Third Notice | | 12/1/2019 | 12/16/2019 | | DONE |
|
|
|
This permit finaled on the web by Todd Holbrook
|
Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | 10/8/2019 | 10/8/2019 | 10/29/2019 | | DONE |
Tony Young
|
|
|
mailed 11-1
|
Elevation Cert Rec'd-Final | | | 10/9/2019 | | DONE |
|
|
|
Recieved final EC. JCT
|
BLD-Final | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####
|
DOC - Permit Finaled | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 9/10/2019 | 9/11/2019 | 9/11/2019 | P | PART |
Tony Young
|
|
|
Todd Phone #: ###-####,,, plans only show 1 handrail?,, call into plan review for verification
|
Zoning Approval | 9/6/2019 | 9/6/2019 | 9/6/2019 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 8/14/2019 | 8/15/2019 | 8/15/2019 | A | NR |
Dave Hannah
|
|
|
Todd Phone #: ###-#### needs to finish paving and civil concrete work and ext handraiul;s
|
FIRE-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, this is for a vanilla space, fire exitnguishers will be placed with tenant inprovements. Final life fire safety inspection for area of work complete, as stated in project description, no occupancy allowed under this permit. Todd Phone #: ###-####
|
BLD-Energy code compliance | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Chesnut
|
BLD-Framing/Rough-in | 5/8/2019 | 5/9/2019 | 5/9/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Chesnut,, walls ok
|
Elevation Cert Rec'd-Midconst | | | 5/9/2019 | | DONE |
|
|
|
Elevation Certificate #2 has been recieved.
|
Routing PW Flood Plain | 5/9/2019 | | 5/9/2019 | | PASS |
Jason C. Taylor
|
|
|
Elevation Certificate #2 has been recieved.Framing inspection may be scheduled. JCT
|
BLD-Framing/Rough-in | 5/8/2019 | 5/8/2019 | 5/8/2019 | P | NR |
Tony Young
|
|
|
Todd Phone #: ###-####,, needs seal pack,, flood cert
|
Inspection Record Card- Bld | | | 5/8/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/8/2019 | | DONE |
|
|
|
plan mod
|
BLD-Wall Bracing | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####
|
OVERRIDE | | | 4/1/2019 | | |
|
|
|
|
Routing - PLUMBING | 3/28/2019 | | 4/1/2019 | | PASS |
Daryl Spivey
|
|
|
(Plan Mod) Per plan and ISPC.
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
PLAN MOD-do not re issue
|
Plan assigned to (JHB) | 3/22/2019 | | 4/1/2019 | | PASS |
Joe Bruce
|
|
|
04/01 (Plan Mod) Bogus Basin Retail
|
Routing - PLAN CHECK | 3/28/2019 | | 3/29/2019 | | PASS |
Joe Bruce
|
|
|
(Plan Mod)
|
Plan Reviewer's activity | | | 3/27/2019 | | DONE |
Joe Bruce
|
|
|
The applicant emailed me a revised sheet E1.0 to replace the prior sheet that was uploaded. This sheet has been uploaded into ePlan. **JHB**
|
Plan Modification Accepted | | | 3/22/2019 | | DONE |
|
|
|
Minor changes in electrical one line diagram. Minor changes to plumbing layout.
