BLD-Final | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | NR |
Jim Storey
|
|
|
Curt Phone #: ###-#### need spk and fire final
|
BLD-Footing | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PASS |
Jim Storey
|
|
|
directions by the gas pump behind the shop // Shaun Phone #: ###-####
|
(F) Reprint permit | | | 1/17/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/15/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/15/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 11/4/2018 | 11/4/2018 | 1/10/2019 | | PASS |
Joe Bruce
|
|
|
*(3rd Rev Comp) 11/27 (L3) - Knife River (PW Streetlights)
|
Routing PW Street Lights | 1/9/2019 | | 1/10/2019 | | PASS |
Tom Marshall
|
|
|
Street lights will be tracked on BLD19-00101.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/10/2019 | | DONE |
|
|
|
all met-NEED
GC FORM-met
REVISED VALUE-met
|
Plan resubmittals received | | | 1/9/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 12/28/2018 | 12/28/2018 | 1/8/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan resubmittals requested | | | 1/8/2019 | | FAIL |
Joe Bruce
|
|
|
See comments from Public Works - Street Lighting.
|
Routing Off Site - STRUCTURAL | 12/28/2018 | | 1/4/2019 | | PASS |
Joe Bruce
|
|
|
KPFF
|
Routing PW Drainage | 12/28/2018 | | 1/3/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 12/28/2018 | | 1/3/2019 | | FAIL |
Tom Marshall
|
|
|
Need to review change mark and put the information on the drawing.
|
Plan resubmittals received | | | 12/28/2018 | | DONE |
Joe Bruce
|
|
|
Received plans in ePlan for resubmittal. **JHB**
|
Routing - FIRE | 11/4/2018 | 11/4/2018 | 12/6/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed applicant
|
Routing PW Street Lights | 12/6/2018 | | 12/6/2018 | | FAIL |
Tom Marshall
|
|
|
Street light plan needs to added to drawing AS1.1
|
Routing - PLAN CHECK | 11/4/2018 | | 11/27/2018 | | PASS |
Joe Bruce
|
|
|
|
1st review completed | | | 11/27/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 11/27/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 11/4/2018 | | 11/15/2018 | | FAIL |
Joe Bruce
|
|
|
KPFF - Cory Harelson
|
Routing - Erosion and Sediment | 11/4/2018 | | 11/13/2018 | | PASS |
Michael Zawacki
|
|
|
Small TI in industrial area.
|
Routing PW Flood Plain | 11/5/2018 | | 11/13/2018 | | PASS |
Jason C. Taylor
|
|
|
Project meets the technical requirements section (floodproof materials steel/concrete) of Boise Floodplain Ordinance (B.C.C. 11-08). No floodplain requirements necessary. If you have any questions, please call Jason Taylor at ###-####.
|
Routing PW Drainage | 11/5/2018 | | 11/6/2018 | | FAIL |
Brian Murphy
|
|
|
need drainage report
|
Routing - PLANNING | 11/4/2018 | | 11/5/2018 | | PASS |
David Moser
|
|
|
See DRH18-00372
|
Routing - Addressing | 11/4/2018 | | 11/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/4/2018 | | 11/5/2018 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 11/4/2018 | | 11/5/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00372
|
Intake Approval | | | 10/31/2018 | | PASS |
|
|
|
|
Intake Approval | | | 10/25/2018 | | FAIL |
Joe Bruce
|
|
|
Please provide the following to complete your prescreen:
1) Provide Planning and Zoning letters of approval for exterior changes to building. Since this parcel is located in a M-2D (Design Overlay District) you will need to apply for a zoning certificate or design review approval.
2) Plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” (4"x4" on cover) space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp. Electronic Submittal Standards can be found on our website: https://pds.cityofboise.org/media/464072/pdox86_electronic_standards_full_050718.pdf
|
Application received | | | 10/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2018 3:36PM
|