Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-03786
StatusTemporary Occupancy
Name VERTICAL CORP
Site Address 2404 W BANK DR Unit: 301
Project NameLaw Alternatives 301 Temp CO
Customer NumberBLD18-02699
ePlanReview 
Description
(TWO PERMITS IN EPLAN UNDER BLD18-02699) **(LAW ALTERNATIVES - SUITE 301) (Temporary Occupancy through June 30th, 2019)** // 11/28/18 PLAN MOD TO ADDRESS CODE DEFICIENCIES AT STAIR ENLCSOURE AND EXTEND FIRE BARRIER WALL TO DECK AT ALL FLOORS AND PROVIDE HANDRAIL ON BOTH SIDES OF STAIR. JAR // Permit for a temporary certificate of occupancy for an existing 1,253 sq ft office tenant on the third floor. No work under this permit. The remainder of the floor is remodeled under permit BLD18-02699 for Fifty Flowers Suite 350. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the building’s Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 and NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Change Expiration Date Only  7/15/2020 DONE
BLD-Aging Inspection7/13/20207/13/20207/13/2020 PASS
DetailsJim Storey
Upgrade Agreement attached for this permit and for permit BLD18-02699.jcb
Plan Reviewer's activity  6/10/2020 DONE
DetailsJason Blais
Upgrade Agreement attached for this permit and for permit BLD18-02699.
Change Expiration Date Only  6/1/2020 DONE
permit extended 90 days from June 1, 2020 per Jason Blais. See DOCs
Change Expiration Date Only  5/28/2020 DONE
Telephone call  5/28/2020 DONE
emailed todd@vertical-corp.com: Your TMP for the subject permits will expire soon. Please request an extension from Jason Blais: jblais@cityofboise.org. Please provide your permit numbers and explain where you are with the draft Upgrade Agreement.
BLD-Aging Inspection5/11/20205/11/20205/11/2020 PASS
DetailsJim Storey
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
BLD-Aging Inspection3/9/20203/9/20203/9/2020 PASS
DetailsJim Storey
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
Telephone call  2/25/2020  
Spoke with Julie and she and Jason are still working with the applicant.
Meeting  2/4/2020 DONE
expiring TCO: emailed Julie and she said she and Jason are working directly with the applicant and that I need not contact them.
BLD-Aging Inspection1/6/20201/6/20201/6/2020 DEFR
DetailsJim Storey
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
BLD-Aging Inspection11/4/201911/4/201911/4/2019 DONE
DetailsJim Storey
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
BLD-Aging Inspection9/2/20199/2/20199/3/2019 PASS
DetailsJim Storey
Expires: 06/30/19 /bo expired
BLD-Conference7/2/20197/2/20197/2/2019PDONE
DetailsJim Storey
can you please verify if business has vacated building? they only have a temp c of o good to 6/30/19 Candy Phone #: ###-#### occupied
Telephone call  7/2/2019 DONE
sent inspector to verify if building was vacated since this is a temp c of o ONLY good through 6/30/19
Telephone call  7/2/2019 DONE
per Julie R- she and Jason Blais are working on a letter for this project so ok if it's expired for now-she will let me know when i need to change it
BLD-Aging Inspection6/3/20196/3/20196/3/2019 FAIL
DetailsJim Storey
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
Temporary Occupancy4/11/20197/10/20194/11/2019 DONE
DetailsCandy A. Nichols
as per Jason Blais-90 temp c of o extension was approved from 3/31/19
Plan Reviewer's activity  4/11/2019 DONE
DetailsJulie Romig
Temporary C of O extended to June 30th per Jason Blais Building Official. Email attached.
BLD-Other4/1/20194/2/20194/2/2019ADONE
DetailsJim Storey
Candy-Can you please verify if business has vacated-temp only c of o expired 3/31/19-thank you Phone #: ###-#### stil occ.Temp per plan review. Life safety passed.
BLD-Aging Inspection3/13/20193/13/20193/13/2019 PASS
DetailsJim Storey
Temp per plan review. Life safety passed.
Temporary Occupancy1/14/20194/14/20191/14/2019 DONE
DetailsCandy A. Nichols
FIRE-Final Inspection1/11/20191/11/20191/11/2019PPASS
DetailsTroy Cobbley
Permit to be finaled as per plan review
BLD-Final1/9/20191/10/20191/10/2019APASS
DetailsJim Storey
Todd Phone #: ###-#### Temp per plan review. Life safety passed.
FIRE-Final Inspection1/8/20191/9/20191/9/2019APART
DetailsTroy Cobbley
Temp per plan review. Life safety passed.

