: ###-####. Interior steel stud framed walls and soffits only for phase 1.
|
CHANGE STATUS TO (ISS) | | | 3/4/2019 | | DONE |
|
|
|
plan mod paid
|
Print Occupancy Form | | | 3/4/2019 | | DONE |
|
|
|
|
Change Expiration Date Only | | | 3/4/2019 | | DONE |
|
|
|
re-issued by mistake. changed back to original exp date
|
Plan assigned to (JAR) | 2/22/2019 | 2/22/2019 | 2/28/2019 | | DONE |
Julie Romig
|
|
|
03/01 - Plan Mod - Planet Fitness Milwaukee Marketplace
|
Routing - PLAN CHECK | 2/22/2019 | | 2/28/2019 | | PASS |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 2/28/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan Modification Accepted | | | 2/21/2019 | | DONE |
|
|
|
Revision on Structural Sheets: S100 and S200. Structural Calculations
|
Issue PAID IN FULL permit | | | 1/28/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/28/2019 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 1/28/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 10/25/2018 | 10/25/2018 | 12/18/2018 | | DONE |
Julie Romig
|
|
|
*12/18 - 3rd Rev - 1st Rev Comp - L3 Planet Fitness
|
Routing - PLAN CHECK | 12/18/2018 | | 12/18/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - Design Review | 12/18/2018 | | 12/18/2018 | | PASS |
Katelyn Menuge
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/18/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 12/11/2018 | | 12/17/2018 | | FAIL |
Julie Romig
|
|
|
Plan review report emailed to architect.
|
Routing - FIRE | 12/11/2018 | 12/11/2018 | 12/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLANNING | 12/11/2018 | | 12/12/2018 | | PASS |
Celine Acord
|
|
|
per CUP18-00054. A sign permit is required for all signage proposed.
|
Routing - Design Review | 12/11/2018 | | 12/12/2018 | | PASS |
Katelyn Menuge
|
|
|
CZC18-00301
|
Routing - MECHANICAL | 12/11/2018 | | 12/12/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/11/2018 | | 12/12/2018 | | PASS |
Daryl Spivey
|
|
|
1) Install plumbing as shown on isometric pages.
2) Install tempering valve on public showers as required by ISPC 408.3.
|
Routing - PUBLIC WORKS | 12/11/2018 | | 12/12/2018 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 11/21/2018 | 11/24/2018 | 11/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 10/25/2018 | 10/25/2018 | 11/21/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 11/21/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 10/25/2018 | | 11/21/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 10/25/2018 | | 10/29/2018 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 10/25/2018 | | 10/26/2018 | | FAIL |
Celine Acord
|
|
|
Corrections required per ePlanReview
|
Routing - Design Review | 10/25/2018 | | 10/26/2018 | | FAIL |
Katelyn Menuge
|
|
|
Need Zoning Certificate for Exterior Modifications
|
Routing - Addressing | 10/25/2018 | | 10/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/25/2018 | | 10/25/2018 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Routing - PLUMBING | 10/25/2018 | | 10/25/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Intake Approval | | | 10/24/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/18/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
1. Provide planning and zoning letters of approval
2. Provide engineering calculations for the new roof top unit openings (engineering required to be stamped, dated and signed by an Idaho licensed engineer)
3. Provide commissioning Plan per IECC printed on the plans. Can also include a separate attached document. Form #308 IECC System Commissioning Agencies can be found at this link: http://pds.cityofboise.org/home/documents/apps/300/#
|
Application received | | | 10/5/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 5 2018 2:49PM
|