BLD-Footing | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PART |
Tony Young
|
|
|
JR Phone #: ###-####,, basement footings,, work in progress
|
Issue PAID IN FULL permit | | | 10/23/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/22/2018 | 10/25/2018 | 10/22/2018 | | PASS |
Eric Bilimoria
|
|
|
|
Permit Ready to Issue | | | 10/22/2018 | | DONE |
|
|
|
met
|
Inspection Record Card- Bld | | | 10/22/2018 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2018 | | DONE |
|
|
|
spoke with george informing permit is ready and fee amount due
|
1st review completed | | | 10/22/2018 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 10/22/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2018 | | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 10/8/2018 | | 10/22/2018 | | DONE |
Rob Patrick
|
|
|
Foundation Only Request; Paper...10/18 Waiting to get a valuation for a foundation and house attach only permit.
|
Routing - PLAN CHECK | 10/9/2018 | | 10/22/2018 | | PASS |
Rob Patrick
|
|
|
|
Plan resubmittals received | | | 10/15/2018 | | DONE |
|
|
|
One pack of Engineering taken to Rob
|
Routing - PLANNING | 10/15/2018 | | 10/15/2018 | | PASS |
Ted Vanegas
|
|
|
The garage is not included with this permit. Sign-off is for the house only.
|
Plans ACCEPTED BY PLAN TECH | | | 10/8/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/8/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/8/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 10/8/2018 | | 10/8/2018 | | FAIL |
Ted Vanegas
|
|
|
Proposed garage does not meet the 15' rear setback requirement. Garage needs to be moved or a variance approved.
|
Routing - Addressing | 10/8/2018 | | 10/8/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/8/2018 | | 10/8/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | 10/8/2018 | | | |
|
|
|
|