Request inspection after 10:00, please. Please call Todd 30 min prior to inspection. thx Phone #: ###-#### Inspection requested via web by Todd Weltner
BLD-Final1/7/20191/8/20191/8/2019PCANC
DetailsJim Storey
Please call Todd 15 min prior. thx Phone #: ###-#### >> Inspection requested via web by Todd Weltner Inspection cancelled from web by: Todd Weltner
FIRE-Final Inspection1/7/20191/8/20191/8/2019AFAIL
DetailsTroy Cobbley
I called contacts phone number and left message that I would be there in 15 or 20 minutes. Arrived at 3rd floor project but did not make contact. I found plans for BLD18-02699 but not other plans or any small documents. Please call Todd 15 min prior. thx Phone #: ###-#### Inspection requested via web by Todd Weltner
FIRE-Final Inspection1/4/20191/4/20191/4/2019PFAIL
DetailsJim Page
Fire sprinkler permit is still in issued status, fire sprinkler permit needs to be completed and in finaled status before life fire safety inspection can be performed as stated in past notes.

Please call Todd ahead 15 min Phone #: ###-#### Inspection requested via web by Todd Weltner
BLD-Final1/2/20191/4/20191/4/2019ACANC
DetailsJim Storey
Call before arrival // Todd Phone #: ###-#### Inspection cancelled from web by: Todd Weltner
BLD-Final1/3/20191/4/20191/4/2019PCANC
DetailsJim Storey
call 15 minutes ahead // Todd ###-#### Inspection cancelled from web by: Todd Weltner
FIRE-Final Inspection1/3/20191/4/20191/4/2019AFAIL
DetailsJim Page
Fire sprinkler inspection failed. All foil on fire sprinkler heads needs to be removed. Fire extinguisher is mount to high and is not code compliant, extinguisher needs to be lowered and tagged with a current inspection tag.

Call 15 minutes ahead // Todd Phone #: ###-####
FIRE-Final Inspection1/2/20191/3/20191/3/2019PCANC
DetailsJim Page
Tried to call point of contact provided, left voicemail stating that FIR permit for fire sprinklers is still in issued status, installing contractor for fire sprinklers has inspection scheduled for 04JAN2019, life fire safety inspection cannot be completed before FIR permit for fire sprinklers is finaled, this request is cancelled and a new inspection will need to be generated to coincide with fire sprinkler inspection.

Call before arrival // Todd Phone #: ###-####
CHANGE STATUS TO (ISS)  1/2/2019 DONE
plan mod
Plan assigned to (JAR)11/5/201811/5/201811/28/2018 DONE
DetailsJulie Romig
11/27 - 3rd Rev - Plan Mod Fifty Flowers/Law Alternatives
Routing - PLAN CHECK11/21/2018 11/28/2018 PASS
DetailsJulie Romig
Permit Ready to Issue  11/28/2018 DONE
PLAN MOD (BLD18-02699 NEEDS TO BE PAID BEFORE THIS CAN GO BACK IN ISSUE STATUS)
Routing - PLAN CHECK11/15/2018 11/15/2018 FAIL
DetailsJulie Romig
Routing - PLAN CHECK11/5/2018 11/7/2018 FAIL
DetailsJulie Romig
Plan Modification Accepted  11/5/2018 DONE
The fire wall construction at the top of the stairwell walls has been modified. r revised detail is being provided
Issue PAID IN FULL permit  10/23/2018 DONE
Print Occupancy Form  10/23/2018 DONE
Plan assigned to (JAR)10/15/201810/15/201810/19/2018 DONE
DetailsJulie Romig
10/25 - 2nd Rev - 1st Rev Comp - L1 Law Alternatives Temp CO
Routing - PLAN CHECK10/19/2018 10/19/2018 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  10/19/2018 DONE
Permit Ready to Issue  10/19/2018 DONE
MET
NEED
REVISED VALUE

MET
GC FORM
Routing - PLAN CHECK10/15/2018 10/15/2018 FAIL
DetailsJulie Romig
Pending approval of BLD18-02699
Routing - Addressing10/15/2018 10/15/2018 PASS
DetailsDoug Chausow
Suite 301
1st review completed  10/15/2018 DONE
Intake Approval  10/15/2018  
Agreement of Future work6/10/20203/4/2023   
DetailsJulie Romig
(LAW ALTERNATIVES) Upgrade Agreement attached and is due March 4, 2023. Is also tied to Building Permit BLD18-02699.
Application received 10/15/2018   
Application received 10/15/2018   
Pending Assignment by JCB10/15/2018