PubWorks Occupancy Approval | 12/30/2019 | 12/30/2019 | 12/30/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Aging Inspection | 12/24/2019 | 12/24/2019 | 12/26/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/23/2019 | 12/23/2019 | 12/26/2019 | | PEND |
Tony Young
|
|
|
|
OVERRIDE | | | 2/7/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 2/1/2019 | 2/1/2019 | 2/7/2019 | | PASS |
Josh Bogle
|
|
|
2/7 retaining wall, ePlan
|
Routing - PLAN CHECK | 2/1/2019 | | 2/7/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing - PLANNING | 2/1/2019 | | 2/7/2019 | | PASS |
Nicolette Womack
|
|
|
|
1st review completed | | | 2/7/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Override - Parcel Holds | | | 2/7/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 2/7/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/7/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/7/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 2/1/2019 | | 2/1/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 2/1/2019 | | 2/1/2019 | | PASS |
Michael Zawacki
|
|
|
|
Routing PW Grading-Hillside | 2/1/2019 | | 2/1/2019 | | PASS |
Melissa Jannusch
|
|
|
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - Addressing | 2/1/2019 | | 2/1/2019 | | PASS |
Laura Hunter
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/1/2019 | | DONE |
|
|
|
|
Intake Approval | | | 2/1/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 2/1/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/1/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/30/2019 | | FAIL |
|
|
|
Informed to upload documents into the documents folder and to not sign off on task until the zoning approval letter is uploaded
|
Intake Approval | | | 10/31/2018 | | FAIL |
|
|
|
nothing was completed
|
Telephone call | | | 10/30/2018 | | DONE |
|
|
|
Spoke with Andy L, once prescreen passes route to ESC and he will sign off in Eplan.
|
Intake Approval | | | 10/29/2018 | | FAIL |
|
|
|
1.Please see prescreen checklist items listed above.
2.Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Jason Taylor ###-####.
|
Routing - Erosion and Sediment | 10/16/2018 | | 10/16/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver approved. Certified RP designated.
|
Application received | | | 10/10/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 10 2018 11:30AM
|