|
BLD-Concrete | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PART |
Tony Young
|
|
|
Jason Phone #: ###-####,, work in progress on founation wall
|
BLD-Footing | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Tony Young
|
|
|
Jason Phone #: ###-####,, work in progress
|
Inspection Record Card- Bld | | | 3/18/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/11/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 1/30/2019 | | |
|
|
|
|
Plan assigned to (JHB) | 10/18/2018 | 10/18/2018 | 1/30/2019 | | PASS |
Joe Bruce
|
|
|
*(3rd Rev Comp) 11/12 (L3) - Bogus Basin Retail (Flood Plain, Planning)
|
Routing PW Flood Plain | 1/25/2019 | | 1/30/2019 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
Routing - PLANNING | 1/25/2019 | | 1/30/2019 | | PASS |
Leon Letson
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 1/30/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/30/2019 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT BLD18-03807
NEED
met - GC FORM
met REVISED VALUE-met
|
Plan resubmittals received | | | 1/25/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLANNING | 1/17/2019 | | 1/22/2019 | | PASS |
Leon Letson
|
|
|
|
Routing PW Flood Plain | 1/17/2019 | | 1/22/2019 | | FAIL |
Jason C. Taylor
|
|
|
Upload corrected Elevation Certificates. Elevation Certificate elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####
|
Plan resubmittals received | | | 1/17/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan Reviewer's activity | | | 1/16/2019 | | DONE |
Joe Bruce
|
|
|
Resubmittal plans returned to architect since resubmittal comments from Jason Taylor were not addressed. **JHB**
|
Routing - PLANNING | 1/2/2019 | | 1/9/2019 | | FAIL |
Leon Letson
|
|
|
See Public Works Comments
|
Routing Off Site - STRUCTURAL | 1/2/2019 | | 1/9/2019 | | PASS |
Joe Bruce
|
|
|
AHJ
|
Plan resubmittals requested | | | 1/9/2019 | | FAIL |
Joe Bruce
|
|
|
Spoke with Doug Newell on the phone in regards to flood plain comments. **JHB**
|
Plan Reviewer's activity | | | 1/9/2019 | | DONE |
Joe Bruce
|
|
|
Multiple tasks in Eplan for Structural Plan review for AHJ were erroneous from out-sourced plan review. Carl Madsen has signed off on the task in Eplan after Chris Holladay approved the task on 1/9/2019. **JHB**
|
Routing - PLAN CHECK | 1/2/2019 | | 1/8/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing PW Flood Plain | 1/2/2019 | | 1/7/2019 | | FAIL |
Jason C. Taylor
|
|
|
Elevation Certificate needs uploaded and flood elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####
|
Plan resubmittals received | | | 1/2/2019 | | DONE |
Joe Bruce
|
|
|
Received plans and documents in Eplan. **JHB**
|
Routing - Design Review | 1/2/2019 | | 1/2/2019 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 11/15/2018 | 11/18/2018 | 11/15/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 10/18/2018 | 10/18/2018 | 11/15/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 11/15/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 11/15/2018 | | DONE |
Joe Bruce
|
|
|
Emailed Plan Review Report to architect. **JHB**
|
Routing - PLAN CHECK | 10/18/2018 | | 11/13/2018 | | FAIL |
Joe Bruce
|
|
|
Attached comments to case in Eplan. **JHB**
|
Routing - MECHANICAL | 10/18/2018 | | 10/24/2018 | | PASS |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 10/18/2018 | | 10/23/2018 | | FAIL |
Joe Bruce
|
|
|
AHJ
|
Routing PW Flood Plain | 10/18/2018 | | 10/23/2018 | | FAIL |
Jason C. Taylor
|
|
|
A portion of the subject property is within the regulatory floodplain. This project must comply with the Boise Floodplain Ordinance (B.C.C. 11-08). If you have any questions, please call Jason Taylor at ###-####.
|
Routing - PLANNING | 10/18/2018 | | 10/19/2018 | | FAIL |
Cody Riddle
|
|
|
Floodplain Development Permit Required.
|
Routing - Addressing | 10/18/2018 | | 10/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/18/2018 | | 10/18/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 10/18/2018 | | 10/18/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed. All SWPPP info provided on plan sheet C1.5
|
Routing - PLUMBING | 10/18/2018 | | 10/18/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 10/18/2018 | | 10/18/2018 | | FAIL |
Andrea Tuning
|
|
|
Flood Plain application is required.
|
Plan Reviewer's activity | | | 10/16/2018 | | DONE |
|
|
|
Asked Tisha to create 2nd permit for Reed Cycle. Building will have two permits. BLD18-03764 for shell/core and 2nd permit for north tenant space Reed Cycle for CO. Both reviewed under ePlan case BLD18-03764.
|
Intake Approval | | | 10/16/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/15/2018 | | FAIL |
Julie Romig
|
|
|
Need: 1. Owner signature on Form 310.
2. This permit application is for the Shell/Core of the full building area. It appears that there is a bike retail tenant for a portion of the building. If you'd like a Certificate of Occupancy for that tenant, please provide a PDF of a second 520 application with the square footage, occupant load, business name, and value specific to the bike retail space.
3. On Structural, Mechanical, Plumbing, and Landscape sheets, leave 4" x 2" blank space located 3" off the right sheet edge for City electronic stamp.
4. Stamp/signature on Structural sheets.
|
Application received | | | 10/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 12 2018 10:40AM
|