BLD-Final | 4/16/2019 | 4/17/2019 | 4/17/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved.
|
BLD-Final | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | NH |
Mike Jordan
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. No access. Door locked, no key pad for garage present??
|
BLD-Final | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | FAIL |
Mike Jordan
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Need mech. final. Can not verify tempered glazing in door to den.
|
BLD-Blower Door Test Results | 4/10/2019 | 4/10/2019 | 4/10/2019 | A | DONE |
Mike Jordan
|
|
|
4.6 ACH @50 pa
|
BLD-Final | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | NR |
Mike Jordan
|
|
|
Garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs mech. final.
|
BLD-Energy code compliance | 2/14/2019 | 2/15/2019 | 2/14/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 2/14/2019 | 2/15/2019 | 2/14/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 2/11/2019 | 2/13/2019 | 2/13/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Nail off 2 ply G3 flat truss per the engineering. Fireblock concealed space at ceiling next to water heater in garage. Ok to insulate. Correction notice posted.
|
BLD-Wall Bracing | 1/28/2019 | 1/29/2019 | 1/29/2019 | P | PASS |
Brandon Shaw
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 1/7/2019 | 1/7/2019 | 1/7/2019 | P | PART |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/17/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/21/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 10/22/2018 | 10/22/2018 | 11/21/2018 | | DONE |
Jenny Nelson
|
|
|
11/02 sfd L1 ePlan. 2nd review 11/1, no corrections provided with resubmittal. 1st review complete 10/31, wall bracing offsets too far
|
Routing - PLAN CHECK | 11/21/2018 | | 11/21/2018 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/21/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 11/21/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/1/2018 | | 11/1/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 10/22/2018 | | 10/31/2018 | | FAIL |
Jenny Nelson
|
|
|
|
1st review completed | | | 10/31/2018 | | FAIL |
Jenny Nelson
|
|
|
Wall bracing offsets too large on main floor
|
Routing - MECHANICAL | 10/22/2018 | | 10/25/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/22/2018 | 10/25/2018 | 10/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/22/2018 | | 10/23/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 10/22/2018 | | 10/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/22/2018 | | 10/23/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/22/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/22/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/22/2018 | | DONE |
|
|
|
|
Application received | | | 10/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 18 2018 2:28PM
|