First Notice | | 11/30/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
Permanent Occupancy | | | 11/20/2018 | | DONE |
|
|
|
|
BLD-Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Storey
|
|
|
Diane Phone #: ###-####
|
FIRE-Final Inspection | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguisher will be placed in discussed location. Final life fire safety inspection for area of work complete.
Diane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/30/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/29/2018 | 11/1/2018 | 10/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (M_H) | 10/24/2018 | | 10/29/2018 | | DONE |
Michael Hanson
|
|
|
10/30 #518 L2 Paper
|
Routing - PLAN CHECK | | | 10/29/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 10/29/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2018 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 10/29/2018 | | DONE |
Michael Hanson
|
|
|
|
Print Occupancy Form | | | 10/29/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/29/2018 | | DONE |
|
|
|
Need
GC Form
|
Telephone call | | | 10/29/2018 | | DONE |
|
|
|
Left a message for Diane informing permit ready and that we need a letter from the parcel owner allowing them to act as the gc and the parcel owner needs to fill out the 302 formg
|
Plan resubmittals requested | | | 10/26/2018 | | DONE |
|
|
|
2 copies of floor plan, stamped and taked to M_H
|
Routing - PLANNING | 10/24/2018 | | 10/24/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/24/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/24/2018 | | DONE |
|
|
|
|
Application received | | 10/23/2018 | | | |
|
|
|
|