Print Statement | | | 7/24/2019 | | DONE |
|
|
|
|
First Notice | | 6/17/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
Permanent Occupancy | | | 6/7/2019 | | DONE |
|
|
|
|
BLD-Final | 4/24/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Mike Jordan
|
|
|
Please call JP at ###-####. Phone #: ###-#### Inspection requested via web by Mattie Botero. Ok for perm occ. Plumbing has signed perm.
|
Temporary Occupancy | 3/26/2019 | 6/24/2019 | 3/26/2019 | | DONE |
Candy A. Nichols
|
|
|
|
BLD-Final | 3/22/2019 | 3/25/2019 | 3/25/2019 | A | PART |
Mike Jordan
|
|
|
Please call JP before at ###-####. Phone #: ###-#### Inspection requested via web by Mattie Botero. Ok for temp occ. Per the contractor, no mech. work needed to be completed. need plumbing final
|
FIRE-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Fire alarm is NA
Please contact Scott Hawker at ###-####. Phone #: ###-#### Inspection requested via web by Mattie Botero
|
FIRE-Alarm Testing | 3/21/2019 | 3/22/2019 | 3/21/2019 | P | CANC |
Troy Cobbley
|
|
|
Please call Scott Hawker ###-#### Phone #: ###-#### >> Inspection requested via web by Mattie Botero Inspection cancelled from web by: Mattie Botero
|
Print Occupancy Form | | | 3/19/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 2/13/2019 | 2/15/2019 | 2/15/2019 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Mattie Botero
|
BLD-Framing/Rough-in | 1/8/2019 | 1/9/2019 | 1/9/2019 | A | PASS |
Brandon Shaw
|
|
|
Please call JP at ###-####. Phone #: ###-#### Inspection requested via web by Mattie Botero
|
Issue PAID IN FULL permit | | | 12/5/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/5/2018 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/26/2018 | 10/26/2018 | 12/4/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 11/07 L2 DR. Achkerman ePlan,
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/4/2018 | | DONE |
|
|
|
MET HAWKER@MORGAN-CONSTRUCTION.COM
NEED
GC
Rev cert of val
|
Routing - PLAN CHECK | 11/30/2018 | | 12/4/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 11/30/2018 | | 12/4/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC and NFPA 99
|
Routing - PUBLIC WORKS | 11/30/2018 | | 12/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 11/30/2018 | | 12/3/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/9/2018 | 11/12/2018 | 11/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 10/26/2018 | 10/26/2018 | 11/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 11/9/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/26/2018 | | 11/8/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 10/26/2018 | | 11/5/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 10/26/2018 | | 10/30/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 10/26/2018 | | 10/26/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC and NFPA 99
|
Routing - Addressing | 10/26/2018 | | 10/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/26/2018 | | 10/26/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 10/25/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 10/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 19 2018 1:31PM
|