Third Notice | | 11/3/2019 | 11/27/2019 | | DONE |
|
|
|
mailed 12-2-19 with third and final follow up
|
Third Follow up | | | 11/27/2019 | | DONE |
|
|
|
final
|
Third Notice | | 9/23/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1 with second follow up
|
Second Follow up | | | 10/29/2019 | | DONE |
|
|
|
|
Third Notice | | 8/18/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19 with first follow up letter
|
First Follow up | | | 9/18/2019 | | DONE |
|
|
|
|
Third Notice | | 7/15/2019 | 8/13/2019 | | DONE |
|
|
|
mailed 8-13 with second follow up
|
Second Follow up | | | 8/13/2019 | | DONE |
|
|
|
|
Third Notice | | 6/12/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11 with first follow up
|
First Follow up | | | 7/10/2019 | | DONE |
|
|
|
|
Third Notice | | 5/11/2019 | 6/7/2019 | | DONE |
|
|
|
mailed 6-10
|
Second Notice | | 4/18/2019 | 5/6/2019 | | DONE |
|
|
|
mailed 5-10-19
|
First Notice | | 4/4/2019 | 4/8/2019 | | DONE |
|
|
|
mailed 4-11-19
|
Permanent Occupancy | | | 3/25/2019 | | DONE |
|
|
|
|
BLD-Final | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Dave Hannah
|
|
|
after 9:30 am please- Tami Phone #: ###-####
|
BLD-Final | 2/14/2019 | 2/19/2019 | 2/19/2019 | P | PEND |
Dave Hannah
|
|
|
Tammera Phone #: ###-#### ok for tco needs to fix some locks no door hardwear
|
FIRE-Final Inspection | 2/14/2019 | 2/15/2019 | 2/15/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags, thumbturn deadbolts on main entry doors to be replaced with double keyed deadbolts or the inside lock function will be removed so only the key function works outside to secure door, deadbolt changes to be completed before final BLD inspection. Final life fire safety inspection for area of work complete.
Tammera Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 2/14/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/14/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/31/2018 | 12/31/2018 | 2/12/2019 | | PASS |
Javier Guzman
|
|
|
1st rev comp, Plan Mod Muse Salon & Spa ePlan
|
Routing - PLAN CHECK | 2/12/2019 | | 2/12/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 2/12/2019 | | 2/12/2019 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/12/2019 | | DONE |
|
|
|
Plan mod- please do no re issue-need rev cert of val
|
Routing - PLAN CHECK | 1/7/2019 | | 1/15/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 1/7/2019 | | 1/10/2019 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 12/31/2018 | | DONE |
|
|
|
Plan mod accepted in e plan-update mechanical plans-M0.0 & M1.1-assigned to JG
|
Issue PAID IN FULL permit | | | 12/12/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/12/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/10/2018 | | DONE |
|
|
|
MET
ACHD
GC FORM
REVISED VALUE
|
Plan assigned to (JG) | 10/26/2018 | 10/26/2018 | 12/8/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 11/07 L2 MUSE SPA ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/8/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/6/2018 | | 12/7/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 12/6/2018 | | 12/7/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLAN CHECK | 11/21/2018 | | 11/27/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 11/21/2018 | | 11/26/2018 | | FAIL |
Daryl Spivey
|
|
|
Idaho State stamped set of engineered plans required for salon. resubmit showing water and all fixtures to be installed. Backwater valve to be installed to protect water closets also.
|
Routing - MECHANICAL | 11/21/2018 | | 11/26/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 11/10/2018 | 11/13/2018 | 11/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 10/26/2018 | | 11/10/2018 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 11/10/2018 | | DONE |
Javier Guzman
|
|
|
|
Routing - FIRE | 11/8/2018 | 11/8/2018 | 11/9/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLUMBING | 10/26/2018 | | 11/5/2018 | | FAIL |
Daryl Spivey
|
|
|
Failed in ePlan by Plumbing Daryl Spivey
|
Routing - MECHANICAL | 10/26/2018 | | 10/30/2018 | | FAIL |
Troy James
|
|
|
|
Routing - Addressing | 10/26/2018 | | 10/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/26/2018 | | 10/26/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 10/25/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 10/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2018 4:09PM
|